2913 W AVENEL TER 90039

Certificate Information: 2913 W AVENEL TER 90039

Application / Permit
20010-10000-00854
Plan Check / Job No.
B20LA05016
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SINGLE FAMILY RESIDENCE 3 STORY AND ATTACHED GARAGE (VTT-82869-SL) small lot subdivision
Permit Issued
Issued on 7/8/2021
Issuing Office
Current Status
CofO Issued on 7/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 SAM CHANG
Corrections Issued 4/1/2020 SAM CHANG
Quality Review Completed 4/15/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 4/24/2020 APPLICANT
Applicant returned to address corrections 7/16/2020 SAM CHANG
Applicant returned to address corrections 8/7/2020 SAM CHANG
Green Plans Picked Up 8/28/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 SAM CHANG
Applicant returned to address corrections 10/27/2020 SAM CHANG
Applicant returned to address corrections 1/29/2021 SAM CHANG
Applicant returned to address corrections 2/25/2021 SAM CHANG
Applicant returned to address corrections 4/8/2021 SAM CHANG
Plan Check Approved 4/12/2021 SAM CHANG
Plan Check Approved 7/7/2021 SAM CHANG
Issued 7/8/2021 APPLICANT
CofO in Progress 7/11/2023 ALIZAH MAYAGOITIA
CofO Issued 7/14/2023 DEROLD HAUFF
Permit Finaled 7/14/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/17/2020 ELAINE LEI
Hydrant and Access approval Cleared 8/26/2020 KURT CORRAL
Excavation more than 5-ft deep Cleared 8/27/2020 CALOSHA APPROVED
Green Code Cleared 8/28/2020 DONALD CRICHLOW
Green Code Cleared 8/28/2020 SAM CHANG
Eng Process Fee Ord 176,300 Cleared 9/2/2020 ELAINE LEI
GPI Written Notices Cleared 10/26/2020 SAM CHANG
Grading Pre-Inspection Cleared 10/26/2020 SAM CHANG
Address approval Cleared 10/28/2020 ELAINE LEI
Sewer availability Cleared 11/4/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 1/12/2021 LINDA MARGARET
BHO/Hillside ordinance Cleared 1/12/2021 LINDA MARGARET
Permit Cleared 1/12/2021 LINDA MARGARET
Roof/Waste drainage to street Cleared 1/12/2021 LINDA MARGARET
Low Impact Development Cleared 3/16/2021 ANDRES COVARRUBIAS
CPC Cleared 3/18/2021 ANACANY HURTADO
Frnt yard landscape/Water mgmt Cleared 3/18/2021 ANACANY HURTADO
Miscellaneous Cleared 3/24/2021 ANACANY HURTADO
Trees in Parkway Cleared 4/6/2021 JOHN KIM

Contact Information

Architect Gibbs,, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/29/2021 Partial Approval SCOTT FINNILA
Piling/Pier/Caisson 7/30/2021 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 8/2/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 8/19/2021 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 8/20/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 10/22/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 11/1/2021 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 11/3/2021 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 11/8/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 11/9/2021 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 11/10/2021 Partial Approval SCOTT FINNILA
Underground Mechanical 11/29/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 12/6/2021 Approved SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 12/15/2021 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 12/21/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 No Access for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Partial Approval SCOTT FINNILA
Drywall Nailing 1/6/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval SCOTT FINNILA
Deputy Wood Construction 1/21/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Steel/Welding 1/28/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 1/28/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 2/17/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 5/11/2022 Corrections Issued STUART CHAPMAN
Sewer 6/29/2022 Corrections Issued SCOTT FINNILA
Underground Mechanical 6/29/2022 Corrections Issued SCOTT FINNILA
Underground Mechanical 7/1/2022 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/28/2022 No Access for Inspection SCOTT FINNILA
ELECTRICAL-Rough 8/5/2022 Approved SCOTT FINNILA
HVAC-Rough 8/15/2022 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 8/15/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/7/2022 Partial Approval SCOTT FINNILA
Green Building Rough 9/7/2022 Partial Approval SCOTT FINNILA
MERV13>=Rough 9/7/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/14/2022 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Partial Inspection SCOTT FINNILA
Green Building Rough 9/14/2022 Approved SCOTT FINNILA
Interior/Exterior Lathing 9/14/2022 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 9/21/2022 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 9/21/2022 Partial Approval SCOTT FINNILA
Underground Mechanical 9/21/2022 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 9/26/2022 Approved SCOTT FINNILA
Insulation 9/26/2022 Not Ready for Inspection SCOTT FINNILA
Interior/Exterior Lathing 9/26/2022 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 9/26/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/29/2022 Approved SCOTT FINNILA
Insulation 9/29/2022 Approved SCOTT FINNILA
Drywall Nailing 10/5/2022 Approved SCOTT FINNILA
Interior/Exterior Lathing 10/5/2022 Partial Approval SCOTT FINNILA
Shower Pan 10/13/2022 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 10/25/2022 Approved SCOTT FINNILA
Shower Pan 10/25/2022 Approved SCOTT FINNILA
HVAC-Final 2/16/2023 No Access for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 2/16/2023 No Access for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 3/8/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 3/22/2023 Approved ALIZAH MAYAGOITIA
Service/Power Release 3/23/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 4/20/2023 Approved ALIZAH MAYAGOITIA
Final 4/20/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 4/20/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 4/20/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 4/20/2023 Approved ALIZAH MAYAGOITIA
Reinforced Concrete Frame 4/20/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 4/20/2023 Approved ALIZAH MAYAGOITIA
Final 5/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 5/10/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/10/2023 Approved ALIZAH MAYAGOITIA
Final 6/21/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 7/11/2023 OK to Issue CofO ALIZAH MAYAGOITIA