2913 W AVENEL TER 90039
Certificate Information: 2913 W AVENEL TER 90039
- Application / Permit
- 20010-10000-00854
- Plan Check / Job No.
- B20LA05016
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SINGLE FAMILY RESIDENCE 3 STORY AND ATTACHED GARAGE (VTT-82869-SL) small lot subdivision
- Permit Issued
- Issued on 7/8/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SAM CHANG |
| Corrections Issued | 4/1/2020 | SAM CHANG |
| Quality Review Completed | 4/15/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| Applicant returned to address corrections | 7/16/2020 | SAM CHANG |
| Applicant returned to address corrections | 8/7/2020 | SAM CHANG |
| Green Plans Picked Up | 8/28/2020 | APPLICANT |
| Applicant returned to address corrections | 10/6/2020 | SAM CHANG |
| Applicant returned to address corrections | 10/27/2020 | SAM CHANG |
| Applicant returned to address corrections | 1/29/2021 | SAM CHANG |
| Applicant returned to address corrections | 2/25/2021 | SAM CHANG |
| Applicant returned to address corrections | 4/8/2021 | SAM CHANG |
| Plan Check Approved | 4/12/2021 | SAM CHANG |
| Plan Check Approved | 7/7/2021 | SAM CHANG |
| Issued | 7/8/2021 | APPLICANT |
| CofO in Progress | 7/11/2023 | ALIZAH MAYAGOITIA |
| CofO Issued | 7/14/2023 | DEROLD HAUFF |
| Permit Finaled | 7/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/17/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 8/26/2020 | KURT CORRAL |
| Excavation more than 5-ft deep | Cleared | 8/27/2020 | CALOSHA APPROVED |
| Green Code | Cleared | 8/28/2020 | DONALD CRICHLOW |
| Green Code | Cleared | 8/28/2020 | SAM CHANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2020 | ELAINE LEI |
| GPI Written Notices | Cleared | 10/26/2020 | SAM CHANG |
| Grading Pre-Inspection | Cleared | 10/26/2020 | SAM CHANG |
| Address approval | Cleared | 10/28/2020 | ELAINE LEI |
| Sewer availability | Cleared | 11/4/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 1/12/2021 | LINDA MARGARET |
| BHO/Hillside ordinance | Cleared | 1/12/2021 | LINDA MARGARET |
| Permit | Cleared | 1/12/2021 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 1/12/2021 | LINDA MARGARET |
| Low Impact Development | Cleared | 3/16/2021 | ANDRES COVARRUBIAS |
| CPC | Cleared | 3/18/2021 | ANACANY HURTADO |
| Frnt yard landscape/Water mgmt | Cleared | 3/18/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 3/24/2021 | ANACANY HURTADO |
| Trees in Parkway | Cleared | 4/6/2021 | JOHN KIM |
Contact Information
| Architect | Gibbs,, Kurt Robert; Lic. No.: C22275 | 3575 LONG BEACH BLVD LONG BEACH, CA 90807 |
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Geologist | Hill,, Thomas George; Lic. No.: EG1100 | 3210 VAL VERDE LONG BEACH, CA 90808 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 7/29/2021 | Partial Approval | SCOTT FINNILA |
| Piling/Pier/Caisson | 7/30/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 8/2/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/19/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 8/20/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/22/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/1/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 11/3/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 11/8/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/9/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 11/10/2021 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 11/29/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/6/2021 | Approved | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/15/2021 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 12/21/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | No Access for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 1/6/2022 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 1/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 1/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/17/2022 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 5/11/2022 | Corrections Issued | STUART CHAPMAN |
| Sewer | 6/29/2022 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 6/29/2022 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 7/1/2022 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 7/28/2022 | No Access for Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/5/2022 | Approved | SCOTT FINNILA |
| HVAC-Rough | 8/15/2022 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 8/15/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/7/2022 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 9/7/2022 | Partial Approval | SCOTT FINNILA |
| MERV13>=Rough | 9/7/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/14/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 9/14/2022 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 9/14/2022 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/21/2022 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 9/21/2022 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 9/21/2022 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/26/2022 | Approved | SCOTT FINNILA |
| Insulation | 9/26/2022 | Not Ready for Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 9/26/2022 | Partial Approval | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 9/26/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | SCOTT FINNILA |
| Insulation | 9/29/2022 | Approved | SCOTT FINNILA |
| Drywall Nailing | 10/5/2022 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 10/5/2022 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 10/13/2022 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 10/25/2022 | Approved | SCOTT FINNILA |
| Shower Pan | 10/25/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 2/16/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/16/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/8/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/22/2023 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/23/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 4/20/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 4/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Reinforced Concrete Frame | 4/20/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/20/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/10/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/10/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/10/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/21/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 7/11/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |