12869 N NORRIS AVE 91342
Certificate Information: 12869 N NORRIS AVE 91342
- Application / Permit
- 20010-10000-00823
- Plan Check / Job No.
- B20LA04786
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW 18' x18', 2-CAR CARPORT IN REAR OF PROPERTY PER IB P/BC 2017-009
- Permit Issued
- Issued on 3/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | SAM CHANG |
| Corrections Issued | 3/12/2020 | SAM CHANG |
| Plan Check Approved | 3/13/2020 | SHANGQIN XIE |
| Issued | 3/20/2020 | LADBS |
| CofO in Progress | 2/7/2022 | JOHN HAYES |
| No Progress | 2/12/2022 | MICHAEL TEMPLE |
| CofO in Progress | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
| CofO Issued | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/13/2020 | ELENA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2021 | Approved | JOHN HAYES |
| Piling/Pier/Caisson | 9/14/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/7/2021 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Approved | JOHN HAYES |
| Final | 12/10/2021 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 12/10/2021 | Not Required | JOHN HAYES |
| Smoke Detectors | 12/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/7/2022 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 2/7/2022 | Approved | JOHN HAYES |