11502 W CALVERT ST 91606

Certificate Information: 11502 W CALVERT ST 91606

Application / Permit
20010-10000-00796
Plan Check / Job No.
B20LA04653
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY (1173 SQ FT) ADU PER ORDINANCE
Permit Issued
Issued on 9/26/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/27/2020 CRYSTEL MAALOUF
Corrections Issued 4/2/2020 CRYSTEL MAALOUF
Quality Review Completed 4/13/2020 BILL STUTSMAN
Building Plans Picked Up 4/24/2020 APPLICANT
Green Plans Picked Up 5/4/2020 APPLICANT
Applicant returned to address corrections 8/7/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 8/13/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 9/4/2020 CRYSTEL MAALOUF
Plan Check Approved 9/8/2020 CRYSTEL MAALOUF
Issued 9/26/2024 APPLICANT
CofO in Progress 5/19/2025 JOSE AVILA
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Green Code Cleared 5/11/2020 KHEDER ALRAZAA
Address approval Cleared 6/3/2020 ADRIAN CASTRO
Sewer availability Cleared 6/9/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/22/2020 ADRIAN CASTRO
Construction near power lines Cleared 8/9/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 8/20/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/21/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/25/2020 ADRIAN CASTRO
Stormwater Pollution Mitigatn Cleared 8/25/2020 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/23/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/28/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 10/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/13/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/11/2024 Corrections Issued JOSE AVILA
HVAC-Rough 12/11/2024 Conditional Approval JOSE AVILA
PLUMBING-Rough 12/11/2024 Approved JOSE AVILA
Deputy Drilled-In Anchors 12/13/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 12/17/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/17/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/17/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 12/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/19/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 12/23/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 12/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 1/6/2025 Approved JOSE AVILA
Drywall Nailing 1/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/23/2025 Approved RAUL OLAGI
Gas Test 4/15/2025 Approved JOSE AVILA
HVAC-Rough 4/15/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 4/15/2025 Approved JOSE AVILA
ELECTRICAL-Final 5/16/2025 Approved JOSE AVILA
Final 5/16/2025 OK to Issue CofO JOSE AVILA
Green Building Final 5/16/2025 Approved JOSE AVILA
HVAC-Final 5/16/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Approved JOSE AVILA
Service/Power Release 5/16/2025 Approved JOSE AVILA
Smoke Detectors 5/16/2025 Approved JOSE AVILA