11502 W CALVERT ST 91606
Certificate Information: 11502 W CALVERT ST 91606
- Application / Permit
- 20010-10000-00796
- Plan Check / Job No.
- B20LA04653
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY (1173 SQ FT) ADU PER ORDINANCE
- Permit Issued
- Issued on 9/26/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 4/2/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/13/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| Green Plans Picked Up | 5/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/7/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/13/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/4/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/8/2020 | CRYSTEL MAALOUF |
| Issued | 9/26/2024 | APPLICANT |
| CofO in Progress | 5/19/2025 | JOSE AVILA |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
| CofO Issued | 8/28/2025 | RUBEN SALAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Green Code | Cleared | 5/11/2020 | KHEDER ALRAZAA |
| Address approval | Cleared | 6/3/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 8/9/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 8/20/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/21/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/25/2020 | ADRIAN CASTRO |
| Stormwater Pollution Mitigatn | Cleared | 8/25/2020 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/23/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/28/2024 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 10/29/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 10/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/13/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 11/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 12/11/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 12/11/2024 | Conditional Approval | JOSE AVILA |
| PLUMBING-Rough | 12/11/2024 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/13/2024 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/17/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 12/17/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 12/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/19/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 12/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 12/30/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 12/30/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 12/30/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 1/6/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 1/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 1/23/2025 | Approved | RAUL OLAGI |
| Gas Test | 4/15/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 4/15/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 4/15/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 5/16/2025 | Approved | JOSE AVILA |
| Final | 5/16/2025 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 5/16/2025 | Approved | JOSE AVILA |
| HVAC-Final | 5/16/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 5/16/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 5/16/2025 | Approved | JOSE AVILA |