1612 W TORRANCE BLVD 90501
Certificate Information: 1612 W TORRANCE BLVD 90501
- Application / Permit
- 20010-10000-00785
- Plan Check / Job No.
- B20LA04557
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD OVER BASEMENT GARAGE. (3 OF 3)
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Metro
- Current Status
- Issued on 5/20/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 4/24/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/18/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/22/2020 | CRYSTEL MAALOUF |
| Green Plans Picked Up | 9/24/2020 | APPLICANT |
| Applicant returned to address corrections | 6/8/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/21/2021 | CRYSTEL MAALOUF |
| Building Plans Picked Up | 2/22/2022 | APPLICANT |
| Plan Check Approved | 5/20/2022 | CRYSTEL MAALOUF |
| Issued | 5/20/2022 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 9/1/2020 | DONALD CRICHLOW |
| Tract Map conditions | Cleared | 10/26/2020 | KENTON TRINH |
| Hydrant and Access approval | Cleared | 11/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/29/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/15/2021 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 7/30/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/30/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/30/2021 | RIDWAN HARDY |
| Address approval | Cleared | 8/2/2021 | CHINH DINH |
| Sewer availability | Cleared | 8/2/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | CHINH DINH |
Contact Information
| Contractor | R M G Engineering Inc; Lic. No.: 1000744-B | 8845 IRON HITCH AVE LAS VEGAS, NV 89143 |
| Engineer | Roan,, Oliver J H; Lic. No.: S3173 | 9778 EL DURANGO CIRCLE FOUNTAIN VALLEY, CA 92708 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/29/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 8/2/2022 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/13/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/30/2023 | Approved | JOHN KLARIN |
| Reinforced Concrete Frame | 1/30/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/25/2023 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 5/31/2023 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 6/2/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Corrections Issued | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 8/2/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/8/2023 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 8/15/2023 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 3/20/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 4/10/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 5/20/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 8/29/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/17/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/21/2024 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 10/21/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/14/2024 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/14/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 11/14/2024 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 11/14/2024 | Approved | EUGENE CASSIDY |
| Deck | 2/3/2025 | Partial Approval | EUGENE CASSIDY |
| Insulation | 2/3/2025 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/3/2025 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 2/3/2025 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/3/2025 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 7/7/2025 | Approved | EUGENE CASSIDY |