2142 W MARATHON ST 90026

Certificate Information: 2142 W MARATHON ST 90026

Application / Permit
20010-10000-00761
Plan Check / Job No.
B20LA04306
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FOR (N) 3-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/27/2021
Issuing Office
Metro
Current Status
CofO Issued on 3/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ADAM HEGAZI
Corrections Issued 3/25/2020 ADAM HEGAZI
Quality Review Completed 4/1/2020 YOUNG KIM
Green Plans Picked Up 6/11/2020 APPLICANT
Plan Check Approved 1/15/2021 ADAM HEGAZI
Issued 1/27/2021 APPLICANT
Building Plans Picked Up 2/1/2021 APPLICANT
CofO in Progress 2/27/2023 FREDDIE RIVERA
Permit Finaled 3/10/2023 DEROLD HAUFF
CofO Issued 3/10/2023 DEROLD HAUFF
Permit Finaled 3/10/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/30/2020 PATRICK MISCHLICH
Address approval Cleared 5/5/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/15/2020 CELINA MORENO
Sewer availability Cleared 5/20/2020 CELINA MORENO
Green Code Cleared 6/11/2020 DONALD CRICHLOW
Low Impact Development Cleared 10/20/2020 ROBIN YAMADA
Frnt yard landscape/Water mgmt Cleared 11/5/2020 JASON CHAN
Hydrant and Access approval Cleared 11/10/2020 KURT CORRAL
Roof/Waste drainage to street Cleared 11/10/2020 JEANIE LAM

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor True Vision Development Inc; Lic. No.: 1047713-B 1332 W PARADE STREET      LONG BEACH, CA 90810
Engineer Hakemi,, Fahim; Lic. No.: S5160 26982 MARBELLA      MISSION VIEJO, CA 92691
Engineer Wright,, Adam Ruck; Lic. No.: C31016 2400 VISTA HOGAR      NEWPORT BEACH, CA 926604043

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/12/2021 No Access for Inspection RUBEN SALAS
Underground Mechanical 3/18/2021 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 4/5/2021 Not Ready for Inspection ROBERT VORHIS
Deputy Reinf. Concrete 4/6/2021 Conditional Approval ROBERT VORHIS
Footing/Foundation/Slab 4/13/2021 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval ROBERT VORHIS
ELECTRICAL-Rough 8/20/2021 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Partial Inspection ROBERT VORHIS
HVAC-Rough 8/20/2021 Not Ready for Inspection ROBERT VORHIS
PLUMBING-Rough 8/20/2021 Not Ready for Inspection ROBERT VORHIS
PLUMBING-Rough 9/20/2021 Not Ready for Inspection ALAN MORELOS
Sewer 9/20/2021 Approved ALAN MORELOS
HVAC-Rough 9/23/2021 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 9/23/2021 Approved ROBERT VORHIS
HVAC-Rough 10/14/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval ROBERT VORHIS
Interior/Exterior Lathing 11/9/2021 Partial Approval ADAM ESCOTO
BUILDING-Rough-Frame 11/15/2021 Corrections Issued ROBERT VORHIS
Green Building Rough 11/15/2021 Approved ROBERT VORHIS
Interior/Exterior Lathing 11/15/2021 Partial Approval ROBERT VORHIS
Shower Pan 11/15/2021 Approved ROBERT VORHIS
Verify Sprinkler Sign Off 11/15/2021 Approved ROBERT VORHIS
BUILDING-Rough-Frame 11/23/2021 Approved ROBERT VORHIS
Insulation 12/1/2021 Approved ADAM ESCOTO
Drywall Nailing 12/9/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/9/2021 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 1/7/2022 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/2/2022 Approved ADAM ESCOTO
Final 10/28/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 10/28/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved FREDDIE RIVERA
Service/Power Release 10/28/2022 Partial Inspection FREDDIE RIVERA
Smoke Detectors 10/28/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/30/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 12/2/2022 Approved BRENDAN MORELLI
ELECTRICAL-Final 12/5/2022 Approved FREDDIE RIVERA
Final 2/7/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 2/7/2023 Partial Inspection FREDDIE RIVERA
Service/Power Release 2/7/2023 Partial Inspection FREDDIE RIVERA
Final 2/15/2023 Conditional Approval FREDDIE RIVERA
Green Building Final 2/15/2023 Approved FREDDIE RIVERA
Service/Power Release 2/15/2023 Approved FREDDIE RIVERA
Final 2/27/2023 OK to Issue CofO FREDDIE RIVERA