Pre-Inspection
|
8/17/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
9/10/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
9/13/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
9/17/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
9/20/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
9/28/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/28/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
9/28/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
9/28/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
9/30/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/30/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
9/30/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
9/30/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/6/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/6/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/6/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
10/6/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/6/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/7/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/7/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/8/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/20/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
10/20/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/20/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
11/1/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/2/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/1/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
12/6/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
1/4/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
1/5/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
1/11/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/11/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
2/1/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
2/4/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
2/23/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
2/23/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
2/23/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/1/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
3/2/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
3/4/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
3/4/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
3/4/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
3/10/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/11/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
3/14/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
3/30/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/30/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/1/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
4/4/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/18/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
4/19/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/12/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
5/16/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
5/20/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/6/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
6/7/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Pre-Inspection
|
6/10/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
6/28/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/28/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
7/7/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
7/20/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
7/21/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
8/2/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/3/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
8/30/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
8/30/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
8/31/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
8/31/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
9/1/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
9/1/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
9/13/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Drywall Nailing
|
9/20/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
9/21/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
9/27/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
10/4/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
10/4/2022
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
10/6/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
10/7/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
10/29/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
1/12/2023
|
Corrections Issued
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/1/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/17/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Final
|
5/16/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
5/16/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Final
|
5/16/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
5/16/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
5/16/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
5/16/2023
|
Approved
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
5/16/2023
|
SGSOV Not Ready
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
5/16/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
5/16/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
5/16/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
10/31/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Final
|
10/31/2023
|
Approved
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
10/31/2023
|
SGSOV Approved
|
EDWIN GREGORYONA
|
|
Final
|
12/14/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
5/29/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
7/18/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Final
|
8/19/2024
|
OK to Issue CofO
|
EDWIN GREGORYONA
|