726 S WILTON PL 90005

Certificate Information: 726 S WILTON PL 90005

Application / Permit
20010-10000-00740
Plan Check / Job No.
B20LA04240
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 6 STORY APARTMENT BUILDING (R-2), 25 UNITS OVER A PARKING GARAGE ON GRADE (S-2). TOC TIER 3, WITH 3 EXTREMELY LOW INCOME, 1 VERY LOW INCOME, 1 LOW INCOME UNIT.
Permit Issued
Issued on 7/14/2021
Issuing Office
Metro
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ARMEN JIVALAGIAN
Corrections Issued 4/1/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 4/1/2020 APPLICANT
Quality Review Completed 4/6/2020 TIEN JEN WANG
Applicant returned to address corrections 4/7/2020 SAM CHANG
Applicant returned to address corrections 7/10/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/28/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/21/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/28/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/16/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/19/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/24/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/7/2021 ARMEN JIVALAGIAN
Green Plans Picked Up 3/11/2021 APPLICANT
Disabled Access Plans Picked Up 3/22/2021 APPLICANT
Applicant returned to address corrections 6/24/2021 ARMEN JIVALAGIAN
Plan Check Approved 7/7/2021 ARMEN JIVALAGIAN
Issued 7/14/2021 APPLICANT
TCO Issued (Expire Date: 06-15-2024) 12/18/2023 ADAM BURGESS
CofO in Progress 8/21/2024 EDWIN GREGORYONA
CofO Issued 8/26/2024 ERNESTO CORRAL
Permit Finaled 8/26/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 5/26/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 5/26/2020 RENZ SORIANO
DCP conditions approval Cleared 6/9/2020 NICHOLAS KAWAZOE
Density Bonus 12.22.A.31 Cleared 6/9/2020 NICHOLAS KAWAZOE
Highway dedication Cleared 6/17/2020 RENZ SORIANO
Building over 3-story or 36-ft Cleared 6/18/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 6/18/2020 CALOSHA APPROVED
Trees in Parkway Cleared 7/13/2020 JOHN KIM
Construction near power lines Cleared 7/20/2020 RIDWAN HARDY
Construction within easement Cleared 7/20/2020 RIDWAN HARDY
Sewer availability Cleared 8/26/2020 ELAINE LEI
Hydrant and Access approval Cleared 10/7/2020 KURT CORRAL
DAS Clearance Cleared 11/5/2020 ARMEN JIVALAGIAN
Fire Marshall Fire Life Safety Cleared 2/9/2021 MENOA AGHAJANI
Green Code Cleared 2/26/2021 ARMEN JIVALAGIAN
Low Impact Development Cleared 3/12/2021 ORVAL HERNANDEZ-MARCI
Permit Cleared 3/16/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 3/16/2021 ROSA SILVA
Miscellaneous Cleared 5/17/2021 KENTON TRINH
Miscellaneous Cleared 5/17/2021 KENTON TRINH
Frnt yard landscape/Water mgmt Cleared 5/18/2021 KENTON TRINH
Miscellaneous Cleared 5/18/2021 KENTON TRINH
Miscellaneous Cleared 5/18/2021 KENTON TRINH
Opn space landscape/Water mgmt Cleared 5/18/2021 KENTON TRINH

Contact Information

Architect Bittoni,, Mark Christopher; Lic. No.: C34136 434 N GREENCRAIG ROAD      LOS ANGELES, CA 90049
Contractor Category Construction Llc; Lic. No.: 1041679-B 8271 MELROSE AVE #207      LOS ANGELES, CA 90046
Engineer Melnyk,, Matthew John; Lic. No.: S5853 527 WEST 7TH ST STE 701      LOS ANGELES, CA 90014
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 1453 14TH ST STE A      SANTA MONICA, CA 90404

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/17/2021 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 9/10/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/13/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/17/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 9/20/2021 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 9/28/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/28/2021 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 9/28/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 9/28/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 9/30/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/30/2021 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 9/30/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 9/30/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 10/6/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/6/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/6/2021 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 10/6/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/6/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 10/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/8/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/20/2021 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 10/20/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/20/2021 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 11/1/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/2/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/1/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 12/6/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 1/4/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 1/5/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/11/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/11/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/4/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 2/23/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 2/23/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/23/2022 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/2/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 3/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 3/4/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 3/10/2022 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/30/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/4/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/19/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/16/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/20/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 6/7/2022 Conditional Approval ERNESTO CORRAL
Pre-Inspection 6/10/2022 Approved EDWIN GREGORYONA
Deputy Wood Construction 6/28/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/20/2022 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 7/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/2/2022 Conditional Approval WINSTON DUNNING
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 8/30/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 8/30/2022 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 8/31/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 8/31/2022 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 9/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 9/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/13/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 9/20/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 9/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 9/27/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/4/2022 Partial Approval GREGORY POMISH
Drywall Nailing 10/4/2022 Partial Approval JAMES POWERS
Drywall Nailing 10/6/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 10/7/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/29/2022 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 1/12/2023 Corrections Issued EDWIN GREGORYONA
Light Gage Steel Frame 3/1/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/17/2023 Partial Approval EDWIN GREGORYONA
Final 5/16/2023 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 5/16/2023 Approved EDWIN GREGORYONA
Green Building Final 5/16/2023 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 5/16/2023 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 5/16/2023 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 5/16/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 5/16/2023 Approved EDWIN GREGORYONA
Special/Order Compliance 5/16/2023 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/16/2023 Approved EDWIN GREGORYONA
Final 10/31/2023 Partial Inspection EDWIN GREGORYONA
Green Building Final 10/31/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved EDWIN GREGORYONA
Final 12/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Special/Order Compliance 5/29/2024 Approved EDWIN GREGORYONA
Final 7/18/2024 Partial Inspection EDWIN GREGORYONA
Final 8/19/2024 OK to Issue CofO EDWIN GREGORYONA