4422-4424 S WILTON PL 90018
Certificate Information: 4422-4424 S WILTON PL 90018
- Application / Permit
- 20010-10000-00734
- Plan Check / Job No.
- B20LA04215
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 6/30/2020
- Issuing Office
- Current Status
- CofO Issued on 12/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 3/23/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 4/13/2020 | KESETE HAREGOT |
| Green Plans Picked Up | 6/3/2020 | APPLICANT |
| Applicant returned to address corrections | 6/18/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 6/25/2020 | SERGIO GUTIERREZ |
| Issued | 6/30/2020 | APPLICANT |
| Building Plans Picked Up | 7/2/2020 | APPLICANT |
| CofO in Progress | 12/3/2020 | ROBERT MCDOWELL |
| Permit Finaled | 12/15/2020 | RONALD MYRICK |
| CofO Issued | 12/15/2020 | RONALD MYRICK |
| Permit Finaled | 12/15/2020 | RONALD MYRICK |
Permit Application Clearance Information
| Green Code | Cleared | 6/1/2020 | NEGAR NEJAD |
| Low Impact Development | Cleared | 6/11/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/12/2020 | RENZ SORIANO |
| Frnt yard landscape/Water mgmt | Cleared | 6/15/2020 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 6/18/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 6/19/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 6/19/2020 | JUAN ASHTON |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2020 | Approved | ROBERT MCDOWELL |
| Deputy Reinf. Concrete | 7/15/2020 | Conditional Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 7/22/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2020 | Partial Approval | ROBERT MCDOWELL |
| Insulation | 7/23/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 9/15/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 9/15/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 9/15/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 9/15/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 9/15/2020 | Approved | ROBERT MCDOWELL |
| Rough-Elec/Plmb/HVAC | 9/15/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 9/15/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 9/16/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Insulation | 9/18/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 10/2/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 10/2/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 12/3/2020 | Approved | ROBERT MCDOWELL |
| Final | 12/3/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 12/3/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 12/3/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 12/3/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 12/3/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 12/3/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 12/3/2020 | Approved | ROBERT MCDOWELL |