10401 W WASHINGTON BLVD 90232

Certificate Information: 10401 W WASHINGTON BLVD 90232

Application / Permit
20010-10000-00723
Plan Check / Job No.
B20LA04173
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
Construction of 8-story mixed-use building. 5-stories of Type III-A, 112-unit, affordable housing Apartment over 3-levels of Type I-A parking and ground floor commercial over 1-level of subterranean parking as an addition to the exisiting 4-story, 33-unit apartment building. 15 units are set aside for extremely low income households, and 2,000 square feet of ground floor commercial uses. TOC w/ base and additional incentives.
Permit Issued
Issued on 10/25/2021
Issuing Office
Metro
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 QUAN NGHIEM
Corrections Issued 6/24/2021 QUAN NGHIEM
Quality Review Completed 6/24/2021 ALLEN MANALANSAN
Plan Check Approved 10/22/2021 QUAN NGHIEM
Issued 10/25/2021 APPLICANT
TCO Issued (Expire Date: 09-20-2025) 3/24/2025 ERNESTO CORRAL
CofO in Progress 4/22/2025 DERRICK SPENCER
Permit Finaled 4/22/2025 HENRY BAGHDASSARIAN
CofO Issued 4/22/2025 HENRY BAGHDASSARIAN
Permit Finaled 4/22/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Building over 36-ft Cleared 3/30/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/30/2021 CALOSHA APPROVED
Eng Process Fee Ord 176,300 Cleared 4/15/2021 RAYMOND MUGAMBWA
Address approval Cleared 5/3/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/11/2021 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 5/13/2021 MATTHEW CRAIG
Highway dedication Cleared 5/25/2021 RAYMOND MUGAMBWA
Permit Cleared 5/25/2021 RAYMOND MUGAMBWA
Miscellaneous Cleared 6/2/2021 JENSON LEE
DCP conditions approval Cleared 8/26/2021 NGHIEM TRAN
Density Bonus 12.22.A.31 Cleared 8/26/2021 NGHIEM TRAN
Low Impact Development Cleared 9/3/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/3/2021 DINAH GARIN
Work Adjacent to Public Way Cleared 9/13/2021 SAUL GARCIA
Fire Marshall Fire Life Safety Cleared 9/30/2021 OSCAR SALGADO JR
DAS Clearance Cleared 10/12/2021 SHINE LIN
APC Cleared 10/13/2021 MAXFIELD VERMY
Frnt yard landscape/Water mgmt Cleared 10/13/2021 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 10/13/2021 MAXFIELD VERMY
Site Plan review Cleared 10/13/2021 MAXFIELD VERMY

Contact Information

Architect Abramson,, Trevor David; Lic. No.: C17597 8924 LINDBLADE STREET      CULVER CITY, CA 90232
Contractor C L G Construction Inc; Lic. No.: 969926-B 10600 SANTA MONICA BLVD      LOS ANGELES, CA 90025
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/3/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/3/2022 Partial Approval JEFF BYTHEWAY
METHANE-Barrier 2/3/2022 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 2/3/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Concrete 2/4/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/17/2022 Partial Approval DERRICK SPENCER
METHANE-Barrier 2/17/2022 Partial Approval DERRICK SPENCER
METHANE-Subgrade 2/17/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/18/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 2/23/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 2/23/2022 Partial Approval DERRICK SPENCER
METHANE-Barrier 2/23/2022 Partial Approval DERRICK SPENCER
METHANE-Subgrade 2/23/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/24/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/3/2022 Approved DERRICK SPENCER
Green Building Rough 3/3/2022 Approved DERRICK SPENCER
METHANE-Rough 3/3/2022 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 3/3/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/4/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/10/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/11/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/15/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/16/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/17/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/18/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/21/2022 Approved DERRICK SPENCER
METHANE-Rough 3/21/2022 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 3/21/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/22/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/22/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/23/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/23/2022 Approved DERRICK SPENCER
Deputy Shotcrete 3/24/2022 Approved DERRICK SPENCER
METHANE-Rough 3/25/2022 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 3/25/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/29/2022 Approved DERRICK SPENCER
Deputy Methane Barrier 5/2/2022 Approved DERRICK SPENCER
Deputy Methane Barrier 5/3/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 5/4/2022 Approved DERRICK SPENCER
Deputy Methane Barrier 5/4/2022 Approved DERRICK SPENCER
Deputy Methane Barrier 5/5/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 5/6/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 5/6/2022 Partial Approval DERRICK SPENCER
METHANE-Barrier 5/6/2022 Approved DERRICK SPENCER
METHANE-Subgrade 5/6/2022 Approved DERRICK SPENCER
METHANE-Rough 5/17/2022 Not Ready for Inspection NICK LAROCCA
Reinforced Masonry Frame 5/17/2022 Partial Inspection NICK LAROCCA
METHANE-Rough 6/1/2022 Approved NICK LAROCCA
Reinforced Concrete Frame 6/1/2022 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 6/7/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/8/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/8/2022 Conditional Approval DERRICK SPENCER
Deputy Shotcrete 6/14/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/15/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/16/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/17/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/21/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/21/2022 Partial Approval DERRICK SPENCER
Deputy Shotcrete 6/22/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/23/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/24/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/27/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/28/2022 Approved DERRICK SPENCER
Structural Steel Frame 6/28/2022 Partial Approval DERRICK SPENCER
T-Bar Ceiling 6/28/2022 Not Ready for Inspection DERRICK SPENCER
Wall Anchors 6/28/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/29/2022 Approved DERRICK SPENCER
Deputy Shotcrete 6/30/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/30/2022 Partial Approval DERRICK SPENCER
Deputy Shotcrete 7/1/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 7/5/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/5/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 7/6/2022 Approved DERRICK SPENCER
Interior/Exterior Lathing 7/7/2022 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/11/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/8/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 8/18/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 8/26/2022 Approved DERRICK SPENCER
Masonry Wall/Backfill 8/29/2022 Partial Approval DERRICK SPENCER
Piling/Pier/Caisson 8/29/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/30/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/31/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 8/31/2022 Approved DERRICK SPENCER
Deputy Other (see comments) 9/1/2022 Approved DERRICK SPENCER
Deputy Other (see comments) 9/7/2022 Approved DERRICK SPENCER
Deputy Shotcrete 9/7/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 10/11/2022 Approved DERRICK SPENCER
Reinforced Concrete Frame 10/12/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 10/18/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 10/21/2022 Partial Approval DERRICK SPENCER
Deputy Other (see comments) 10/25/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 11/1/2022 Approved NICK LAROCCA
Reinforced Concrete Frame 11/1/2022 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 11/3/2022 Approved NICK LAROCCA
Special/Order Compliance 11/15/2022 Approved NICK LAROCCA
Deputy Reinf. Concrete 12/19/2022 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 12/20/2022 Partial Inspection NICK LAROCCA
Structural Steel Frame 12/20/2022 Not Ready for Inspection NICK LAROCCA
Deputy Reinf. Concrete 12/22/2022 Approved GRANT WOODS
Deputy Reinf. Concrete 12/23/2022 Approved GRANT WOODS
Deputy Reinf. Concrete 1/12/2023 Approved DERRICK SPENCER
Drywall Nailing 1/26/2023 Corrections Issued NICK LAROCCA
Deputy Wood Construction 1/27/2023 Approved NICK LAROCCA
Structural Steel Frame 1/27/2023 Partial Inspection NICK LAROCCA
Special/Order Compliance 2/2/2023 Corrections Issued NICK LAROCCA
Deputy Reinf. Concrete 2/10/2023 Approved NICK LAROCCA
Deputy Wood Construction 2/10/2023 Approved NICK LAROCCA
Footing/Foundation/Slab 2/10/2023 Not Ready for Inspection NICK LAROCCA
Special/Order Compliance 2/10/2023 Partial Inspection NICK LAROCCA
Masonry Wall/Backfill 2/13/2023 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 2/14/2023 Partial Approval NICK LAROCCA
Deputy Wood Construction 3/3/2023 Approved NICK LAROCCA
Deputy Fireproofing 3/7/2023 Approved NICK LAROCCA
Wood Frame 3/8/2023 Partial Inspection NICK LAROCCA
Deputy Wood Construction 3/9/2023 Approved NICK LAROCCA
Deputy Fireproofing 3/15/2023 Approved NICK LAROCCA
Deputy Fireproofing 3/29/2023 Approved NICK LAROCCA
Deputy Wood Construction 3/31/2023 Approved NICK LAROCCA
Wood Frame 4/7/2023 Not Ready for Inspection NICK LAROCCA
Deputy Wood Construction 4/11/2023 Approved NICK LAROCCA
Deputy Wood Construction 4/12/2023 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 4/13/2023 Approved NICK LAROCCA
Deputy Steel/Welding 4/17/2023 Approved NICK LAROCCA
Wood Frame 5/2/2023 Partial Approval NICK LAROCCA
Light Gage Steel Frame 5/19/2023 Partial Inspection NICK LAROCCA
Wood Frame 5/31/2023 Partial Approval NICK LAROCCA
Wood Frame 6/1/2023 Partial Inspection NICK LAROCCA
Deputy Reinf. Masonry 6/6/2023 Conditional Approval ALAN NOVAK
Wood Frame 6/29/2023 Partial Approval ALAN NOVAK
Insulation 7/12/2023 Partial Approval ALAN NOVAK
Deputy Wood Construction 7/19/2023 Approved NICK LAROCCA
Wood Frame 8/9/2023 Partial Approval NICK LAROCCA
Insulation 8/24/2023 Partial Approval ALAN NOVAK
Wood Frame 8/30/2023 Partial Approval ALAN NOVAK
Wood Frame 9/5/2023 Partial Approval ALAN NOVAK
Wood Frame 9/21/2023 No Access for Inspection ALAN NOVAK
Wood Frame 9/25/2023 Partial Approval NICK LAROCCA
Insulation 9/29/2023 Partial Approval NICK LAROCCA
Wood Frame 10/2/2023 Partial Approval ALAN NOVAK
Deputy Wood Construction 10/3/2023 Conditional Approval ALAN NOVAK
Wood Frame 10/10/2023 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 10/11/2023 Partial Inspection NICK LAROCCA
Insulation 10/20/2023 Partial Approval ALAN NOVAK
Drywall Nailing 11/3/2023 Partial Approval NICK LAROCCA
Insulation 11/8/2023 Partial Approval NICK LAROCCA
Insulation 11/9/2023 Partial Approval ALAN NOVAK
Drywall Nailing 11/28/2023 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 11/28/2023 Not Ready for Inspection NICK LAROCCA
Interior/Exterior Lathing 11/30/2023 Partial Inspection NICK LAROCCA
Drywall Nailing 12/1/2023 Partial Approval ALAN NOVAK
Interior/Exterior Lathing 12/1/2023 Partial Approval ALAN NOVAK
Pre-Inspection 12/1/2023 Approved ALAN NOVAK
Pre-Inspection 12/5/2023 Approved ALAN NOVAK
Insulation 12/8/2023 Partial Approval ALAN NOVAK
Insulation 12/14/2023 Partial Approval ALAN NOVAK
Pre-Inspection 12/19/2023 Approved ALAN NOVAK
Drywall Nailing 12/21/2023 Partial Approval ALAN NOVAK
Pre-Inspection 12/28/2023 Not Ready for Inspection NICK LAROCCA
Interior/Exterior Lathing 1/4/2024 Approved NICK LAROCCA
Wood Frame 1/4/2024 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 1/8/2024 Partial Approval NICK LAROCCA
Pre-Inspection 1/10/2024 Approved ALAN NOVAK
Pre-Inspection 1/16/2024 Not Ready for Inspection ALAN NOVAK
Insulation 1/19/2024 Order to Comply Issued ALAN NOVAK
Insulation 2/9/2024 Partial Approval ALAN NOVAK
Pre-Inspection 2/27/2024 Partial Inspection PAUL DAVIDSON
Insulation 3/1/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 4/1/2024 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 4/1/2024 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 4/5/2024 Partial Approval PAUL DAVIDSON
Special/Order Compliance 4/10/2024 Partial Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 4/16/2024 Partial Approval DERRICK SPENCER
Pre-Inspection 4/24/2024 Partial Inspection PAUL DAVIDSON
Deputy Drilled-In Anchors 5/9/2024 Conditional Approval PAUL DAVIDSON
Insulation 5/31/2024 Partial Inspection RICARDO ROBLES
Deputy Reinf. Concrete 6/3/2024 Conditional Approval PAUL DAVIDSON
Reinforced Concrete Frame 6/4/2024 Partial Approval PAUL DAVIDSON
Interior/Exterior Lathing 7/3/2024 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 7/16/2024 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 7/25/2024 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 8/19/2024 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/20/2024 Approved ALAN NOVAK
Pre-Inspection 8/30/2024 Approved DERRICK SPENCER
Light Gage Steel Frame 10/2/2024 Partial Approval DERRICK SPENCER
Green Building Final 3/18/2025 Approved PAUL DAVIDSON
Special/Order Compliance 3/19/2025 Corrections Issued PAUL DAVIDSON
Final 3/21/2025 OK for TCO PAUL DAVIDSON
Footing/Foundation/Slab 3/21/2025 Approved PAUL DAVIDSON
Reinforced Concrete Frame 3/21/2025 Approved PAUL DAVIDSON
Reinforced Masonry Frame 3/21/2025 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 3/21/2025 Approved PAUL DAVIDSON
Final 3/27/2025 Not Ready for Inspection PAUL DAVIDSON
Final 4/2/2025 OK to Issue CofO DERRICK SPENCER