Deputy Reinf. Concrete
|
2/3/2022
|
Approved
|
JEFF BYTHEWAY
|
|
Footing/Foundation/Slab
|
2/3/2022
|
Partial Approval
|
JEFF BYTHEWAY
|
|
METHANE-Barrier
|
2/3/2022
|
Not Ready for Inspection
|
JEFF BYTHEWAY
|
|
METHANE-Subgrade
|
2/3/2022
|
Not Ready for Inspection
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Concrete
|
2/4/2022
|
Approved
|
JEFF BYTHEWAY
|
|
Footing/Foundation/Slab
|
2/17/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
METHANE-Barrier
|
2/17/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
METHANE-Subgrade
|
2/17/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
2/18/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
2/23/2022
|
Approved
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
2/23/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
METHANE-Barrier
|
2/23/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
METHANE-Subgrade
|
2/23/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
2/24/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
3/3/2022
|
Approved
|
DERRICK SPENCER
|
|
Green Building Rough
|
3/3/2022
|
Approved
|
DERRICK SPENCER
|
|
METHANE-Rough
|
3/3/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
3/3/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
3/4/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/10/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/11/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/15/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/16/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/17/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/18/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/21/2022
|
Approved
|
DERRICK SPENCER
|
|
METHANE-Rough
|
3/21/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
3/21/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
3/22/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/22/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
3/23/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/23/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
3/24/2022
|
Approved
|
DERRICK SPENCER
|
|
METHANE-Rough
|
3/25/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
3/25/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
3/29/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Methane Barrier
|
5/2/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Methane Barrier
|
5/3/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
5/4/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Methane Barrier
|
5/4/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Methane Barrier
|
5/5/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
5/6/2022
|
Approved
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
5/6/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
METHANE-Barrier
|
5/6/2022
|
Approved
|
DERRICK SPENCER
|
|
METHANE-Subgrade
|
5/6/2022
|
Approved
|
DERRICK SPENCER
|
|
METHANE-Rough
|
5/17/2022
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Reinforced Masonry Frame
|
5/17/2022
|
Partial Inspection
|
NICK LAROCCA
|
|
METHANE-Rough
|
6/1/2022
|
Approved
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
6/1/2022
|
Partial Approval
|
NICK LAROCCA
|
|
Footing/Foundation/Slab
|
6/7/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
6/8/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
6/8/2022
|
Conditional Approval
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/14/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/15/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/16/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/17/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/21/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/22/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/23/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/24/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/27/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/28/2022
|
Approved
|
DERRICK SPENCER
|
|
Structural Steel Frame
|
6/28/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
T-Bar Ceiling
|
6/28/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Wall Anchors
|
6/28/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/29/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
6/30/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
6/30/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
7/1/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
7/5/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
7/6/2022
|
Approved
|
DERRICK SPENCER
|
|
Interior/Exterior Lathing
|
7/7/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
7/11/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
8/8/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
8/18/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Masonry
|
8/26/2022
|
Approved
|
DERRICK SPENCER
|
|
Masonry Wall/Backfill
|
8/29/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Piling/Pier/Caisson
|
8/29/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
8/30/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
8/31/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Masonry
|
8/31/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Other (see comments)
|
9/1/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Other (see comments)
|
9/7/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Shotcrete
|
9/7/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
10/11/2022
|
Approved
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
10/12/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
10/18/2022
|
Approved
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
10/21/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Other (see comments)
|
10/25/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
11/1/2022
|
Approved
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
11/1/2022
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
11/3/2022
|
Approved
|
NICK LAROCCA
|
|
Special/Order Compliance
|
11/15/2022
|
Approved
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
12/19/2022
|
Conditional Approval
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
12/20/2022
|
Partial Inspection
|
NICK LAROCCA
|
|
Structural Steel Frame
|
12/20/2022
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
12/22/2022
|
Approved
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
12/23/2022
|
Approved
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
1/12/2023
|
Approved
|
DERRICK SPENCER
|
|
Drywall Nailing
|
1/26/2023
|
Corrections Issued
|
NICK LAROCCA
|
|
Deputy Wood Construction
|
1/27/2023
|
Approved
|
NICK LAROCCA
|
|
Structural Steel Frame
|
1/27/2023
|
Partial Inspection
|
NICK LAROCCA
|
|
Special/Order Compliance
|
2/2/2023
|
Corrections Issued
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
2/10/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Wood Construction
|
2/10/2023
|
Approved
|
NICK LAROCCA
|
|
Footing/Foundation/Slab
|
2/10/2023
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Special/Order Compliance
|
2/10/2023
|
Partial Inspection
|
NICK LAROCCA
|
|
Masonry Wall/Backfill
|
2/13/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
2/14/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Wood Construction
|
3/3/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Fireproofing
|
3/7/2023
|
Approved
|
NICK LAROCCA
|
|
Wood Frame
|
3/8/2023
|
Partial Inspection
|
NICK LAROCCA
|
|
Deputy Wood Construction
|
3/9/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Fireproofing
|
3/15/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Fireproofing
|
3/29/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Wood Construction
|
3/31/2023
|
Approved
|
NICK LAROCCA
|
|
Wood Frame
|
4/7/2023
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Deputy Wood Construction
|
4/11/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Wood Construction
|
4/12/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Steel/Welding
|
4/13/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Steel/Welding
|
4/17/2023
|
Approved
|
NICK LAROCCA
|
|
Wood Frame
|
5/2/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Light Gage Steel Frame
|
5/19/2023
|
Partial Inspection
|
NICK LAROCCA
|
|
Wood Frame
|
5/31/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Wood Frame
|
6/1/2023
|
Partial Inspection
|
NICK LAROCCA
|
|
Deputy Reinf. Masonry
|
6/6/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Wood Frame
|
6/29/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Insulation
|
7/12/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Wood Construction
|
7/19/2023
|
Approved
|
NICK LAROCCA
|
|
Wood Frame
|
8/9/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Insulation
|
8/24/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Wood Frame
|
8/30/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Wood Frame
|
9/5/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Wood Frame
|
9/21/2023
|
No Access for Inspection
|
ALAN NOVAK
|
|
Wood Frame
|
9/25/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Insulation
|
9/29/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Wood Frame
|
10/2/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Wood Construction
|
10/3/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Wood Frame
|
10/10/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Interior/Exterior Lathing
|
10/11/2023
|
Partial Inspection
|
NICK LAROCCA
|
|
Insulation
|
10/20/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Drywall Nailing
|
11/3/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Insulation
|
11/8/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Insulation
|
11/9/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Drywall Nailing
|
11/28/2023
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Pre-Inspection
|
11/28/2023
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Interior/Exterior Lathing
|
11/30/2023
|
Partial Inspection
|
NICK LAROCCA
|
|
Drywall Nailing
|
12/1/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Interior/Exterior Lathing
|
12/1/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Pre-Inspection
|
12/1/2023
|
Approved
|
ALAN NOVAK
|
|
Pre-Inspection
|
12/5/2023
|
Approved
|
ALAN NOVAK
|
|
Insulation
|
12/8/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Insulation
|
12/14/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Pre-Inspection
|
12/19/2023
|
Approved
|
ALAN NOVAK
|
|
Drywall Nailing
|
12/21/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Pre-Inspection
|
12/28/2023
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Interior/Exterior Lathing
|
1/4/2024
|
Approved
|
NICK LAROCCA
|
|
Wood Frame
|
1/4/2024
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Pre-Inspection
|
1/8/2024
|
Partial Approval
|
NICK LAROCCA
|
|
Pre-Inspection
|
1/10/2024
|
Approved
|
ALAN NOVAK
|
|
Pre-Inspection
|
1/16/2024
|
Not Ready for Inspection
|
ALAN NOVAK
|
|
Insulation
|
1/19/2024
|
Order to Comply Issued
|
ALAN NOVAK
|
|
Insulation
|
2/9/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Pre-Inspection
|
2/27/2024
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Insulation
|
3/1/2024
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
4/1/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Light Gage Steel Frame
|
4/1/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Light Gage Steel Frame
|
4/5/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
4/10/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/16/2024
|
Partial Approval
|
DERRICK SPENCER
|
|
Pre-Inspection
|
4/24/2024
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Deputy Drilled-In Anchors
|
5/9/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Insulation
|
5/31/2024
|
Partial Inspection
|
RICARDO ROBLES
|
|
Deputy Reinf. Concrete
|
6/3/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Reinforced Concrete Frame
|
6/4/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Interior/Exterior Lathing
|
7/3/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Light Gage Steel Frame
|
7/16/2024
|
Not Ready for Inspection
|
PAUL DAVIDSON
|
|
Light Gage Steel Frame
|
7/25/2024
|
Not Ready for Inspection
|
PAUL DAVIDSON
|
|
Light Gage Steel Frame
|
8/19/2024
|
Partial Approval
|
DERRICK SPENCER
|
|
Light Gage Steel Frame
|
8/20/2024
|
Approved
|
ALAN NOVAK
|
|
Pre-Inspection
|
8/30/2024
|
Approved
|
DERRICK SPENCER
|
|
Light Gage Steel Frame
|
10/2/2024
|
Partial Approval
|
DERRICK SPENCER
|
|
Green Building Final
|
3/18/2025
|
Approved
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
3/19/2025
|
Corrections Issued
|
PAUL DAVIDSON
|
|
Final
|
3/21/2025
|
OK for TCO
|
PAUL DAVIDSON
|
|
Footing/Foundation/Slab
|
3/21/2025
|
Approved
|
PAUL DAVIDSON
|
|
Reinforced Concrete Frame
|
3/21/2025
|
Approved
|
PAUL DAVIDSON
|
|
Reinforced Masonry Frame
|
3/21/2025
|
Approved
|
PAUL DAVIDSON
|
|
SGSOV-Seismic Gas S/O Valve
|
3/21/2025
|
SGSOV Approved
|
PAUL DAVIDSON
|
|
Smoke Detectors
|
3/21/2025
|
Approved
|
PAUL DAVIDSON
|
|
Final
|
3/27/2025
|
Not Ready for Inspection
|
PAUL DAVIDSON
|
|
Final
|
4/2/2025
|
OK to Issue CofO
|
DERRICK SPENCER
|