9532-9534 S GRAHAM AVE 90002

Certificate Information: 9532-9534 S GRAHAM AVE 90002

Application / Permit
20010-10000-00700
Plan Check / Job No.
B20LA04017
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 1 STORY DUPLEX WITH ATTACHED GARAGE
Permit Issued
Issued on 12/15/2021
Issuing Office
Current Status
CofO Issued on 2/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2020 APPLICANT
Green Plans Picked Up 3/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 FERNANDO FLORES
Corrections Issued 3/26/2020 FERNANDO FLORES
Quality Review Completed 4/1/2020 STANLEY RAAP
Plan Check Approved 12/13/2021 FERNANDO FLORES
Issued 12/15/2021 APPLICANT
Building Plans Picked Up 12/17/2021 APPLICANT
CofO in Progress 2/26/2024 BEN MOLSTAD
Permit Finaled 2/26/2024 ANSON MAGLASANG
CofO Issued 2/26/2024 ANSON MAGLASANG
Permit Finaled 2/26/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/26/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/26/2021 JEANIE LAM
Permit Cleared 7/26/2021 JEANIE LAM
Sewer availability Cleared 7/26/2021 JEANIE LAM
Trees in Parkway Cleared 8/12/2021 JOHN KIM
Hydrant and Access approval Cleared 9/11/2021 JOHN CONNEALLY
Low Impact Development Cleared 11/22/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 12/6/2021 KHOUNG LE
Green Code Cleared 12/13/2021 FERNANDO FLORES
Metro Rail approval Cleared 12/13/2021 EDDI ZEPEDA

Contact Information

Contractor Kashmal Group Of America Inc; Lic. No.: 592828-B 2100 SOUTH FIGUEROA #326      LOS ANGELES, CA 90007
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/27/2022 Partial Approval JOHN KLARIN
Sewer 4/27/2022 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 5/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/19/2022 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 5/20/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/20/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 10/3/2022 Partial Approval ALIZAH MAYAGOITIA
Wood Frame 10/3/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/17/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 10/17/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 10/17/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/17/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 10/17/2022 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 10/17/2022 Approved ALIZAH MAYAGOITIA
Insulation 10/21/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 10/21/2022 Approved JOHN KLARIN
Drywall Nailing 10/26/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/28/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Final 2/28/2023 Corrections Issued JOHN KLARIN
Final 2/28/2023 Corrections Issued JOHN KLARIN
Green Building Final 2/28/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 2/28/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Not Ready JOHN KLARIN
Service/Power Release 2/28/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 2/28/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 2/28/2023 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 6/5/2023 Approved JOHN KLARIN
Final 6/5/2023 Corrections Issued JOHN KLARIN
Green Building Final 6/5/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/5/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 6/5/2023 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 6/5/2023 Approved JOHN KLARIN
ELECTRICAL-Final 10/4/2023 Approved JOHN KLARIN
Final 10/4/2023 Corrections Issued JOHN KLARIN
HVAC-Final 10/4/2023 Approved JOHN KLARIN
PLUMBING-Final 10/4/2023 Approved JOHN KLARIN
Service/Power Release 10/4/2023 Not Ready for Inspection JOHN KLARIN
Final 2/20/2024 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 2/20/2024 Not Ready for Inspection BEN MOLSTAD
Final 2/23/2024 OK to Issue CofO BEN MOLSTAD
Service/Power Release 2/23/2024 Approved BEN MOLSTAD