9532-9534 S GRAHAM AVE 90002
Certificate Information: 9532-9534 S GRAHAM AVE 90002
- Application / Permit
- 20010-10000-00700
- Plan Check / Job No.
- B20LA04017
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 1 STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2020 | APPLICANT |
| Green Plans Picked Up | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | FERNANDO FLORES |
| Corrections Issued | 3/26/2020 | FERNANDO FLORES |
| Quality Review Completed | 4/1/2020 | STANLEY RAAP |
| Plan Check Approved | 12/13/2021 | FERNANDO FLORES |
| Issued | 12/15/2021 | APPLICANT |
| Building Plans Picked Up | 12/17/2021 | APPLICANT |
| CofO in Progress | 2/26/2024 | BEN MOLSTAD |
| Permit Finaled | 2/26/2024 | ANSON MAGLASANG |
| CofO Issued | 2/26/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/26/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | JEANIE LAM |
| Permit | Cleared | 7/26/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/26/2021 | JEANIE LAM |
| Trees in Parkway | Cleared | 8/12/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/11/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/22/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | KHOUNG LE |
| Green Code | Cleared | 12/13/2021 | FERNANDO FLORES |
| Metro Rail approval | Cleared | 12/13/2021 | EDDI ZEPEDA |
Contact Information
| Contractor | Kashmal Group Of America Inc; Lic. No.: 592828-B | 2100 SOUTH FIGUEROA #326 LOS ANGELES, CA 90007 |
| Engineer | Gorgy,, Moheb Shohdy; Lic. No.: C53260 | 1545 VICTORY BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/27/2022 | Partial Approval | JOHN KLARIN |
| Sewer | 4/27/2022 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 5/13/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/20/2022 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/20/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/3/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 10/3/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/17/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 10/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 10/21/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/21/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 10/26/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/28/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Final | 2/28/2023 | Corrections Issued | JOHN KLARIN |
| Final | 2/28/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 2/28/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 2/28/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 2/28/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 2/28/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 2/28/2023 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/5/2023 | Approved | JOHN KLARIN |
| Final | 6/5/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/5/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 6/5/2023 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 6/5/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 10/4/2023 | Approved | JOHN KLARIN |
| Final | 10/4/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 10/4/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 10/4/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 10/4/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 2/20/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 2/20/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 2/23/2024 | OK to Issue CofO | BEN MOLSTAD |
| Service/Power Release | 2/23/2024 | Approved | BEN MOLSTAD |