15275 W LAKESIDE ST 91342

Certificate Information: 15275 W LAKESIDE ST 91342

Application / Permit
20010-10000-00688
Plan Check / Job No.
B20LA03977
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Patio Cover
Work Description
1 NEW FABRIC SHADE STRUCTURES AT CITY PARK 30' X 60', 1800 SQ FT 3 OF 5
Permit Issued
Issued on 11/18/2020
Issuing Office
Current Status
Issued on 11/18/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 ERIC WONG
Corrections Issued 4/1/2020 ERIC WONG
Quality Review Completed 4/1/2020 KEN GILL
Disabled Access Plans Picked Up 4/16/2020 APPLICANT
Building Plans Picked Up 4/21/2020 APPLICANT
Applicant returned to address corrections 10/19/2020 ERIC WONG
Applicant returned to address corrections 10/22/2020 ERIC WONG
Plan Check Approved 11/4/2020 ERIC WONG
Issued 11/18/2020 APPLICANT

Permit Application Clearance Information

Green Code Cleared 3/12/2020 KHEDER ALRAZAA
City owned building/parcel Cleared 5/19/2020 HAROOT AVANESIAN
Address approval Cleared 6/5/2020 ADRIAN CASTRO
Low Impact Development Cleared 6/5/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/5/2020 ADRIAN CASTRO
Sewer availability Cleared 6/5/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/9/2020 ADRIAN CASTRO
Green Code Cleared 8/6/2020 ERIC WONG
DAS Clearance Cleared 9/3/2020 CHOI YAN

Contact Information

Contractor Shade Structures Inc; Lic. No.: 989458-B P O BOX 3467      COPELL, TX 75019
Engineer Santo, Domingo, Catalina Magno; Lic. No.: C57608 424 AUDRAINE DR      GLENDALE, CA 91202

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2021 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/19/2021 Partial Approval DANNY RODRIGUEZ
Final 9/21/2021 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 9/21/2021 Conditional Approval DANNY RODRIGUEZ
Green Building Final 9/21/2021 Approved DANNY RODRIGUEZ
Green Building Rough 9/21/2021 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/21/2021 SGSOV No Gas DANNY RODRIGUEZ
Smoke Detectors 9/21/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/21/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 9/21/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 9/30/2021 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 9/30/2021 Not Ready for Inspection DANNY RODRIGUEZ
Smoke Detectors 9/30/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/30/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 9/30/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 3/11/2022 Conditional Approval DANNY RODRIGUEZ
Final 3/23/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/23/2022 Approved DANNY RODRIGUEZ
Smoke Detectors 3/23/2022 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/23/2022 Approved DANNY RODRIGUEZ
Wood Frame 3/23/2022 Approved DANNY RODRIGUEZ