Piling/Pier/Caisson
|
11/8/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Reinf. Concrete
|
11/10/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Piling/Pier/Caisson
|
11/10/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Deputy Reinf. Concrete
|
11/18/2021
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Steel/Welding
|
1/6/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
3/16/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Drilled-In Anchors
|
3/17/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Drilled-In Anchors
|
3/18/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Drilled-In Anchors
|
4/14/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Drilled-In Anchors
|
4/15/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
4/15/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Reinf. Concrete
|
4/19/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Shotcrete
|
4/22/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
4/26/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Drilled-In Anchors
|
7/25/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Reinf. Concrete
|
7/25/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Drilled-In Anchors
|
7/26/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Reinf. Concrete
|
7/26/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
7/28/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Reinf. Concrete
|
8/2/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/26/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Drywall Nailing
|
9/30/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/11/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
11/18/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
11/28/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/7/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/22/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
12/30/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/6/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/23/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/3/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
2/15/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Drilled-In Anchors
|
2/22/2023
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/22/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/31/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
4/13/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/18/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/16/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/16/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Insulation
|
6/16/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/27/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/5/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Insulation
|
7/11/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
7/24/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
Verify Sprinkler Sign Off
|
7/24/2023
|
Approved
|
BRENDAN MORELLI
|
|
Wood Frame
|
7/24/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
Green Building Rough
|
7/31/2023
|
Approved
|
BRENDAN MORELLI
|
|
Wood Frame
|
7/31/2023
|
Approved
|
BRENDAN MORELLI
|
|
Interior/Exterior Lathing
|
8/14/2023
|
Partial Approval
|
BRENDAN MORELLI
|
|
Insulation
|
8/15/2023
|
Approved
|
BRENDAN MORELLI
|
|
Drywall Nailing
|
9/14/2023
|
Approved
|
BRENDAN MORELLI
|
|
Interior/Exterior Lathing
|
9/28/2023
|
Approved
|
BRENDAN MORELLI
|
|
Footing/Foundation/Slab
|
3/20/2024
|
Approved
|
BRENDAN MORELLI
|
|
Verify Rec and Parks Fee Memo
|
4/26/2024
|
Approved
|
BRENDAN MORELLI
|
|
Special/Order Compliance
|
3/19/2025
|
Corrections Issued
|
BRENDAN MORELLI
|
|
Final
|
10/10/2025
|
Corrections Issued
|
BRENDAN MORELLI
|
|
Green Building Final
|
10/10/2025
|
Approved
|
BRENDAN MORELLI
|
|
SGSOV-Seismic Gas S/O Valve
|
10/10/2025
|
SGSOV Not Required
|
BRENDAN MORELLI
|
|
Smoke Detectors
|
10/10/2025
|
Approved
|
BRENDAN MORELLI
|
|
Final
|
12/3/2025
|
Corrections Issued
|
NICHOLAS LOPEZ
|
|
Final
|
4/6/2026
|
OK to Issue CofO
|
NICHOLAS LOPEZ
|