1318 W CANNON DR 90026
Certificate Information: 1318 W CANNON DR 90026
- Application / Permit
- 20010-10000-00666
- Plan Check / Job No.
- B20LA03963
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 3 STORY SINGLE FAMILY DWELLING PER VTT-78277-SL (LOT 3) SMALL LOT SUBDIVISION PURSUANT TO VTT 78277-SL. CERT. OF OCC. SHALL NOT BE ISSUED UNTIL AFTER FINAL MAP HAS BEEN RECORDED.
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/10/2020 | LAWRENCE QUIRANTE |
| Quality Review Completed | 4/15/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 5/7/2020 | APPLICANT |
| Applicant returned to address corrections | 9/23/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 9/24/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 9/29/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 10/1/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/6/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/16/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 1/29/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 2/2/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 2/24/2021 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 3/12/2021 | APPLICANT |
| Applicant returned to address corrections | 3/18/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 3/23/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 5/5/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 5/7/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 9/17/2021 | LAWRENCE QUIRANTE |
| Issued | 9/20/2021 | APPLICANT |
| CofO in Progress | 4/9/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 4/10/2026 | DEROLD HAUFF |
| CofO Issued | 4/10/2026 | DEROLD HAUFF |
| Permit Finaled | 4/10/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | THOMAS LANG |
| Sewer availability | Cleared | 10/1/2020 | THOMAS LANG |
| Grading Pre-Inspection | Cleared | 10/15/2020 | LAWRENCE QUIRANTE |
| Tract Map conditions | Cleared | 10/21/2020 | RUBEN VASQUEZ |
| Green Code | Cleared | 11/2/2020 | LAWRENCE QUIRANTE |
| Hydrant and Access approval | Cleared | 11/16/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/14/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/21/2021 | WALLIE JONG |
| Miscellaneous | Cleared | 9/15/2021 | LINDA MARGARET |
Contact Information
| Architect | Garrison,, John Clark; Lic. No.: C16833 | 3100 BRISTOL STREET SUITE 400 COSTA MESA, CA 92626 |
| Contractor | Joseph P Development Corporation; Lic. No.: 988764-B | 4210 RIVERWALK PARKWAY #270 RIVERSIDE, CA 92505 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Tosounian,, Oshin Bedros; Lic. No.: S3730 | 7136 HASKELL AVE STE 301 VAN NUYS, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/24/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 9/30/2022 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/18/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/23/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/29/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/10/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Insulation | 3/8/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 4/18/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 4/21/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 4/21/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 7/10/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/19/2023 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 7/19/2023 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 7/19/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Wood Frame | 7/28/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 8/8/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 8/11/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 9/12/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 9/21/2023 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/20/2024 | Approved | BRENDAN MORELLI |
| Verify Rec and Parks Fee Memo | 4/26/2024 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 3/19/2025 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/6/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Final | 9/15/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 9/15/2025 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 9/15/2025 | Approved | BRENDAN MORELLI |
| Final | 10/8/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 4/8/2026 | OK to Issue CofO | NICHOLAS LOPEZ |