1328 1/2 E 33RD ST 90011

Certificate Information: 1328 1/2 E 33RD ST 90011

Application / Permit
20010-10000-00650
Plan Check / Job No.
B20LA03907
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 894SQ.FT DETACHED ACCESSARY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) AT REAR.
Permit Issued
Issued on 5/7/2021
Issuing Office
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 RAHEL BEYENE
Corrections Issued 3/25/2020 RAHEL BEYENE
Quality Review Completed 4/1/2020 STANLEY RAAP
Applicant returned to address corrections 6/9/2020 RAHEL BEYENE
Green Plans Picked Up 6/16/2020 APPLICANT
Plan Check Approved 2/4/2021 RAHEL BEYENE
Issued 5/7/2021 APPLICANT
Building Plans Picked Up 6/3/2021 APPLICANT
CofO in Progress 8/2/2024 ALEJANDRO DE ARTOLA
Permit Finaled 9/3/2024 RUBEN SALAS
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Historic Resource Verification Cleared 5/27/2020 MICAELA TORRES-GIL
Green Code Cleared 6/1/2020 VIVIAN LAO
Redevelopment Project Area Cleared 7/9/2020 GRACIELA ACOSTA
Address approval Cleared 7/13/2020 JEANIE LAM
Permit Cleared 7/13/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/14/2020 JEANIE LAM
Sewer availability Cleared 7/14/2020 JEANIE LAM
Hydrant and Access approval Cleared 8/12/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/13/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/10/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 3129 S HACIENDA BL STE 524      HACIENDA HEIGHTS, CA 91745

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2021 Corrections Issued ANTHONY EGSON
Service/Power Release 11/3/2021 Not Ready for Inspection ANTHONY EGSON
Sewer 11/3/2021 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 11/24/2021 Corrections Issued ADAM ESCOTO
Sewer 11/24/2021 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 11/30/2021 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/3/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 2/3/2022 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 2/9/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/9/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 4/4/2022 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 6/7/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 6/7/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/24/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 8/24/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 8/24/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 9/6/2022 Approved SHAVONNE ESPINOZA
PLUMBING-Rough 9/6/2022 Not Ready for Inspection SHAVONNE ESPINOZA
PLUMBING-Rough 9/8/2022 Approved RYAN SALAZAR
Insulation 9/12/2022 Corrections Issued SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/14/2022 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 9/14/2022 Approved FREDDIE RIVERA
Insulation 9/14/2022 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 9/14/2022 Approved FREDDIE RIVERA
Drywall Nailing 9/19/2022 Partial Approval SHAVONNE ESPINOZA
Green Building Rough 9/19/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Rough 9/28/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 6/12/2023 Approved BRENDAN MORELLI
Drywall Nailing 6/12/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 6/12/2023 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 6/12/2023 Approved BRENDAN MORELLI
Green Building Final 6/12/2023 Approved BRENDAN MORELLI
HVAC-Final 6/12/2023 Corrections Issued BRENDAN MORELLI
Reinforced Concrete Frame 6/12/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 6/12/2023 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 6/12/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
PLUMBING-Final 11/7/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/21/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 12/4/2023 Approved ALEJANDRO DE ARTOLA
Final 6/17/2024 No Access for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Not Ready DAVID FEILER
Service/Power Release 6/17/2024 No Access for Inspection DAVID FEILER
Final 6/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/20/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 6/20/2024 Approved ALEJANDRO DE ARTOLA
Final 6/28/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Final 7/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/30/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Final 8/1/2024 OK to Issue CofO ALEJANDRO DE ARTOLA