2230 N MEADOWVALE AVE 90031

Certificate Information: 2230 N MEADOWVALE AVE 90031

Application / Permit
20010-10000-00617
Plan Check / Job No.
B20LA03733
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED (N) DETACHED 1148 SF TWO-STORY ACCESSORY DWELLING UNIT W/ROOF TOP DECK PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 RAHEL BEYENE
Corrections Issued 3/17/2020 RAHEL BEYENE
Quality Review Completed 3/21/2020 STANLEY RAAP
Green Plans Picked Up 9/11/2020 APPLICANT
Applicant returned to address corrections 9/30/2020 RAHEL BEYENE
Building Plans Picked Up 10/8/2020 APPLICANT
Applicant returned to address corrections 1/27/2021 RAHEL BEYENE
Plan Check Approved 1/29/2021 RAHEL BEYENE
Issued 3/12/2021 APPLICANT
CofO in Progress 2/8/2023 THOMAS LOGRASSO
Permit Finaled 2/14/2023 DEROLD HAUFF
CofO Issued 2/14/2023 DEROLD HAUFF
Permit Finaled 2/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/29/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 4/30/2020 JUAN ASHTON
Sewer availability Cleared 4/30/2020 JUAN ASHTON
ZI Cleared 5/15/2020 RICHARD REASER
Hydrant and Access approval Cleared 7/16/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 7/22/2020 WALLIE JONG
Low Impact Development Cleared 8/25/2020 SARAH YOUSSEF
Green Code Cleared 9/9/2020 RAHEL BEYENE

Contact Information

Contractor D C L A Design Build Inc; Lic. No.: 1060451-B 712 N BONNIE BRAE ST      LOS ANGELES, CA 90026
Engineer Lin,, Jason K; Lic. No.: S6095 900 N SANTA ANITA AVE STE B      ARCADIA, CA 91006

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/27/2021 Conditional Approval THOMAS LOGRASSO
Special/Order Compliance 12/27/2021 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 1/20/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 1/27/2022 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 3/2/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval KATHRYN BUTTERWORTH
Deputy Wood Construction 8/2/2022 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 8/23/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 8/23/2022 Corrections Issued THOMAS LOGRASSO
Green Building Rough 8/23/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 8/23/2022 Corrections Issued THOMAS LOGRASSO
MERV13>=Rough 8/23/2022 Approved THOMAS LOGRASSO
PLUMBING-Rough 8/23/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 8/30/2022 Approved THOMAS LOGRASSO
Green Building Rough 8/30/2022 Not Ready for Inspection THOMAS LOGRASSO
Insulation 9/7/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 9/7/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 9/16/2022 Approved THOMAS LOGRASSO
Green Building Rough 9/16/2022 Approved THOMAS LOGRASSO
Insulation 9/16/2022 Approved THOMAS LOGRASSO
Drywall Nailing 9/21/2022 Approved THOMAS LOGRASSO
Green Building Rough 9/21/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 9/21/2022 Approved THOMAS LOGRASSO
Shower Pan 9/21/2022 Approved THOMAS LOGRASSO
Final 1/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 1/9/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 1/9/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 1/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 1/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 1/19/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 1/19/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 1/19/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 1/19/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 1/19/2023 Approved THOMAS LOGRASSO
Final 2/7/2023 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 2/7/2023 Approved THOMAS LOGRASSO
MERV13>=Final 2/7/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 2/7/2023 Approved THOMAS LOGRASSO