1233 S DUNSMUIR AVE 90019
Certificate Information: 1233 S DUNSMUIR AVE 90019
- Application / Permit
- 20010-10000-00598
- Plan Check / Job No.
- B20LA03671
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 4-story Type VA, 17-unit, Apartment with 1 VLI unit & ELI unit and 1-level of Type IA basement parking.
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Issued | 11/8/2021 | APPLICANT |
| TCO Issued (Expire Date: 08-21-2024) | 2/23/2024 | WINSTON DUNNING |
| TCO Issued (Expire Date: 02-04-2025) | 8/8/2024 | ERNESTO CORRAL |
| CofO in Progress | 4/1/2025 | EDWIN GREGORYONA |
| CofO Issued | 4/1/2025 | ERNESTO CORRAL |
| Permit Finaled | 4/1/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2020 | THOMAS LANG |
| Highway dedication | Cleared | 12/22/2020 | THOMAS LANG |
| Permit | Cleared | 12/22/2020 | THOMAS LANG |
| Encroachment in public way | Cleared | 1/19/2021 | ELAINE LEI |
| Trees in Parkway | Cleared | 3/31/2021 | JOHN KIM |
| Sewer availability | Cleared | 4/30/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2021 | RENZ SORIANO |
| Green Code | Cleared | 5/12/2021 | DEAN LEE |
| Density Bonus 12.22.A.31 | Cleared | 6/8/2021 | JAMES MCCARTHY |
| Fire Marshall Fire Life Safety | Cleared | 6/22/2021 | VIDAL GARCIA |
| Hydrant and Access approval | Cleared | 6/22/2021 | KURT CORRAL |
| DAS Clearance | Cleared | 7/22/2021 | DEAN LEE |
| Excavation more than 5-ft deep | Cleared | 8/26/2021 | CALOSHA APPROVED |
| Building over 36-ft | Cleared | 8/30/2021 | CALOSHA APPROVED |
| ZA Case | Cleared | 9/9/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/9/2021 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 9/10/2021 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | THOMAS LANG |
| Opn space landscape/Water mgmt | Cleared | 9/16/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/16/2021 | RUBEN VASQUEZ |
Contact Information
| Architect | Andrew, G Crane; Lic. No.: C34124 | 209 S MARKET STREET INGLEWOOD, CA 90301 |
| Contractor | Steiner Douglas Construction Inc; Lic. No.: 916002-B | 1541 PARKWAY LOOP STE A TUSTIN, CA 92780 |
| Engineer | Arriola,, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | Krief,, Dan Dov; Lic. No.: C76041 | 6420 WILSHIRE BLVD STE 1000 LOS ANGELES, CA 90048 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Voorheis,, Jeff Stuart; Lic. No.: L7570 | 17049 SUNBURST ST NORTHRIDGE, CA 91325 |
| Geologist | Minas,, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/17/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 11/18/2021 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 11/19/2021 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 12/17/2021 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 1/7/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 1/11/2022 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 1/14/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 1/27/2022 | Conditional Approval | EDWIN GREGORYONA |
| METHANE-Barrier | 1/27/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Subgrade | 1/27/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 2/4/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Barrier | 2/4/2022 | Partial Inspection | EDWIN GREGORYONA |
| METHANE-Rough | 2/4/2022 | Partial Inspection | EDWIN GREGORYONA |
| METHANE-Subgrade | 2/4/2022 | Partial Inspection | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 2/4/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Final | 2/8/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 2/10/2022 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Barrier | 2/10/2022 | Approved | EDWIN GREGORYONA |
| METHANE-Subgrade | 2/10/2022 | Approved | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 3/17/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 5/17/2022 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 5/18/2022 | Partial Inspection | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Partial Approval | EDWIN GREGORYONA |
| Wall Anchors | 6/6/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/9/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Insulation | 6/27/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Partial Inspection | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 7/28/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 7/28/2022 | Partial Inspection | EDWIN GREGORYONA |
| Special/Order Compliance | 8/3/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Drywall Nailing | 8/25/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 8/25/2022 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 9/29/2022 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 10/12/2022 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 10/25/2022 | Approved | EDWIN GREGORYONA |
| Final | 7/28/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 7/28/2023 | Approved | EDWIN GREGORYONA |
| Green Building Final | 7/28/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Final | 7/28/2023 | Approved | EDWIN GREGORYONA |
| METHANE-Rough | 7/28/2023 | Approved | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 7/28/2023 | Approved | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 7/28/2023 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 7/28/2023 | Approved | EDWIN GREGORYONA |
| Structural Steel Frame | 7/28/2023 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 7/28/2023 | Approved | EDWIN GREGORYONA |
| Wood Frame | 7/28/2023 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 7/19/2024 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 7/23/2024 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 1/14/2025 | Partial Inspection | CHRISTOPHER BLACKWOOD |
| Final | 4/1/2025 | OK to Issue CofO | EDWIN GREGORYONA |
| Green Building Final | 4/1/2025 | Approved | EDWIN GREGORYONA |