1622 E 113TH ST 90059

Certificate Information: 1622 E 113TH ST 90059

Application / Permit
20010-10000-00596
Plan Check / Job No.
B20LA03669
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY 18'X72' SFD WITH ATTACHED 1-CAR CARPORT. "PER WOOD FRAME PERSCRIPTIVE PROVISIONS 1-STORY RESIDENTIAL CONSTRUCTION ONLY" INFORMATION BULLETIN P/BC 2020-004
Permit Issued
Issued on 6/18/2020
Issuing Office
Current Status
CofO Issued on 2/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 AMIR DANAI
Corrections Issued 3/17/2020 AMIR DANAI
Quality Review Completed 3/18/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 3/24/2020 APPLICANT
Green Plans Picked Up 5/1/2020 APPLICANT
Plan Check Approved 6/12/2020 AMIR DANAI
Issued 6/18/2020 APPLICANT
CofO in Progress 2/9/2021 ANSON MAGLASANG
Permit Finaled 2/11/2021 DEROLD HAUFF
CofO Issued 2/11/2021 DEROLD HAUFF
Permit Finaled 2/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/15/2020 RENZ SORIANO
Permit Cleared 4/15/2020 RENZ SORIANO
Green Code Cleared 4/30/2020 AMIR DANAI
Eng Process Fee Ord 176,300 Cleared 5/7/2020 RENZ SORIANO
Sewer availability Cleared 5/7/2020 RENZ SORIANO
Hydrant and Access approval Cleared 5/13/2020 GEORGE SUCHAND
Trees in Parkway Cleared 5/21/2020 JOHN KIM
Low Impact Development Cleared 6/2/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 6/3/2020 RENZ SORIANO

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/30/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 6/30/2020 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 6/30/2020 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/13/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/4/2020 Approved DAVID FEILER
Green Building Rough 9/4/2020 Approved DAVID FEILER
Interior/Exterior Lathing 9/4/2020 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 9/4/2020 Approved DAVID FEILER
Verify Sprinkler Sign Off 9/4/2020 Approved DAVID FEILER
Insulation 9/11/2020 Approved EUGENE CASSIDY
Drywall Nailing 9/17/2020 Approved EUGENE CASSIDY
Sewer 9/23/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 9/30/2020 Approved EUGENE CASSIDY
Final 11/6/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/6/2020 Approved EUGENE CASSIDY
Green Building Final 11/6/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 11/6/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 11/6/2020 Approved EUGENE CASSIDY
Final 11/19/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 11/19/2020 Not Ready for Inspection EUGENE CASSIDY
Final 12/9/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 12/9/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 1/5/2021 Approved EUGENE CASSIDY
Final 1/5/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 1/5/2021 Approved EUGENE CASSIDY
PLUMBING-Final 1/5/2021 Approved EUGENE CASSIDY
Service/Power Release 1/5/2021 Approved EUGENE CASSIDY