Pre-Inspection
|
11/17/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
3/30/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
3/30/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
3/30/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
3/30/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
4/4/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
4/4/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
4/4/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Methane Barrier
|
4/26/2022
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
METHANE-Barrier
|
5/20/2022
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
5/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
5/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
5/26/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Methane Barrier
|
6/3/2022
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
6/3/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
6/3/2022
|
Approved
|
NICK DANERI
|
|
METHANE-Subgrade
|
6/3/2022
|
Approved
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
6/6/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
6/7/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/8/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/9/2022
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
6/9/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Rough
|
6/9/2022
|
Approved
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
6/9/2022
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
6/9/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
6/10/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Green Building Rough
|
6/13/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
6/13/2022
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
6/13/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
6/15/2022
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
6/16/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
6/24/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
6/27/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
6/28/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/28/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/1/2022
|
Approved
|
GREGORY POMISH
|
|
Deputy Pre-Stress Concrete
|
7/5/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Green Building Rough
|
7/5/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
7/5/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
7/5/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
7/8/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/25/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
7/25/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Pre-Stress Concrete
|
7/26/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
7/28/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Pre-Stress Concrete
|
8/2/2022
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
8/2/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
8/2/2022
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
8/2/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
8/16/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/16/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Green Building Rough
|
8/25/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
8/25/2022
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
8/25/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
8/29/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/29/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Pre-Stress Concrete
|
9/2/2022
|
Conditional Approval
|
GREGORY POMISH
|
|
Masonry Wall/Backfill
|
9/7/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
9/8/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
9/21/2022
|
Conditional Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
9/21/2022
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
9/21/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
9/26/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/27/2022
|
Conditional Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
9/27/2022
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/4/2022
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
10/20/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Wood Frame
|
10/20/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/24/2022
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
10/28/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
10/28/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Masonry Wall/Backfill
|
11/2/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
11/4/2022
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2022
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
11/16/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
12/1/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/1/2022
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
12/1/2022
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
12/9/2022
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/16/2022
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
12/16/2022
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
12/29/2022
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/11/2023
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
1/11/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
1/12/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Insulation
|
1/17/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
1/23/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Interior/Exterior Lathing
|
1/24/2023
|
Partial Inspection
|
NICK DANERI
|
|
Wood Frame
|
1/24/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
1/26/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
1/31/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Drywall Nailing
|
2/1/2023
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
2/1/2023
|
Corrections Issued
|
NICK DANERI
|
|
Drywall Nailing
|
2/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
2/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
2/21/2023
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
3/9/2023
|
Partial Inspection
|
NICK DANERI
|
|
Insulation
|
3/20/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Wood Frame
|
3/23/2023
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
4/4/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Wood Frame
|
4/4/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Wood Frame
|
4/5/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
4/6/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
4/12/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
4/13/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
4/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
4/19/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/19/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/20/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/21/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
4/21/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
4/21/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
4/25/2023
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/25/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
4/25/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/26/2023
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
4/28/2023
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
4/28/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
5/4/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
5/9/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
5/16/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
5/19/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Wood Frame
|
5/30/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
6/6/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
6/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
6/20/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
6/27/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
7/25/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
8/24/2023
|
Partial Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
9/13/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
9/22/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Light Gage Steel Frame
|
10/3/2023
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
10/13/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
11/15/2023
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
11/15/2023
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
11/15/2023
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
11/17/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
11/21/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Drywall Nailing
|
11/29/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
12/5/2023
|
Approved
|
NICK DANERI
|
|
Final
|
12/5/2023
|
Partial Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
12/5/2023
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
12/5/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
12/5/2023
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
12/5/2023
|
Partial Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
12/5/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
12/5/2023
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
12/5/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
12/5/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
12/6/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
1/29/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Final
|
1/30/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Final
|
1/30/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
1/30/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Reinforced Masonry Frame
|
1/30/2024
|
Partial Approval
|
GREGORY POMISH
|
|
SGSOV-Seismic Gas S/O Valve
|
1/30/2024
|
SGSOV Approved
|
GREGORY POMISH
|
|
Smoke Detectors
|
1/30/2024
|
Approved
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
1/30/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
1/31/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
2/1/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
2/2/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
2/8/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
2/21/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
2/29/2024
|
Partial Inspection
|
NICK DANERI
|
|
Final
|
4/2/2024
|
Partial Inspection
|
NICK DANERI
|
|
Green Building Final
|
4/2/2024
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
4/2/2024
|
Approved
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
4/2/2024
|
Approved
|
NICK DANERI
|
|
Special/Order Compliance
|
4/2/2024
|
Conditional Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/2/2024
|
Approved
|
NICK DANERI
|
|
Final
|
4/23/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
4/23/2024
|
Partial Inspection
|
NICK DANERI
|
|
Final
|
4/29/2024
|
Conditional Approval
|
NICK DANERI
|