12865 N NORRIS AVE 91342

Certificate Information: 12865 N NORRIS AVE 91342

Application / Permit
20010-10000-00577
Plan Check / Job No.
B20LA03579
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETATCHED ADU PER ORDINANCE AT REAR HALF OF THE LOT (1200sqft) PER WFPP
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
CofO Issued on 4/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 AMIR DANAI
Corrections Issued 3/17/2020 AMIR DANAI
Quality Review Completed 4/1/2020 ARMEN JIVALAGIAN
Green Plans Picked Up 5/11/2020 APPLICANT
Applicant returned to address corrections 9/18/2020 AMIR DANAI
Plan Check Approved 11/12/2020 AMIR DANAI
Issued 12/1/2020 APPLICANT
Building Plans Picked Up 12/3/2020 APPLICANT
CofO in Progress 2/7/2022 JOHN HAYES
No Progress 2/12/2022 MICHAEL TEMPLE
CofO in Progress 4/2/2022 DEROLD HAUFF
Permit Finaled 4/2/2022 DEROLD HAUFF
CofO Issued 4/2/2022 DEROLD HAUFF
Permit Finaled 4/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/17/2020 ADRIAN CASTRO
Sewer availability Cleared 4/17/2020 ADRIAN CASTRO
Green Code Cleared 5/11/2020 DONALD CRICHLOW
Hydrant and Access approval Cleared 5/12/2020 MATTHEW CRAIG
Low Impact Development Cleared 6/29/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/7/2020 ADRIAN CASTRO
Tenant Habitability Plan Cleared 8/21/2020 PHILLIP MUNGUIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/22/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 12/22/2020 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 1/6/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 1/6/2021 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Partial Approval MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 3/19/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/14/2021 Approved MISAEL ESPARZA
Green Building Rough 6/14/2021 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 6/14/2021 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 6/14/2021 Approved MISAEL ESPARZA
Insulation 6/23/2021 Corrections Issued DEANDRE HOFFMAN
Interior/Exterior Lathing 6/23/2021 Not Ready for Inspection DEANDRE HOFFMAN
Insulation 6/28/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/28/2021 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 6/28/2021 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 7/1/2021 Approved JOHN HAYES
Green Building Rough 7/1/2021 Approved JOHN HAYES
Interior/Exterior Lathing 7/1/2021 Approved JOHN HAYES
Shower Pan 7/1/2021 Approved JOHN HAYES
Underground Mechanical 8/12/2021 Corrections Issued MISAEL ESPARZA
Sewer 8/17/2021 Approved MISAEL ESPARZA
Gas Test 8/20/2021 Partial Approval MISAEL ESPARZA
Final 12/10/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 12/10/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 12/10/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 12/10/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 12/10/2021 Not Ready for Inspection JOHN HAYES
Final 2/7/2022 OK to Issue CofO JOHN HAYES
Footing/Foundation/Slab 2/7/2022 Approved JOHN HAYES
Green Building Final 2/7/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved JOHN HAYES
Service/Power Release 2/7/2022 Approved JOHN HAYES
Smoke Detectors 2/7/2022 Approved JOHN HAYES
Special/Order Compliance 2/7/2022 Approved JOHN HAYES