3609 S 10TH AVE 90018

Certificate Information: 3609 S 10TH AVE 90018

Application / Permit
20010-10000-00533
Plan Check / Job No.
B20LA03208
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NEW 3-STORY, TYPE llB, COMMERCIAL OFFICE BUILDING OVER 2 LEVEL, TYPE lA, SUBTERRANEAN PARKING GARAGES. CORE AND SHELL ONLY.
Permit Issued
Issued on 6/22/2021
Issuing Office
Metro
Current Status
Issued on 6/22/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 KESETE HAREGOT
Disabled Access Plans Picked Up 4/2/2020 APPLICANT
Corrections Issued 4/7/2020 KESETE HAREGOT
Quality Review Completed 4/23/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 5/12/2020 APPLICANT
Green Plans Picked Up 8/18/2020 APPLICANT
Applicant returned to address corrections 11/13/2020 KESETE HAREGOT
Applicant returned to address corrections 11/24/2020 KESETE HAREGOT
Applicant returned to address corrections 6/11/2021 KESETE HAREGOT
Plan Check Approved 6/21/2021 KESETE HAREGOT
Issued 6/22/2021 APPLICANT
TCO Issued (Expire Date: 05-15-2024) 11/17/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 6/1/2020 EMIL KYUPELYAN
Highway dedication Cleared 6/1/2020 EMIL KYUPELYAN
Permit Cleared 6/1/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 6/15/2020 EMIL KYUPELYAN
Sewer availability Cleared 6/15/2020 EMIL KYUPELYAN
Transportation Demand Ord. Cleared 7/7/2020 MOHAMMAD HASAN
Green Code Cleared 8/24/2020 KHEDER ALRAZAA
DAS Clearance Cleared 8/27/2020 KESETE HAREGOT
Hydrant and Access approval Cleared 9/2/2020 MATTHEW CRAIG
Trees in Parkway Cleared 10/13/2020 JOHN KIM
Low Impact Development Cleared 11/5/2020 SARAH YOUSSEF
Building over 3-story or 36-ft Cleared 11/10/2020 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 4/20/2021 ROSA SILVA
Frnt yard landscape/Water mgmt Cleared 5/4/2021 JASON CHAN
Miscellaneous Cleared 5/4/2021 JASON CHAN
Miscellaneous Cleared 5/4/2021 JASON CHAN
Site Plan review Cleared 5/4/2021 JASON CHAN
Specific Plan Cleared 5/4/2021 JASON CHAN
Tract Map conditions Cleared 5/4/2021 JASON CHAN
ZI Cleared 5/4/2021 JASON CHAN
Specific Plan Cleared 5/5/2021 JASON CHAN
Work Adjacent to Public Way Cleared 5/19/2021 JOSE RODRIGUEZ

Contact Information

Architect Swartz,, David Louis; Lic. No.: C19729 1437 4TH STREET SUITE 400      SANTA MONICA, CA 90401
Contractor Kprs Construction Services Inc; Lic. No.: 751130-B 2850 SATURN STREET      BREA, CA 92821
Engineer Albus,, David Edward; Lic. No.: GE2455 1612 WINDSOR LN      SANTA ANA, CA 92705
Engineer Breaks,, Matthew Calvin; Lic. No.: S6028 5056 TUJUNGA AVE APT 17      NORTH HOLLYWOOD, CA 91601
Engineer Kim,, Hyun Jin; Lic. No.: GE3106 6412 STANFORD AVENUE      GARDEN GROVE, CA 92845
Engineer Risha,, Janah Adib; Lic. No.: C46811 410 EAST CYPRESS AVE      BURBANK, CA 91501

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/23/2021 Approved JAMES POWERS
Pre-Inspection 9/9/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/30/2021 Partial Approval JONATHAN QUACH
METHANE-Barrier 9/30/2021 Not Ready for Inspection JONATHAN QUACH
METHANE-Subgrade 9/30/2021 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 10/7/2021 Partial Approval JAMES POWERS
METHANE-Barrier 10/7/2021 Approved JAMES POWERS
METHANE-Subgrade 10/7/2021 Approved JAMES POWERS
Green Building Rough 10/13/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 10/13/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/13/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/13/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/19/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 10/19/2021 Partial Approval RUSSELL BONVOULOIR
Green Building Rough 10/19/2021 Partial Inspection RUSSELL BONVOULOIR
METHANE-Rough 10/19/2021 Partial Inspection RUSSELL BONVOULOIR
Reinforced Concrete Frame 10/19/2021 Partial Approval RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 10/19/2021 Partial Inspection RUSSELL BONVOULOIR
Deputy Reinf. Concrete 10/20/2021 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 10/21/2021 Conditional Approval RUSSELL BONVOULOIR
Reinforced Masonry Frame 10/21/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 10/22/2021 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/22/2021 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 10/26/2021 Partial Approval JAMES POWERS
Green Building Rough 10/26/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 10/26/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/26/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/26/2021 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 10/27/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 10/28/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 10/29/2021 Partial Approval JAMES POWERS
Green Building Rough 10/29/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 10/29/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/29/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/29/2021 Not Ready for Inspection JAMES POWERS
Piling/Pier/Caisson 11/1/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Shotcrete 11/2/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/2/2021 Partial Approval JAMES POWERS
Green Building Rough 11/3/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 11/3/2021 Approved JAMES POWERS
Reinforced Concrete Frame 11/3/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/3/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 11/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/5/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/9/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/15/2021 Partial Approval JAMES POWERS
Green Building Rough 12/3/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/3/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 12/3/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/7/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/10/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 12/13/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/14/2021 Partial Approval JAMES POWERS
Structural Steel Frame 12/14/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/15/2021 Partial Approval JAMES POWERS
Green Building Rough 12/15/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/15/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/15/2021 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 12/16/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/16/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 12/17/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/17/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/17/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/20/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/22/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 12/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/28/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/3/2022 Partial Approval JAMES POWERS
Green Building Rough 1/7/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 1/7/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/7/2022 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 1/8/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/10/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/14/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/18/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 1/19/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/20/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 1/21/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 1/27/2022 Partial Approval JAMES POWERS
Green Building Rough 1/27/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/27/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/27/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 1/31/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/1/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/2/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/3/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/4/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/8/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/8/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/9/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/9/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/10/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/14/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/15/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/16/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/17/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/18/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/22/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/23/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/23/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/24/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/24/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/25/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/28/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/1/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/1/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/2/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/3/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/8/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/9/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/15/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/16/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/17/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/17/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/18/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/22/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/29/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/30/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/31/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/1/2022 Conditional Approval TED RIES
Deputy Steel/Welding 4/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/6/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/8/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/12/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/13/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/14/2022 Partial Approval JAMES POWERS
Green Building Rough 4/14/2022 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 4/14/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/14/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 4/15/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/18/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/19/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 4/20/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 4/22/2022 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 4/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/26/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/27/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/28/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/28/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/29/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/2/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/3/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/3/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/5/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/6/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/6/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/9/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/10/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/11/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/11/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/12/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/12/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/13/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/16/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/17/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/17/2022 Not Ready for Inspection JAMES POWERS
Green Building Rough 5/17/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/17/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/17/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 5/18/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/18/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/19/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/20/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 5/20/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/23/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/24/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 5/24/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/25/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/25/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/25/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 5/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/31/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 5/31/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/1/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/2/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/3/2022 Partial Approval JAMES POWERS
Green Building Rough 6/3/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/3/2022 Partial Approval JAMES POWERS
Structural Steel Frame 6/3/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/3/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/6/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/6/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/8/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/9/2022 Partial Approval JAMES POWERS
Green Building Rough 6/9/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 6/9/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/9/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/9/2022 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 6/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/14/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/15/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/16/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/21/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/22/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/23/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/23/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/24/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 6/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/24/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/28/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/29/2022 Partial Approval JAMES POWERS
Green Building Rough 6/30/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Masonry Frame 6/30/2022 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 6/30/2022 Not Ready for Inspection GREGORY POMISH
Deputy Steel/Welding 7/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/7/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/8/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/8/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 7/13/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/21/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/26/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/28/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/29/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/29/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/5/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/5/2022 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 8/5/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/8/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 8/12/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/12/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/15/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/16/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/18/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/23/2022 Partial Approval JAMES POWERS
Drywall Nailing 8/23/2022 Partial Approval JAMES POWERS
Insulation 8/23/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 8/23/2022 Partial Approval JAMES POWERS
Drywall Nailing 8/24/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/29/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/8/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/15/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 9/27/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/30/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 10/7/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/26/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/26/2022 Partial Approval JAMES POWERS
Green Building Rough 10/26/2022 Approved JAMES POWERS
Deputy Reinf. Concrete 11/18/2022 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 11/22/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/1/2022 Partial Approval JAMES POWERS
Green Building Final 1/6/2023 Partial Inspection EDWIN GREGORYONA
Final 3/3/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/23/2023 Not Ready for Inspection JAMES POWERS
Final 3/30/2023 OK for TCO JAMES POWERS
Footing/Foundation/Slab 3/30/2023 Approved JAMES POWERS
Green Building Final 3/30/2023 Approved JAMES POWERS
Reinforced Concrete Frame 3/30/2023 Approved JAMES POWERS
Reinforced Masonry Frame 3/30/2023 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV No Gas JAMES POWERS
Smoke Detectors 3/30/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 3/30/2023 Approved JAMES POWERS
Final 4/18/2023 Partial Inspection GREGORY POMISH
Pre-Inspection 4/18/2023 Conditional Approval DARRYL ARNOLD
Final 5/1/2023 OK for TCO JAMES POWERS
Special/Order Compliance 4/16/2024 Approved JAMES POWERS