132-134 W 54TH ST 90037

Certificate Information: 132-134 W 54TH ST 90037

Application / Permit
20010-10000-00521
Plan Check / Job No.
B20LA03141
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 25'x94' 2-story duplex building with attached 2-car garage at rear and attached 1-car garage at front of building.
Permit Issued
Issued on 12/4/2020
Issuing Office
Current Status
CofO Issued on 6/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 TU HUA
Corrections Issued 3/31/2020 TU HUA
Quality Review Completed 4/8/2020 KEN GILL
Building Plans Picked Up 4/21/2020 APPLICANT
Green Plans Picked Up 5/26/2020 APPLICANT
Applicant returned to address corrections 7/9/2020 TU HUA
Applicant returned to address corrections 7/17/2020 TU HUA
Plan Check Approved 12/3/2020 TU HUA
Issued 12/4/2020 APPLICANT
CofO in Progress 5/18/2021 ROBERT MCDOWELL
Permit Finaled 6/4/2021 DEROLD HAUFF
CofO Issued 6/4/2021 DEROLD HAUFF
Permit Finaled 6/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/11/2020 EMIL KYUPELYAN
Address approval Cleared 5/11/2020 EMIL KYUPELYAN
Permit Cleared 5/11/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 5/12/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/12/2020 EMIL KYUPELYAN
CPC Cleared 5/19/2020 TERRI OSBORNE
ZI Cleared 5/19/2020 TERRI OSBORNE
Green Code Cleared 5/26/2020 KHEDER ALRAZAA
Hydrant and Access approval Cleared 5/27/2020 KURT CORRAL
Low Impact Development Cleared 6/17/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/22/2020 RENZ SORIANO
Trees in Parkway Cleared 7/7/2020 JOHN KIM

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/8/2021 Approved ROBERT MCDOWELL
Deputy Reinf. Concrete 1/11/2021 Conditional Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Partial Approval ROBERT MCDOWELL
Underground Mechanical 1/15/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Partial Approval DAVID FEILER
Insulation 1/19/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 2/24/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 2/24/2021 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 2/24/2021 Approved DAVID FEILER
Verify Sprinkler Sign Off 2/24/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 2/25/2021 Approved ROBERT MCDOWELL
Insulation 3/2/2021 Approved DAVID FEILER
Drywall Nailing 3/12/2021 Approved ROBERT MCDOWELL
Green Building Rough 3/12/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 3/12/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 5/18/2021 Approved ROBERT MCDOWELL
Final 5/18/2021 OK to Issue CofO ROBERT MCDOWELL
Green Building Final 5/18/2021 Approved ROBERT MCDOWELL
HVAC-Final 5/18/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 5/18/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 5/18/2021 Approved ROBERT MCDOWELL
Smoke Detectors 5/18/2021 Approved ROBERT MCDOWELL