936-938 W 75TH ST 90044

Certificate Information: 936-938 W 75TH ST 90044

Application / Permit
20010-10000-00520
Plan Check / Job No.
B20LA03140
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 25'x94' 2-story duplex buliding with attached garage. NFPA 13D provided throughout.
Permit Issued
Issued on 9/18/2020
Issuing Office
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 TU HUA
Corrections Issued 3/31/2020 TU HUA
Quality Review Completed 4/8/2020 KEN GILL
Building Plans Picked Up 4/21/2020 APPLICANT
Green Plans Picked Up 5/18/2020 APPLICANT
Applicant returned to address corrections 9/15/2020 TU HUA
Plan Check Approved 9/18/2020 TU HUA
Issued 9/18/2020 APPLICANT
CofO in Progress 2/11/2021 ALEJANDRO DE ARTOLA
Permit Finaled 2/13/2021 DEROLD HAUFF
CofO Issued 2/13/2021 DEROLD HAUFF
Permit Finaled 2/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 5/15/2020 KHEDER ALRAZAA
ZI Cleared 5/19/2020 TERRI OSBORNE
Trees in Parkway Cleared 5/20/2020 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 6/8/2020 TERRI OSBORNE
Hydrant and Access approval Cleared 6/18/2020 MATTHEW CRAIG
Address approval Cleared 6/19/2020 JUAN ASHTON
Address approval Cleared 6/19/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 6/19/2020 JUAN ASHTON
Sewer availability Cleared 6/19/2020 JUAN ASHTON
Low Impact Development Cleared 8/28/2020 YVAINNE GALSIM
Permit Cleared 8/31/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 8/31/2020 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/9/2020 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/19/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 10/19/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Partial Approval ALEJANDRO DE ARTOLA
Insulation 10/20/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Approved OSVALDO PARAMO
ELECTRICAL-Rough 12/2/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/7/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
HVAC-Rough 12/7/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/7/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/7/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/9/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 12/9/2020 Approved ALEJANDRO DE ARTOLA
Insulation 12/9/2020 Approved ALEJANDRO DE ARTOLA
Sewer 12/9/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 12/22/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 12/22/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 2/8/2021 Approved ALEJANDRO DE ARTOLA
Final 2/8/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/8/2021 Approved ALEJANDRO DE ARTOLA
Gas Test 2/8/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 2/8/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 2/8/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 2/8/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 2/8/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 2/8/2021 Approved ALEJANDRO DE ARTOLA
Final 2/11/2021 OK to Issue CofO ALEJANDRO DE ARTOLA