108-108 1/2 W 103RD ST 90003
Certificate Information: 108-108 1/2 W 103RD ST 90003
- Application / Permit
- 20010-10000-00509
- Plan Check / Job No.
- B20LA03112
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX W 3 CAR GARAGE AT 1ST FLOOR
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 3/25/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 3/31/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 10/5/2020 | APPLICANT |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| Plan Check Approved | 3/7/2023 | SAMUEL GONZALEZ |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 6/21/2025 | DAVID FEILER |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
| CofO Issued | 6/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2020 | ELENA LOPEZ |
| Green Code | Cleared | 7/13/2020 | VIVIAN LAO |
| Sewer availability | Cleared | 7/22/2020 | ELENA LOPEZ |
| Low Impact Development | Cleared | 8/24/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/1/2020 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 10/8/2020 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 1/21/2021 | COLLINS ALLAN |
| Certificate of Compliance | Cleared | 2/16/2021 | MARC WOERSCHING |
| Community Plan Implem. Overlay | Cleared | 3/3/2021 | THOMAS LANG |
| Trees in Parkway | Cleared | 5/5/2021 | JOHN KIM |
| Community Plan Implem. Overlay | Cleared | 11/14/2022 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 1/23/2023 | ADALBERTO VERA |
Contact Information
| Architect | Muhammad,, Alfred H; Lic. No.: C18389 | 400 E COMPTON BLVD UNIT C COMPTON, CA 90221 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/28/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 5/3/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 5/15/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 5/19/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 5/24/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/6/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 6/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 6/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/20/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 7/20/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 7/20/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 7/20/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/20/2023 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/11/2023 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 10/11/2023 | Corrections Issued | JOHN KLARIN |
| Verify Sprinkler Sign Off | 10/11/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 10/16/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Rough | 10/16/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/16/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 10/16/2023 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 10/16/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/19/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 10/19/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 10/19/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 10/19/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/19/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 10/19/2023 | Approved | JOHN KLARIN |
| Insulation | 10/31/2023 | Corrections Issued | JAMES CHAVEZ |
| Insulation | 11/3/2023 | Partial Inspection | JOHN KLARIN |
| Drywall Nailing | 11/9/2023 | Approved | JOHN KLARIN |
| Insulation | 11/9/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/9/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 12/15/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/5/2024 | Approved | BEN MOLSTAD |
| Gas Test | 7/22/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 9/25/2024 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 9/25/2024 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 10/3/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 10/28/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 10/28/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 10/28/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 11/8/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 11/8/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 12/2/2024 | Approved | BEN MOLSTAD |
| Final | 1/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 1/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 1/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 1/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 1/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 1/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 5/29/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 5/29/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 5/29/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 6/2/2025 | Approved | BEN MOLSTAD |
| Final | 6/2/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 6/2/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 6/2/2025 | Partial Approval | BEN MOLSTAD |
| Special/Order Compliance | 6/2/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 6/6/2025 | Approved | JOHN KLARIN |
| Final | 6/6/2025 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 6/6/2025 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 6/6/2025 | Approved | JOHN KLARIN |
| PLUMBING-Final | 6/6/2025 | Approved | JOHN KLARIN |
| Service/Power Release | 6/6/2025 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 6/6/2025 | Corrections Issued | JOHN KLARIN |
| Special/Order Compliance | 6/10/2025 | Approved | JOHN KLARIN |
| Final | 6/21/2025 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 6/21/2025 | Approved | DAVID FEILER |
| Service/Power Release | 6/21/2025 | Approved | DAVID FEILER |
| Smoke Detectors | 6/21/2025 | Approved | DAVID FEILER |