19508 W HART ST 91335
Certificate Information: 19508 W HART ST 91335
- Application / Permit
- 20010-10000-00496
- Plan Check / Job No.
- B20LA03023
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER STATE LAW GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/23/2020
- Issuing Office
- Current Status
- CofO Issued on 9/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 3/7/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 3/18/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 3/20/2020 | APPLICANT |
| Applicant returned to address corrections | 4/23/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 5/1/2020 | CRYSTEL MAALOUF |
| Green Plans Picked Up | 5/20/2020 | APPLICANT |
| Plan Check Approved | 8/7/2020 | CRYSTEL MAALOUF |
| Issued | 8/23/2020 | APPLICANT |
| CofO in Progress | 9/2/2021 | VINCENT HANLEY |
| Permit Finaled | 9/3/2021 | MICHAEL SMITH |
| CofO Issued | 9/3/2021 | MICHAEL SMITH |
| Permit Finaled | 9/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/14/2020 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 4/14/2020 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/15/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 5/14/2020 | CRYSTEL MAALOUF |
| Stormwater Pollution Mitigatn | Cleared | 7/29/2020 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/26/2020 | Approved | VINCENT HANLEY |
| Pre-Inspection | 11/10/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 11/30/2020 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/9/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 2/8/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/8/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/16/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 2/16/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 2/16/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/23/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/23/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/23/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 2/23/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/23/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/5/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 3/5/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 3/11/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/11/2021 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 3/25/2021 | Approved | VINCENT HANLEY |
| Sewer | 3/25/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/1/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/1/2021 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/3/2021 | Approved | VINCENT HANLEY |
| Final | 8/3/2021 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 8/3/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 8/3/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/3/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/3/2021 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 8/3/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 8/3/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/19/2021 | Approved | VINCENT HANLEY |
| Final | 8/19/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Gas Test | 8/19/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/19/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/19/2021 | Approved | VINCENT HANLEY |
| Service/Power Release | 8/19/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 9/2/2021 | Approved | VINCENT HANLEY |
| Final | 9/2/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 9/2/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 9/2/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/2/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/2/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 9/2/2021 | Approved | VINCENT HANLEY |