19508 W HART ST 91335

Certificate Information: 19508 W HART ST 91335

Application / Permit
20010-10000-00496
Plan Check / Job No.
B20LA03023
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER STATE LAW GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/23/2020
Issuing Office
Current Status
CofO Issued on 9/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 CRYSTEL MAALOUF
Corrections Issued 3/7/2020 CRYSTEL MAALOUF
Quality Review Completed 3/18/2020 BILL STUTSMAN
Building Plans Picked Up 3/20/2020 APPLICANT
Applicant returned to address corrections 4/23/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 5/1/2020 CRYSTEL MAALOUF
Green Plans Picked Up 5/20/2020 APPLICANT
Plan Check Approved 8/7/2020 CRYSTEL MAALOUF
Issued 8/23/2020 APPLICANT
CofO in Progress 9/2/2021 VINCENT HANLEY
Permit Finaled 9/3/2021 MICHAEL SMITH
CofO Issued 9/3/2021 MICHAEL SMITH
Permit Finaled 9/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/14/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/14/2020 JOHN TRIANTAFYLLOS
ZI Cleared 4/14/2020 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 4/15/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/15/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 5/14/2020 CRYSTEL MAALOUF
Stormwater Pollution Mitigatn Cleared 7/29/2020 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/26/2020 Approved VINCENT HANLEY
Pre-Inspection 11/10/2020 Approved VINCENT HANLEY
PLUMBING-Rough 11/30/2020 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 12/9/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Partial Approval VINCENT HANLEY
Green Building Rough 2/8/2021 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 2/8/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/16/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 2/16/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/16/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 2/23/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/23/2021 Approved VINCENT HANLEY
Green Building Rough 2/23/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 2/23/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/23/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/5/2021 Partial Approval VINCENT HANLEY
Green Building Rough 3/5/2021 Not Ready for Inspection VINCENT HANLEY
Insulation 3/11/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/11/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 3/25/2021 Approved VINCENT HANLEY
Sewer 3/25/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/1/2021 Approved VINCENT HANLEY
Underground Mechanical 4/1/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 8/3/2021 Approved VINCENT HANLEY
Final 8/3/2021 Corrections Issued VINCENT HANLEY
Gas Test 8/3/2021 Not Ready for Inspection VINCENT HANLEY
Green Building Final 8/3/2021 Approved VINCENT HANLEY
Green Building Rough 8/3/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 8/3/2021 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 8/3/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 8/19/2021 Approved VINCENT HANLEY
Final 8/19/2021 Not Ready for Inspection VINCENT HANLEY
Gas Test 8/19/2021 Approved VINCENT HANLEY
HVAC-Final 8/19/2021 Approved VINCENT HANLEY
PLUMBING-Final 8/19/2021 Approved VINCENT HANLEY
Service/Power Release 8/19/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Final 9/2/2021 Approved VINCENT HANLEY
Final 9/2/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 9/2/2021 Approved VINCENT HANLEY
Green Building Final 9/2/2021 Approved VINCENT HANLEY
HVAC-Final 9/2/2021 Approved VINCENT HANLEY
PLUMBING-Final 9/2/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 9/2/2021 Approved VINCENT HANLEY