1816 S CARMONA AVE 90019

Certificate Information: 1816 S CARMONA AVE 90019

Application / Permit
20010-10000-00454
Plan Check / Job No.
B20LA02700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE.
Permit Issued
Issued on 2/1/2021
Issuing Office
Metro
Current Status
CofO Issued on 9/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 GARO TELMI
Corrections Issued 3/16/2020 GARO TELMI
Quality Review Completed 3/16/2020 KEN GILL
Green Plans Picked Up 10/16/2020 APPLICANT
Plan Check Approved 12/30/2020 GARO TELMI
Issued 2/1/2021 APPLICANT
Building Plans Picked Up 2/2/2021 APPLICANT
CofO in Progress 8/24/2022 JOSE AVILA
Permit Finaled 9/16/2022 DEROLD HAUFF
CofO Issued 9/16/2022 DEROLD HAUFF
Permit Finaled 9/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/25/2020 ERIK BEASLEY
Highway dedication Cleared 6/25/2020 ERIK BEASLEY
Permit Cleared 6/25/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/13/2020 ERIK BEASLEY
Sewer availability Cleared 7/13/2020 ERIK BEASLEY
Frnt yard landscape/Water mgmt Cleared 8/11/2020 MAXFIELD VERMY
Green Code Cleared 10/13/2020 DONALD CRICHLOW
Green Code Cleared 10/13/2020 GARO TELMI
Hydrant and Access approval Cleared 11/10/2020 KURT CORRAL
Low Impact Development Cleared 12/2/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 12/18/2020 ROSA SILVA

Contact Information

Contractor Moving Forward Builders Inc; Lic. No.: 1072204-B 3219 LIBERTY BLVD      SOUTH GATE, CA 90280
Engineer Desai,, Anil Thakorbhai; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/8/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 2/10/2021 Conditional Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 2/16/2021 Conditional Approval SCOTT FINNILA
Underground Mechanical 2/16/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 3/2/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 3/5/2021 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/19/2021 Partial Approval STUART CHAPMAN
Deputy Wood Construction 7/21/2021 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 8/4/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 8/4/2021 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 8/4/2021 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 8/9/2021 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 8/9/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 8/9/2021 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/30/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 8/30/2021 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Approved FREDDIE RIVERA
Green Building Rough 8/30/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 8/30/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 8/30/2021 Conditional Approval FREDDIE RIVERA
Verify Sprinkler Sign Off 8/30/2021 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 9/14/2021 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 9/14/2021 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 9/14/2021 Approved THOMAS LOGRASSO
HVAC-Rough 9/14/2021 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 9/14/2021 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 9/14/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 9/15/2021 Approved STUART CHAPMAN
HVAC-Rough 9/15/2021 Approved STUART CHAPMAN
PLUMBING-Rough 9/15/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 9/21/2021 Corrections Issued ROBERT VORHIS
BUILDING-Rough-Frame 9/24/2021 Approved FREDDIE RIVERA
Insulation 9/30/2021 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 9/30/2021 Corrections Issued ALAN MORELOS
Interior/Exterior Lathing 10/5/2021 Corrections Issued SCOTT FINNILA
Drywall Nailing 10/13/2021 Corrections Issued STUART CHAPMAN
Drywall Nailing 10/13/2021 Off-Hour Fees Due
Insulation 10/13/2021 Approved STUART CHAPMAN
Insulation 10/13/2021 Off-Hour Fees Due
Interior/Exterior Lathing 10/13/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 10/13/2021 Off-Hour Fees Due
Interior/Exterior Lathing 10/22/2021 Approved STUART CHAPMAN
Gas Test 3/29/2022 Not Ready for Inspection JOSE AVILA
HVAC-Final 3/29/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Final 3/29/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 4/6/2022 Corrections Issued JOSE AVILA
Gas Test 4/6/2022 Corrections Issued JOSE AVILA
HVAC-Final 4/6/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 4/6/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 4/13/2022 Corrections Issued JOSE AVILA
Gas Test 4/13/2022 Approved JOSE AVILA
HVAC-Final 4/13/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/12/2022 No Access for Inspection JOSE AVILA
HVAC-Final 5/12/2022 No Access for Inspection JOSE AVILA
PLUMBING-Final 5/12/2022 No Access for Inspection JOSE AVILA
ELECTRICAL-Final 5/18/2022 Partial Inspection JOSE AVILA
HVAC-Final 5/18/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 5/18/2022 Approved JOSE AVILA
ELECTRICAL-Final 8/17/2022 No Access for Inspection JOSE AVILA
Final 8/17/2022 No Access for Inspection JOSE AVILA
Green Building Final 8/17/2022 No Access for Inspection JOSE AVILA
HVAC-Final 8/17/2022 No Access for Inspection JOSE AVILA
PLUMBING-Final 8/17/2022 No Access for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Not Ready JOSE AVILA
Service/Power Release 8/17/2022 No Access for Inspection JOSE AVILA
Smoke Detectors 8/17/2022 No Access for Inspection JOSE AVILA
Pre-Inspection 8/19/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 8/22/2022 Approved JOSE AVILA
Final 8/22/2022 OK to Issue CofO JOSE AVILA
Green Building Final 8/22/2022 Approved JOSE AVILA
HVAC-Final 8/22/2022 Approved JOSE AVILA
PLUMBING-Final 8/22/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Approved JOSE AVILA
Service/Power Release 8/22/2022 Approved JOSE AVILA
Smoke Detectors 8/22/2022 Approved JOSE AVILA