1816 S CARMONA AVE 90019
Certificate Information: 1816 S CARMONA AVE 90019
- Application / Permit
- 20010-10000-00454
- Plan Check / Job No.
- B20LA02700
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE.
- Permit Issued
- Issued on 2/1/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | GARO TELMI |
| Corrections Issued | 3/16/2020 | GARO TELMI |
| Quality Review Completed | 3/16/2020 | KEN GILL |
| Green Plans Picked Up | 10/16/2020 | APPLICANT |
| Plan Check Approved | 12/30/2020 | GARO TELMI |
| Issued | 2/1/2021 | APPLICANT |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| CofO in Progress | 8/24/2022 | JOSE AVILA |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2020 | ERIK BEASLEY |
| Highway dedication | Cleared | 6/25/2020 | ERIK BEASLEY |
| Permit | Cleared | 6/25/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/13/2020 | ERIK BEASLEY |
| Frnt yard landscape/Water mgmt | Cleared | 8/11/2020 | MAXFIELD VERMY |
| Green Code | Cleared | 10/13/2020 | DONALD CRICHLOW |
| Green Code | Cleared | 10/13/2020 | GARO TELMI |
| Hydrant and Access approval | Cleared | 11/10/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 12/2/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 12/18/2020 | ROSA SILVA |
Contact Information
| Contractor | Moving Forward Builders Inc; Lic. No.: 1072204-B | 3219 LIBERTY BLVD SOUTH GATE, CA 90280 |
| Engineer | Desai,, Anil Thakorbhai; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 2/10/2021 | Conditional Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/16/2021 | Conditional Approval | SCOTT FINNILA |
| Underground Mechanical | 2/16/2021 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/5/2021 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 7/21/2021 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 8/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/9/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Rough | 8/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 8/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 8/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 8/30/2021 | Conditional Approval | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 8/30/2021 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/14/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/14/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 9/14/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 9/14/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/14/2021 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 9/14/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/15/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 9/15/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 9/15/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/21/2021 | Corrections Issued | ROBERT VORHIS |
| BUILDING-Rough-Frame | 9/24/2021 | Approved | FREDDIE RIVERA |
| Insulation | 9/30/2021 | Not Ready for Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 9/30/2021 | Corrections Issued | ALAN MORELOS |
| Interior/Exterior Lathing | 10/5/2021 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 10/13/2021 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 10/13/2021 | Off-Hour Fees Due | |
| Insulation | 10/13/2021 | Approved | STUART CHAPMAN |
| Insulation | 10/13/2021 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 10/13/2021 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/13/2021 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 10/22/2021 | Approved | STUART CHAPMAN |
| Gas Test | 3/29/2022 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 3/29/2022 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Final | 3/29/2022 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 4/6/2022 | Corrections Issued | JOSE AVILA |
| Gas Test | 4/6/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 4/6/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 4/6/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 4/13/2022 | Corrections Issued | JOSE AVILA |
| Gas Test | 4/13/2022 | Approved | JOSE AVILA |
| HVAC-Final | 4/13/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 5/12/2022 | No Access for Inspection | JOSE AVILA |
| HVAC-Final | 5/12/2022 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Final | 5/12/2022 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 5/18/2022 | Partial Inspection | JOSE AVILA |
| HVAC-Final | 5/18/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 5/18/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 8/17/2022 | No Access for Inspection | JOSE AVILA |
| Final | 8/17/2022 | No Access for Inspection | JOSE AVILA |
| Green Building Final | 8/17/2022 | No Access for Inspection | JOSE AVILA |
| HVAC-Final | 8/17/2022 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Final | 8/17/2022 | No Access for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 8/17/2022 | No Access for Inspection | JOSE AVILA |
| Smoke Detectors | 8/17/2022 | No Access for Inspection | JOSE AVILA |
| Pre-Inspection | 8/19/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 8/22/2022 | Approved | JOSE AVILA |
| Final | 8/22/2022 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 8/22/2022 | Approved | JOSE AVILA |
| HVAC-Final | 8/22/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 8/22/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 8/22/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 8/22/2022 | Approved | JOSE AVILA |