1827-1827 1/2 S ORANGE DR 90019
Certificate Information: 1827-1827 1/2 S ORANGE DR 90019
- Application / Permit
- 20010-10000-00443
- Plan Check / Job No.
- B20LA02668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX AT FRONT WITH ATTACHED GARAGE. (1 OF 2)
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Current Status
- CofO Issued on 12/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Green Plans Picked Up | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | KEVIN MORALES |
| Corrections Issued | 3/6/2020 | KEVIN MORALES |
| Quality Review Completed | 3/8/2020 | YOUNG KIM |
| Applicant returned to address corrections | 9/29/2020 | KEVIN MORALES |
| Plan Check Approved | 11/20/2020 | KEVIN MORALES |
| Issued | 12/30/2020 | APPLICANT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| CofO in Progress | 12/9/2021 | STUART CHAPMAN |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
| CofO Issued | 12/15/2021 | DEROLD HAUFF |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2020 | CELINA MORENO |
| Permit | Cleared | 3/4/2020 | CELINA MORENO |
| Green Code | Cleared | 3/5/2020 | NEGAR NEJAD |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 3/6/2020 | ROBERT DUFF |
| Sewer availability | Cleared | 3/6/2020 | THOMAS LANG |
| Trees in Parkway | Cleared | 3/13/2020 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 3/17/2020 | RICHARD REASER |
| Low Impact Development | Cleared | 10/8/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/15/2020 | THOMAS LANG |
| Flood clearance | Cleared | 10/27/2020 | RAYMOND LAM |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Engineer | Pinzon,, Eduardo A; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/15/2021 | Approved | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 4/15/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/15/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 4/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/30/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Pre-Inspection | 5/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Partial Approval | RUBEN SALAS |
| Sewer | 6/3/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 6/11/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 6/17/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 6/17/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 6/18/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/23/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/23/2021 | Approved | KATHRYN BUTTERWORTH |
| FLOOD-Proofing Certificate | 6/23/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/23/2021 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 6/23/2021 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 6/25/2021 | Approved | BENEVA JACKSON |
| Special/Order Compliance | 6/25/2021 | Approved | BENEVA JACKSON |
| Insulation | 6/28/2021 | Approved | ALFREDO BALANDRA |
| Interior/Exterior Lathing | 6/28/2021 | Approved | ALFREDO BALANDRA |
| Insulation | 6/30/2021 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/30/2021 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 7/2/2021 | Not Ready for Inspection | ALFREDO BALANDRA |
| Deputy Wood Construction | 7/6/2021 | Partial Approval | RUBEN SALAS |
| Interior/Exterior Lathing | 7/6/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 10/6/2021 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 10/6/2021 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/6/2021 | Approved | LILIANA PORTILLO |
| Service/Power Release | 10/6/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Special/Order Compliance | 10/6/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 10/12/2021 | Approved | JUSTIN HAWLEY |
| Green Building Final | 10/12/2021 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 10/12/2021 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 10/12/2021 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 10/12/2021 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 11/17/2021 | Approved | JUSTIN HAWLEY |
| Final | 12/7/2021 | Partial Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Approved | STUART CHAPMAN |
| Final | 12/8/2021 | OK to Issue CofO | STUART CHAPMAN |