7812 S LA SALLE AVE 90047

Certificate Information: 7812 S LA SALLE AVE 90047

Application / Permit
20010-10000-00410
Plan Check / Job No.
B20LA02478
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1 story detached ADU
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 SAMUEL GONZALEZ
Corrections Issued 3/31/2020 SAMUEL GONZALEZ
Quality Review Completed 4/2/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 6/30/2020 APPLICANT
Applicant returned to address corrections 9/25/2020 SAMUEL GONZALEZ
Plan Check Approved 1/12/2021 SAMUEL GONZALEZ
Issued 1/27/2021 APPLICANT
Building Plans Picked Up 2/1/2021 APPLICANT
CofO in Progress 4/22/2022 FREDDIE RIVERA
CofO in Progress 4/22/2022 HORACE FULTZ
CofO Issued 4/25/2022 DEROLD HAUFF
Permit Finaled 4/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/14/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/15/2020 RENZ SORIANO
Sewer availability Cleared 4/15/2020 RENZ SORIANO
Green Code Cleared 6/29/2020 VIVIAN LAO
Low Impact Development Cleared 8/25/2020 ROBIN YAMADA
Construction near power lines Cleared 11/4/2020 OSCAR CASTRO
Roof/Waste drainage to street Cleared 11/24/2020 ROSA SILVA

Contact Information

Architect Muhammad,, Alfred H; Lic. No.: C18389 400 E COMPTON BLVD UNIT C      COMPTON, CA 90221
Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/26/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 4/16/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 5/11/2021 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 6/24/2021 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 6/24/2021 Not Ready for Inspection HORACE FULTZ
Green Building Rough 6/24/2021 Approved HORACE FULTZ
PLUMBING-Rough 6/24/2021 Corrections Issued HORACE FULTZ
Verify Sprinkler Sign Off 6/24/2021 Approved HORACE FULTZ
ELECTRICAL-Rough 6/30/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Conditional Approval FREDDIE RIVERA
HVAC-Rough 6/30/2021 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 6/30/2021 Approved FREDDIE RIVERA
Pre-Inspection 6/30/2021 Corrections Issued FREDDIE RIVERA
Wood Frame 6/30/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Not Ready for Inspection FREDDIE RIVERA
Insulation 7/14/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 7/14/2021 Conditional Approval FREDDIE RIVERA
Drywall Nailing 7/20/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/20/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/10/2021 Approved FREDDIE RIVERA
Final 11/10/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 11/10/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 11/10/2021 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 11/10/2021 Approved FREDDIE RIVERA
Final 12/7/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 12/7/2021 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 12/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Final 3/2/2022 OK to Issue CofO FREDDIE RIVERA
Green Building Final 3/2/2022 Approved FREDDIE RIVERA
Service/Power Release 3/2/2022 Approved FREDDIE RIVERA