5605 W BLACKWELDER ST 90016
Certificate Information: 5605 W BLACKWELDER ST 90016
- Application / Permit
- 20010-10000-00354
- Plan Check / Job No.
- B20LA02110
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED ACCESSORY DWELLING UNIT PER ORD.186481
- Permit Issued
- Issued on 7/2/2020
- Issuing Office
- Current Status
- CofO Issued on 5/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | AMIR DANAI |
| Corrections Issued | 2/19/2020 | AMIR DANAI |
| Quality Review Completed | 3/5/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 3/10/2020 | APPLICANT |
| Green Plans Picked Up | 5/11/2020 | APPLICANT |
| Plan Check Approved | 6/30/2020 | AMIR DANAI |
| Issued | 7/2/2020 | APPLICANT |
| CofO in Progress | 4/1/2021 | DAVID FEILER |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
| CofO Issued | 5/1/2021 | DEROLD HAUFF |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction within easement | Cleared | 4/25/2020 | RIDWAN HARDY |
| Address approval | Cleared | 5/4/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 5/7/2020 | RENZ SORIANO |
| Green Code | Cleared | 5/11/2020 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 6/1/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 6/20/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/30/2020 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/24/2020 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 8/28/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 10/7/2020 | Conditional Approval | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Approved | DONALD CRICHLOW |
| Green Building Rough | 10/7/2020 | Approved | DONALD CRICHLOW |
| Rough-Elec/Plmb/HVAC | 10/7/2020 | Conditional Approval | DONALD CRICHLOW |
| Verify Sprinkler Sign Off | 10/7/2020 | Approved | DONALD CRICHLOW |
| PLUMBING-Rough | 10/16/2020 | Approved | DAVID CHAN |
| Gas Test | 10/20/2020 | Approved | DAVID CHAN |
| Insulation | 10/20/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 10/29/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 10/29/2020 | Approved | DAVID CHAN |
| Gas Test | 11/5/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/5/2020 | Approved | DAVID CHAN |
| Underground Mechanical | 12/3/2020 | Partial Approval | DAVID CHAN |
| Underground Mechanical | 12/10/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 1/29/2021 | Partial Inspection | DAVID FEILER |
| HVAC-Final | 1/29/2021 | Partial Inspection | DAVID FEILER |
| PLUMBING-Final | 1/29/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 3/1/2021 | Approved | SCOTT FINNILA |
| Final | 3/1/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 3/1/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 3/1/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 3/1/2021 | Approved | SCOTT FINNILA |
| Service/Power Release | 3/1/2021 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 4/1/2021 | OK to Issue CofO | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 4/1/2021 | Approved | DAVID FEILER |
| Smoke Detectors | 4/1/2021 | Approved | DAVID FEILER |