4347 S WOODLAWN AVE 90011
Certificate Information: 4347 S WOODLAWN AVE 90011
- Application / Permit
- 20010-10000-00330
- Plan Check / Job No.
- B20LA01964
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 5-STORY, 33-UNIT TYPE IIIA, 100% AFFORDABLE W/ MANAGERS UNITS
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2022 | HERNAN ARREOLA |
| Plan Check Approved | 6/1/2022 | HERNAN ARREOLA |
| Issued | 11/2/2023 | APPLICANT |
| TCO Issued (Expire Date: 03-03-2026) | 9/4/2025 | ERNESTO CORRAL |
| CofO in Progress | 1/21/2026 | JAMES POWERS |
| Permit Finaled | 1/21/2026 | ERNESTO CORRAL |
| CofO Issued | 1/21/2026 | ERNESTO CORRAL |
| Permit Finaled | 1/21/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Highway dedication | Cleared | 11/18/2020 | RENZ SORIANO |
| Address approval | Cleared | 11/19/2020 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 11/19/2020 | ALBERT TAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2020 | RENZ SORIANO |
| Permit | Cleared | 11/19/2020 | RENZ SORIANO |
| Bicycle Parking | Cleared | 11/20/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 5/7/2021 | MATTHEW CRAIG |
| Community Plan Implem. Overlay | Cleared | 5/21/2021 | WALTER RAMIREZ |
| Building over 3-story or 36-ft | Cleared | 5/25/2021 | CALOSHA APPROVED |
| Community Plan Implem. Overlay | Cleared | 6/8/2021 | JOHN KIM |
| Trees in Parkway | Cleared | 6/8/2021 | JOHN KIM |
| Community Plan Implem. Overlay | Cleared | 6/9/2021 | EDUARDO HERMOSO |
| Sewer availability | Cleared | 7/23/2021 | RENZ SORIANO |
| Work Adjacent to Public Way | Cleared | 10/5/2021 | ARMEN SARKISIAN |
| Green Code | Cleared | 10/26/2021 | ARMEN JIVALAGIAN |
| Fire Marshall Fire Life Safety | Cleared | 1/26/2022 | MENOA AGHAJANI |
| Low Impact Development | Cleared | 2/10/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/14/2022 | AMAAN MALIK |
| DAS Clearance | Cleared | 3/18/2022 | ARMEN JIVALAGIAN |
| DCP conditions approval | Cleared | 4/20/2022 | MARITESS GO |
| Density Bonus 12.22.A.31 | Cleared | 4/20/2022 | MARITESS GO |
| Community Plan Implem. Overlay | Cleared | 5/25/2022 | RYAN LY |
| Frnt yard landscape/Water mgmt | Cleared | 5/25/2022 | RYAN LY |
| Miscellaneous | Cleared | 5/25/2022 | RYAN LY |
| Opn space landscape/Water mgmt | Cleared | 5/25/2022 | RYAN LY |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | H T A Construction & Development; Lic. No.: 1044038-B | 3646 LONG BEACH BLVD STE 107 LONG BEACH, CA 90807 |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 3/11/2024 | Approved | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 3/22/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Wood Construction | 5/3/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 6/3/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Partial Approval | JAMES POWERS |
| Wood Frame | 6/4/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 7/1/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 7/2/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 7/10/2024 | Partial Approval | JAMES POWERS |
| Insulation | 7/19/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 7/22/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Partial Approval | JAMES POWERS |
| Wood Frame | 7/22/2024 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 7/30/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Insulation | 7/30/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Wood Construction | 8/12/2024 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 9/12/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Partial Approval | JAMES POWERS |
| Wood Frame | 9/24/2024 | Partial Approval | JAMES POWERS |
| Wood Frame | 9/30/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 10/4/2024 | Partial Approval | JAMES POWERS |
| Insulation | 10/8/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/16/2024 | Partial Approval | JAMES POWERS |
| Insulation | 10/22/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 10/25/2024 | Partial Approval | LARRY ARNICK |
| Insulation | 10/28/2024 | Not Ready for Inspection | JAMES POWERS |
| Light Gage Steel Frame | 10/28/2024 | Partial Approval | JAMES POWERS |
| Insulation | 10/29/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 10/31/2024 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 11/1/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 11/1/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 11/4/2024 | Partial Approval | JAMES POWERS |
| Insulation | 11/6/2024 | Partial Approval | JAMES POWERS |
| Insulation | 11/14/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 11/19/2024 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 11/19/2024 | Not Ready for Inspection | LARRY ARNICK |
| Insulation | 11/20/2024 | Partial Approval | JAMES POWERS |
| Insulation | 11/21/2024 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 11/21/2024 | Not Ready for Inspection | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Not Ready for Inspection | LARRY ARNICK |
| Insulation | 11/22/2024 | Not Ready for Inspection | LARRY ARNICK |
| Insulation | 11/26/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 11/27/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 12/2/2024 | Partial Approval | JAMES POWERS |
| Wood Frame | 12/2/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 12/3/2024 | Partial Approval | JAMES POWERS |
| Insulation | 12/4/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 12/11/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 12/31/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 1/3/2025 | Partial Approval | JAMES POWERS |
| Wood Frame | 1/3/2025 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 1/28/2025 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 2/6/2025 | Partial Approval | JAMES POWERS |
| Wood Frame | 3/18/2025 | Not Ready for Inspection | JAMES POWERS |
| Green Building Final | 5/2/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 5/2/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Deputy Wood Construction | 5/22/2025 | Partial Approval | JAMES POWERS |
| Green Building Rough | 6/12/2025 | Approved | JAMES POWERS |
| Verify Rec and Parks Fee Memo | 6/12/2025 | Not Ready for Inspection | JAMES POWERS |
| Final | 6/16/2025 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 6/16/2025 | Approved | JAMES POWERS |
| Green Building Final | 6/16/2025 | Approved | JAMES POWERS |
| METHANE-Barrier | 6/16/2025 | Approved | JAMES POWERS |
| METHANE-Final | 6/16/2025 | Approved | JAMES POWERS |
| METHANE-Rough | 6/16/2025 | Approved | JAMES POWERS |
| METHANE-Subgrade | 6/16/2025 | Approved | JAMES POWERS |
| Reinforced Masonry Frame | 6/16/2025 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 6/16/2025 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/16/2025 | Approved | JAMES POWERS |
| Final | 6/20/2025 | Not Ready for Inspection | JAMES POWERS |
| Final | 8/1/2025 | Not Ready for Inspection | JAMES POWERS |
| Final | 9/11/2025 | Partial Approval | JAMES POWERS |
| Final | 1/13/2026 | Not Ready for Inspection | JAMES POWERS |
| Final | 1/21/2026 | OK to Issue CofO | JAMES POWERS |