4347 S WOODLAWN AVE 90011

Certificate Information: 4347 S WOODLAWN AVE 90011

Application / Permit
20010-10000-00330
Plan Check / Job No.
B20LA01964
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 5-STORY, 33-UNIT TYPE IIIA, 100% AFFORDABLE W/ MANAGERS UNITS
Permit Issued
Issued on 11/2/2023
Issuing Office
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2021 APPLICANT
Building Plans Picked Up 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/9/2022 HERNAN ARREOLA
Plan Check Approved 6/1/2022 HERNAN ARREOLA
Issued 11/2/2023 APPLICANT
TCO Issued (Expire Date: 03-03-2026) 9/4/2025 ERNESTO CORRAL
CofO in Progress 1/21/2026 JAMES POWERS
Permit Finaled 1/21/2026 ERNESTO CORRAL
CofO Issued 1/21/2026 ERNESTO CORRAL
Permit Finaled 1/21/2026 ERNESTO CORRAL

Permit Application Clearance Information

Highway dedication Cleared 11/18/2020 RENZ SORIANO
Address approval Cleared 11/19/2020 RENZ SORIANO
Community Plan Implem. Overlay Cleared 11/19/2020 ALBERT TAM
Eng Process Fee Ord 176,300 Cleared 11/19/2020 RENZ SORIANO
Permit Cleared 11/19/2020 RENZ SORIANO
Bicycle Parking Cleared 11/20/2020 ELAINE LEI
Hydrant and Access approval Cleared 5/7/2021 MATTHEW CRAIG
Community Plan Implem. Overlay Cleared 5/21/2021 WALTER RAMIREZ
Building over 3-story or 36-ft Cleared 5/25/2021 CALOSHA APPROVED
Community Plan Implem. Overlay Cleared 6/8/2021 JOHN KIM
Trees in Parkway Cleared 6/8/2021 JOHN KIM
Community Plan Implem. Overlay Cleared 6/9/2021 EDUARDO HERMOSO
Sewer availability Cleared 7/23/2021 RENZ SORIANO
Work Adjacent to Public Way Cleared 10/5/2021 ARMEN SARKISIAN
Green Code Cleared 10/26/2021 ARMEN JIVALAGIAN
Fire Marshall Fire Life Safety Cleared 1/26/2022 MENOA AGHAJANI
Low Impact Development Cleared 2/10/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/14/2022 AMAAN MALIK
DAS Clearance Cleared 3/18/2022 ARMEN JIVALAGIAN
DCP conditions approval Cleared 4/20/2022 MARITESS GO
Density Bonus 12.22.A.31 Cleared 4/20/2022 MARITESS GO
Community Plan Implem. Overlay Cleared 5/25/2022 RYAN LY
Frnt yard landscape/Water mgmt Cleared 5/25/2022 RYAN LY
Miscellaneous Cleared 5/25/2022 RYAN LY
Opn space landscape/Water mgmt Cleared 5/25/2022 RYAN LY

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor H T A Construction & Development; Lic. No.: 1044038-B 3646 LONG BEACH BLVD STE 107      LONG BEACH, CA 90807
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/11/2024 Not Ready for Inspection JAMES POWERS
Pre-Inspection 3/11/2024 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/20/2024 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/21/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/22/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 5/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 6/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval JAMES POWERS
Wood Frame 6/4/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 7/1/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/2/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/10/2024 Partial Approval JAMES POWERS
Insulation 7/19/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 7/22/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval JAMES POWERS
Wood Frame 7/22/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 7/30/2024 Not Ready for Inspection DANIEL VARNUM
Insulation 7/30/2024 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 8/12/2024 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 9/12/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Partial Approval JAMES POWERS
Wood Frame 9/24/2024 Partial Approval JAMES POWERS
Wood Frame 9/30/2024 Not Ready for Inspection JAMES POWERS
Insulation 10/4/2024 Partial Approval JAMES POWERS
Insulation 10/8/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/16/2024 Partial Approval JAMES POWERS
Insulation 10/22/2024 Not Ready for Inspection JAMES POWERS
Insulation 10/25/2024 Partial Approval LARRY ARNICK
Insulation 10/28/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/28/2024 Partial Approval JAMES POWERS
Insulation 10/29/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 11/1/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/1/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2024 Partial Approval JAMES POWERS
Insulation 11/6/2024 Partial Approval JAMES POWERS
Insulation 11/14/2024 Partial Approval RAFAEL ESPINOZA
Insulation 11/19/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 11/19/2024 Not Ready for Inspection LARRY ARNICK
Insulation 11/20/2024 Partial Approval JAMES POWERS
Insulation 11/21/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 11/21/2024 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Not Ready for Inspection LARRY ARNICK
Insulation 11/22/2024 Not Ready for Inspection LARRY ARNICK
Insulation 11/26/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 11/27/2024 Not Ready for Inspection JAMES POWERS
Insulation 12/2/2024 Partial Approval JAMES POWERS
Wood Frame 12/2/2024 Not Ready for Inspection JAMES POWERS
Insulation 12/3/2024 Partial Approval JAMES POWERS
Insulation 12/4/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/11/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/31/2024 Partial Approval JAMES POWERS
Drywall Nailing 1/3/2025 Partial Approval JAMES POWERS
Wood Frame 1/3/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 1/28/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/6/2025 Partial Approval JAMES POWERS
Wood Frame 3/18/2025 Not Ready for Inspection JAMES POWERS
Green Building Final 5/2/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 5/2/2025 Not Ready for Inspection JEROME BLACKWOOD
Deputy Wood Construction 5/22/2025 Partial Approval JAMES POWERS
Green Building Rough 6/12/2025 Approved JAMES POWERS
Verify Rec and Parks Fee Memo 6/12/2025 Not Ready for Inspection JAMES POWERS
Final 6/16/2025 OK for TCO JAMES POWERS
Footing/Foundation/Slab 6/16/2025 Approved JAMES POWERS
Green Building Final 6/16/2025 Approved JAMES POWERS
METHANE-Barrier 6/16/2025 Approved JAMES POWERS
METHANE-Final 6/16/2025 Approved JAMES POWERS
METHANE-Rough 6/16/2025 Approved JAMES POWERS
METHANE-Subgrade 6/16/2025 Approved JAMES POWERS
Reinforced Masonry Frame 6/16/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Approved JAMES POWERS
Smoke Detectors 6/16/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 6/16/2025 Approved JAMES POWERS
Final 6/20/2025 Not Ready for Inspection JAMES POWERS
Final 8/1/2025 Not Ready for Inspection JAMES POWERS
Final 9/11/2025 Partial Approval JAMES POWERS
Final 1/13/2026 Not Ready for Inspection JAMES POWERS
Final 1/21/2026 OK to Issue CofO JAMES POWERS