1290 E LAKE ST 90291

Certificate Information: 1290 E LAKE ST 90291

Application / Permit
20010-10000-00273
Plan Check / Job No.
B20LA01461
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW GARAGE AND SECOND STORY ADU
Permit Issued
Issued on 9/1/2020
Issuing Office
Current Status
CofO Issued on 2/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 CRYSTEL MAALOUF
Corrections Issued 2/24/2020 CRYSTEL MAALOUF
Building Plans Picked Up 3/4/2020 APPLICANT
Quality Review Completed 3/6/2020 BILL STUTSMAN
Green Plans Picked Up 7/16/2020 APPLICANT
Applicant returned to address corrections 8/19/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 8/20/2020 CRYSTEL MAALOUF
Plan Check Approved 9/1/2020 CRYSTEL MAALOUF
Issued 9/1/2020 APPLICANT
CofO in Progress 1/28/2022 DAVID FEILER
Permit Finaled 2/11/2022 DANIEL ORRANTE
CofO Issued 2/11/2022 DANIEL ORRANTE
Permit Finaled 2/11/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/9/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/9/2020 ELENA LOPEZ
Specific Plan Cleared 3/9/2020 COLLINS ALLAN
Construction near power lines Cleared 4/14/2020 RIDWAN HARDY
Construction within easement Cleared 4/14/2020 RIDWAN HARDY
Sewer availability Cleared 4/17/2020 CECILIO NAVARRO
Green Code Cleared 7/16/2020 CRYSTEL MAALOUF
Low Impact Development Cleared 8/4/2020 ROBIN YAMADA
Stormwater Pollution Mitigatn Cleared 8/4/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 8/6/2020 CECILIO NAVARRO
GPI Written Notices Cleared 8/19/2020 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 8/19/2020 CRYSTEL MAALOUF

Contact Information

Contractor Mega Builders Inc; Lic. No.: 898347-B 18375 VENTURA BLVD SUITE 520      TARZANA, CA 91356
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 10/13/2020 Not Ready for Inspection DAVID HEINE
Footing/Foundation/Slab 10/22/2020 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 10/27/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 10/28/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 1/26/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 1/26/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 1/26/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 2/3/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 2/3/2021 Approved JOHNNY MIRANDA
Green Building Rough 2/3/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 2/3/2021 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 2/3/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 3/1/2021 Approved JOHNNY MIRANDA
Green Building Rough 3/1/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/1/2021 Partial Approval JOHNNY MIRANDA
Insulation 3/9/2021 Corrections Issued JOHNNY MIRANDA
Insulation 3/11/2021 Approved JOHNNY MIRANDA
Drywall Nailing 3/15/2021 Approved JOHNNY MIRANDA
Shower Pan 4/7/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 4/12/2021 Approved JOHNNY MIRANDA
Final 10/12/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 10/12/2021 Approved JOHNNY MIRANDA
Green Building Final 10/12/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 10/12/2021 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 10/12/2021 Approved JOHNNY MIRANDA
Final 12/16/2021 Corrections Issued DAVID FEILER
Green Building Final 12/16/2021 No Access for Inspection DAVID FEILER
HVAC-Final 12/16/2021 No Access for Inspection DAVID FEILER
Service/Power Release 12/16/2021 No Access for Inspection DAVID FEILER
Final 12/20/2021 Corrections Issued DAVID FEILER
Green Building Final 12/20/2021 Not Ready for Inspection DAVID FEILER
Service/Power Release 12/20/2021 Not Ready for Inspection DAVID FEILER
Final 1/18/2022 Partial Inspection DAVID FEILER
Green Building Final 1/18/2022 Approved DAVID FEILER
Service/Power Release 1/18/2022 Partial Inspection DAVID FEILER
Final 1/25/2022 OK to Issue CofO DAVID FEILER
Service/Power Release 1/25/2022 Approved DAVID FEILER