305 S ANITA AVE 90049
Certificate Information: 305 S ANITA AVE 90049
- Application / Permit
- 20010-10000-00232
- Plan Check / Job No.
- B20LA01250
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story single family residence w/ basement and attached garage
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 2/24/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 3/9/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 3/12/2020 | APPLICANT |
| Applicant returned to address corrections | 5/4/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 6/10/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 6/22/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/15/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/27/2020 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 7/29/2020 | APPLICANT |
| Applicant returned to address corrections | 8/6/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/27/2020 | ARSALAN SHABESTARI |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 4/24/2023 | KEVIN SARGSYAN |
| CofO in Progress | 4/25/2023 | KEVIN SARGSYAN |
| Permit Finaled | 4/26/2023 | DANIEL ORRANTE |
| CofO Issued | 4/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/30/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 4/30/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 7/8/2020 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 7/29/2020 | VIVIAN LAO |
| Excavation more than 5-ft deep | Cleared | 8/12/2020 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 8/12/2020 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 8/12/2020 | ARSALAN SHABESTARI |
| Haul Route | Cleared | 8/12/2020 | ARSALAN SHABESTARI |
| Roof/Waste drainage to street | Cleared | 8/25/2020 | DINAH GARIN |
Contact Information
| Architect | Borukhim,, Behdad; Lic. No.: C33202 | 6404 WILSHIRE BLVD SUITE 1235 LOS ANGELES, CA 90048 |
| Contractor | Landmark Construction Group Inc; Lic. No.: 732270-B | 11628 SANTA MONICA BOULEVARD SUITE 206 LOS ANGELES, CA 90025 |
| Engineer | Eftekhari,, Hossein; Lic. No.: C50121 | 5945 SETTLER COURT ANAHEIM, CA 92807 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2020 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 12/15/2020 | Partial Approval | JOHN KIDWELL |
| Deputy Shotcrete | 12/21/2020 | Corrections Issued | ROBERT SHELLY |
| PLUMBING-Rough | 1/12/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/9/2021 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 3/5/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Conditional Approval | JOHN KIDWELL |
| PLUMBING-Rough | 6/1/2021 | Approved | JOHN KIDWELL |
| Pre-Gunite | 8/2/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 10/4/2021 | Corrections Issued | JOHN KIDWELL |
| Shower Pan | 10/12/2021 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 10/15/2021 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 11/3/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/21/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 12/21/2021 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/21/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/14/2022 | Approved | JUAN VALENZUELA |
| Insulation | 1/14/2022 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 1/24/2022 | Approved | JOHN KIDWELL |
| Masonry Wall/Backfill | 2/23/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/28/2022 | Partial Approval | KENNETH NAGLE |
| Underground Mechanical | 8/12/2022 | Partial Approval | JUAN VALENZUELA |
| Gas Test | 1/25/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 1/25/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Final | 2/6/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Final | 2/6/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/13/2023 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 2/23/2023 | Approved | KENNETH NAGLE |
| Final | 4/13/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 4/13/2023 | Approved | OGANES TARAKHCHYAN |
| Pool/Spa Cover | 4/13/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/13/2023 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 4/17/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Final | 4/24/2023 | OK to Issue CofO | KEVIN SARGSYAN |