1526 S COCHRAN AVE 90016
Certificate Information: 1526 S COCHRAN AVE 90016
- Application / Permit
- 20010-10000-00190
- Plan Check / Job No.
- B20LA00981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING 19'6"x36'6" (1,296.34 SF) AT REAR HALF OF THE PROPERTY
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Current Status
- CofO Issued on 7/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2020 | AMIR DANAI |
| Corrections Issued | 1/29/2020 | AMIR DANAI |
| Quality Review Completed | 2/5/2020 | JASON HEALEY |
| Building Plans Picked Up | 2/14/2020 | APPLICANT |
| Green Plans Picked Up | 2/19/2020 | APPLICANT |
| Plan Check Approved | 2/25/2020 | AMIR DANAI |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 7/7/2022 | JOSE AVILA |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
| CofO Issued | 7/9/2022 | DEROLD HAUFF |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | ERIK BEASLEY |
| Permit | Cleared | 2/19/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/19/2020 | ERIK BEASLEY |
| Green Code | Cleared | 2/21/2020 | AMIR DANAI |
| Hydrant and Access approval | Cleared | 2/21/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/21/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | ELAINE LEI |
Contact Information
| Contractor | Master Co; Lic. No.: 577769-B | 2426 WEST 8TH STREET #222 LOS ANGELES, CA 90057 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/13/2020 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 12/3/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 12/16/2020 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/4/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 5/4/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/4/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 5/4/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/18/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 5/18/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 5/18/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 5/18/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Wood Construction | 5/20/2021 | No Access for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/2/2021 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 6/2/2021 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 6/2/2021 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/2/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 8/2/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 8/2/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/17/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/17/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Partial Approval | ALAN MORELOS |
| Insulation | 9/9/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/9/2021 | Corrections Issued | ALAN MORELOS |
| Drywall Nailing | 9/22/2021 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 9/22/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/14/2021 | Approved | JUSTIN HAWLEY |
| Shower Pan | 10/14/2021 | Approved | JUSTIN HAWLEY |
| Final | 1/12/2022 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 1/12/2022 | Approved | JOSE AVILA |
| Green Building Final | 1/12/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 1/12/2022 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 1/12/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 1/21/2022 | Partial Approval | JOSE AVILA |
| Green Building Final | 1/21/2022 | Approved | JOSE AVILA |
| Service/Power Release | 1/21/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 1/21/2022 | Approved | JOSE AVILA |
| Final | 4/11/2022 | Corrections Issued | JOSE AVILA |
| Final | 4/18/2022 | Corrections Issued | JOSE AVILA |
| Final | 5/19/2022 | Not Ready for Inspection | JOSE AVILA |
| Final | 7/5/2022 | OK to Issue CofO | JOSE AVILA |