1526 S COCHRAN AVE 90016

Certificate Information: 1526 S COCHRAN AVE 90016

Application / Permit
20010-10000-00190
Plan Check / Job No.
B20LA00981
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING 19'6"x36'6" (1,296.34 SF) AT REAR HALF OF THE PROPERTY
Permit Issued
Issued on 9/2/2020
Issuing Office
Current Status
CofO Issued on 7/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/27/2020 AMIR DANAI
Corrections Issued 1/29/2020 AMIR DANAI
Quality Review Completed 2/5/2020 JASON HEALEY
Building Plans Picked Up 2/14/2020 APPLICANT
Green Plans Picked Up 2/19/2020 APPLICANT
Plan Check Approved 2/25/2020 AMIR DANAI
Issued 9/2/2020 APPLICANT
CofO in Progress 7/7/2022 JOSE AVILA
Permit Finaled 7/9/2022 DEROLD HAUFF
CofO Issued 7/9/2022 DEROLD HAUFF
Permit Finaled 7/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/19/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 2/19/2020 ERIK BEASLEY
Permit Cleared 2/19/2020 ERIK BEASLEY
Sewer availability Cleared 2/19/2020 ERIK BEASLEY
Green Code Cleared 2/21/2020 AMIR DANAI
Hydrant and Access approval Cleared 2/21/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/21/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/21/2020 ELAINE LEI

Contact Information

Contractor Master Co; Lic. No.: 577769-B 2426 WEST 8TH STREET #222      LOS ANGELES, CA 90057
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/13/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 12/3/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 12/16/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 5/4/2021 Approved STUART CHAPMAN
HVAC-Rough 5/4/2021 Approved STUART CHAPMAN
PLUMBING-Rough 5/4/2021 Not Ready for Inspection STUART CHAPMAN
Wood Frame 5/4/2021 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 5/18/2021 Corrections Issued STUART CHAPMAN
Green Building Rough 5/18/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/18/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 5/18/2021 Not Ready for Inspection STUART CHAPMAN
Deputy Wood Construction 5/20/2021 No Access for Inspection WILLIAM WREN
BUILDING-Rough-Frame 6/2/2021 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/2/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 6/2/2021 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 6/2/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 8/2/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 8/2/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 8/2/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/17/2021 Approved STUART CHAPMAN
Green Building Rough 8/17/2021 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Partial Approval ALAN MORELOS
Insulation 9/9/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 9/9/2021 Corrections Issued ALAN MORELOS
Drywall Nailing 9/22/2021 Approved ASHLEY THOMPSON
Green Building Rough 9/22/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 10/14/2021 Approved JUSTIN HAWLEY
Shower Pan 10/14/2021 Approved JUSTIN HAWLEY
Final 1/12/2022 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 1/12/2022 Approved JOSE AVILA
Green Building Final 1/12/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Approved JOSE AVILA
Service/Power Release 1/12/2022 Not Ready for Inspection JOSE AVILA
Smoke Detectors 1/12/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 1/21/2022 Partial Approval JOSE AVILA
Green Building Final 1/21/2022 Approved JOSE AVILA
Service/Power Release 1/21/2022 Approved JOSE AVILA
Smoke Detectors 1/21/2022 Approved JOSE AVILA
Final 4/11/2022 Corrections Issued JOSE AVILA
Final 4/18/2022 Corrections Issued JOSE AVILA
Final 5/19/2022 Not Ready for Inspection JOSE AVILA
Final 7/5/2022 OK to Issue CofO JOSE AVILA