Pre-Inspection
|
9/29/2022
|
Approved
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
10/25/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
11/7/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
12/22/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
12/22/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Piling/Pier/Caisson
|
12/22/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
12/23/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
12/23/2022
|
Partial Approval
|
JAMES POWERS
|
|
Piling/Pier/Caisson
|
12/23/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
12/27/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
12/30/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
12/30/2022
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
12/30/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/18/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
1/19/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
1/20/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
2/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
2/21/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Structural Steel Frame
|
2/21/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
2/21/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wall Anchors
|
2/21/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
2/21/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
2/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
3/1/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
3/1/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
3/1/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
3/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
3/7/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
3/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
3/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Pre-Inspection
|
3/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
3/20/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
3/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
3/23/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
3/23/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
3/23/2023
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
3/28/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
3/28/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
3/28/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
4/10/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
4/10/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/11/2023
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
4/11/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
4/11/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
4/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
4/19/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Pre-Inspection
|
4/19/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
4/19/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
4/19/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/1/2023
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
5/1/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
5/1/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/1/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
5/9/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/9/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
5/9/2023
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
5/15/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
5/15/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
5/15/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/22/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
5/22/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
5/22/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
5/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
5/31/2023
|
Conditional Approval
|
MARTIN TAVITIAN
|
|
Verify Sprinkler Sign Off
|
5/31/2023
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Wood Frame
|
5/31/2023
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
6/2/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
6/2/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/8/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
6/28/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
6/28/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/6/2023
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
7/11/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
7/14/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
7/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/21/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/25/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/26/2023
|
Partial Approval
|
ALAN MORELOS
|
|
Insulation
|
8/4/2023
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
8/7/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
8/7/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
8/8/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
8/8/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
8/8/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
8/16/2023
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
8/18/2023
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
8/21/2023
|
Partial Approval
|
JAMES POWERS
|
|
Structural Steel Frame
|
8/21/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
8/22/2023
|
Partial Approval
|
JAMES POWERS
|
|
Structural Steel Frame
|
8/22/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
8/29/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
8/29/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/1/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/1/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/6/2023
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
9/6/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/11/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
9/11/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
9/11/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
9/19/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/19/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/22/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/22/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/26/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/27/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/27/2023
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
10/11/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
10/31/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
10/31/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/31/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
10/31/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
11/6/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/8/2023
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
11/20/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Structural Steel Frame
|
11/20/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/29/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
12/15/2023
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
12/15/2023
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
1/25/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
2/2/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
2/21/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
2/29/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
3/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
3/22/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
4/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
4/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
5/7/2024
|
Partial Approval
|
JAMES POWERS
|
|
Grading Pre-Inspection
|
5/17/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
7/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
7/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
7/15/2024
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/22/2024
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
7/22/2024
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
7/25/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
8/1/2024
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
8/1/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
8/2/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
8/2/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
8/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
8/21/2024
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
10/16/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
10/16/2024
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
10/16/2024
|
Approved
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
10/16/2024
|
SGSOV Approved
|
JAMES POWERS
|
|
Smoke Detectors
|
10/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
10/16/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
10/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
10/18/2024
|
OK for TCO
|
JAMES POWERS
|
|
Smoke Detectors
|
10/18/2024
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
10/18/2024
|
Approved
|
JAMES POWERS
|
|
Wood Frame
|
10/18/2024
|
Approved
|
JAMES POWERS
|
|
Final
|
10/22/2024
|
OK for TCO
|
JAMES POWERS
|
|
Final
|
11/26/2024
|
OK for TCO
|
JAMES POWERS
|
|
Final
|
11/27/2024
|
OK for TCO
|
JAMES POWERS
|
|
Final
|
4/16/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
5/5/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/5/2025
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
5/5/2025
|
OK to Issue CofO
|
JAMES POWERS
|