3609 N LOCKE AVE 90032
Certificate Information: 3609 N LOCKE AVE 90032
- Application / Permit
- 20010-10000-00077
- Plan Check / Job No.
- B20LA00693
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER ORDINANCE. NFPA 13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 6/22/2023
- Issuing Office
- Metro
- Current Status
- Issued on 6/22/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | KEVIN MORALES |
| Corrections Issued | 3/26/2020 | KEVIN MORALES |
| Quality Review Completed | 4/1/2020 | STANLEY RAAP |
| Building Plans Picked Up | 4/8/2020 | APPLICANT |
| Green Plans Picked Up | 2/6/2023 | APPLICANT |
| Plan Check Approved | 3/7/2023 | KEVIN MORALES |
| Issued | 6/22/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2020 | JUAN ASHTON |
| Low Impact Development | Cleared | 10/5/2021 | SARAH YOUSSEF |
| Grading Pre-Inspection | Cleared | 9/8/2022 | KIRK LINKLATER |
| "D" conditions | Cleared | 9/9/2022 | MAXFIELD VERMY |
| "Q" conditions | Cleared | 9/9/2022 | MAXFIELD VERMY |
| ZI | Cleared | 9/9/2022 | MAXFIELD VERMY |
| Sewer availability | Cleared | 10/21/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 2/27/2023 | KURT CORRAL |
| GPI Written Notices | Cleared | 3/7/2023 | KEVIN MORALES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/8/2024 | Partial Inspection | LILIANA PORTILLO |
| Pre-Inspection | 5/31/2024 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/7/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/17/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/17/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 11/17/2025 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | RONNIE MEDINA |
| Insulation | 12/1/2025 | Approved | RONNIE MEDINA |