401-403 N MARTEL AVE 90036
Certificate Information: 401-403 N MARTEL AVE 90036
- Application / Permit
- 20010-10000-00073
- Plan Check / Job No.
- B20LA00680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY HOUSE WITH ATTACHED 1 CAR CARPORT AND 866 SQ FT ACCESSORY DWELLING UNIT ON THE SECOND STORY.
- Permit Issued
- Issued on 12/4/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | VARAND SARKISIAN |
| Corrections Issued | 2/10/2020 | VARAND SARKISIAN |
| Green Plans Picked Up | 2/11/2020 | APPLICANT |
| Quality Review Completed | 2/14/2020 | TIEN JEN WANG |
| Plan Check Approved | 11/10/2020 | VARAND SARKISIAN |
| Issued | 12/4/2020 | APPLICANT |
| Building Plans Picked Up | 12/4/2020 | APPLICANT |
| CofO in Progress | 2/4/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/17/2022 | DEROLD HAUFF |
| CofO Issued | 2/17/2022 | DEROLD HAUFF |
| Permit Finaled | 2/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 2/18/2020 | VIVIAN LAO |
| Address approval | Cleared | 3/18/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/18/2020 | GEORGE SUCHAND |
| Permit | Cleared | 3/18/2020 | JEANIE LAM |
| ZA Case | Cleared | 3/20/2020 | DANIEL CORONADO |
| Trees in Parkway | Cleared | 4/2/2020 | JOHN KIM |
| Address approval | Cleared | 9/11/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/6/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 10/7/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/8/2020 | JEANIE LAM |
| Hold | Cleared | 4/26/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28000 S WESTERN AVE UNIT 209 SAN PEDRO, CA 90732 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 12/8/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Methane Barrier | 12/9/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 12/9/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 12/9/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Sewer | 12/9/2020 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 12/9/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Methane Barrier | 12/10/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 5/5/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 7/7/2021 | Approved | RONALD KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 7/27/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 8/4/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Methane Barrier | 8/5/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Methane Barrier | 8/6/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 8/19/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 8/26/2021 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 10/5/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/12/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/12/2021 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 10/12/2021 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 10/12/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/14/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 10/14/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 10/14/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 10/14/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 11/2/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/2/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/4/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 11/4/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/4/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 11/8/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 11/8/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/18/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 11/18/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Grounding or Bonding | 1/12/2022 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/12/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/20/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 1/20/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Grounding or Bonding | 1/20/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 1/20/2022 | Approved | CHRIS CHRISTENSEN |
| Pool/Spa Cover | 1/20/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 1/26/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 1/26/2022 | Approved | ARTHUR SARGSYAN |
| Final | 2/2/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/2/2022 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 2/2/2022 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 2/2/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/2/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 2/3/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |