2806 S PALM GROVE AVE 90016

Certificate Information: 2806 S PALM GROVE AVE 90016

Application / Permit
20010-10000-00041
Plan Check / Job No.
B20LA00436
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 29' 10" X 28' 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 19' X 18' 2-CAR GARAGE IN REAR OF LOT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 GURUNATH NESARAJAH
Corrections Issued 2/9/2020 GURUNATH NESARAJAH
Quality Review Completed 2/11/2020 GUANG MIN TUNG
Building Plans Picked Up 2/21/2020 APPLICANT
Green Plans Picked Up 8/6/2020 APPLICANT
Plan Check Approved 1/22/2021 GURUNATH NESARAJAH
Issued 2/9/2021 APPLICANT
CofO in Progress 6/14/2022 STUART CHAPMAN
No Progress 9/22/2022 SCOTT FINNILA
CofO in Progress 11/4/2022 STUART CHAPMAN
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/28/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 2/28/2020 JUAN ASHTON
Sewer availability Cleared 2/28/2020 JUAN ASHTON
Trees in Parkway Cleared 3/13/2020 JOHN KIM
Hydrant and Access approval Cleared 4/22/2020 KURT CORRAL
Green Code Cleared 5/15/2020 KHEDER ALRAZAA
Low Impact Development Cleared 7/17/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/4/2020 ROSA SILVA
Permit Cleared 11/13/2020 RENZ SORIANO

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor Advanced Construction; Lic. No.: 801955-B 18841 PASADERO DRIVE      TARZANA, CA 91356
Engineer Hakemi,, Fahim; Lic. No.: S5160 26982 MARBELLA      MISSION VIEJO, CA 92691

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/18/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 3/3/2021 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 3/9/2021 Approved ROBERT VORHIS
Wood Frame 4/13/2021 Partial Approval STUART CHAPMAN
Wood Frame 5/10/2021 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 8/2/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 8/2/2021 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 8/2/2021 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 8/2/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 8/9/2021 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2021 Partial Approval STUART CHAPMAN
Green Building Rough 8/9/2021 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 8/9/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/11/2021 Approved STUART CHAPMAN
Green Building Rough 8/11/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 8/20/2021 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 8/20/2021 Approved CALEB MEISTER
Green Building Rough 8/24/2021 Approved STUART CHAPMAN
Insulation 8/24/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 9/1/2021 Approved STUART CHAPMAN
Drywall Nailing 9/7/2021 No Access for Inspection SABAS ALONSO
Interior/Exterior Lathing 9/7/2021 No Access for Inspection SABAS ALONSO
Drywall Nailing 9/10/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/10/2021 Approved STUART CHAPMAN
Sewer 1/21/2022 Conditional Approval ALFREDO BALANDRA
Verify Rec and Parks Fee Memo 1/21/2022 Partial Inspection ALFREDO BALANDRA
Final 2/24/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 2/24/2022 Approved STUART CHAPMAN
Green Building Final 2/24/2022 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 2/24/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 2/24/2022 Approved STUART CHAPMAN
Final 3/25/2022 Corrections Issued STUART CHAPMAN
Green Building Final 3/25/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 3/25/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 3/31/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 3/31/2022 Approved STUART CHAPMAN
PLUMBING-Final 3/31/2022 Approved STUART CHAPMAN
Final 4/4/2022 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 4/4/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 4/5/2022 Corrections Issued STUART CHAPMAN
Final 4/5/2022 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 4/5/2022 Not Ready for Inspection STUART CHAPMAN
Final 5/6/2022 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 5/6/2022 Not Ready for Inspection STUART CHAPMAN
Final 5/11/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 5/11/2022 Not Ready for Inspection STUART CHAPMAN
Final 5/18/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 5/18/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 6/14/2022 Approved STUART CHAPMAN
Final 6/14/2022 OK to Issue CofO STUART CHAPMAN
Service/Power Release 6/14/2022 Approved STUART CHAPMAN
Special/Order Compliance 9/22/2022 Corrections Issued SCOTT FINNILA
Special/Order Compliance 10/7/2022 Corrections Issued JOSE AVILA
Special/Order Compliance 10/13/2022 Not Ready for Inspection STUART CHAPMAN
Final 10/18/2022 Conditional Approval STUART CHAPMAN
Final 11/4/2022 OK to Issue CofO STUART CHAPMAN