4321 S HALLDALE AVE 90062
Certificate Information: 4321 S HALLDALE AVE 90062
- Application / Permit
- 20010-10000-00021
- Plan Check / Job No.
- B20LA00228
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'x 25' 1-STORY ADU that includes living room, kitchen, 2-bedrooms, and 1 bathroom.
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 8/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 1/29/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/29/2020 | JASON HEALEY |
| Green Plans Picked Up | 4/15/2020 | APPLICANT |
| Applicant returned to address corrections | 5/19/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/29/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 7/23/2021 | CRYSTEL MAALOUF |
| Issued | 8/3/2021 | APPLICANT |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| CofO in Progress | 8/9/2023 | SABAS ALONSO |
| Permit Finaled | 8/11/2023 | RONALD MYRICK |
| CofO Issued | 8/11/2023 | RONALD MYRICK |
| Permit Finaled | 8/11/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Green Code | Cleared | 4/9/2020 | CRYSTEL MAALOUF |
| Address approval | Cleared | 6/15/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 7/30/2020 | PAMELA TENEZA |
| Construction near power lines | Cleared | 4/20/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/30/2021 | ANDRES COVARRUBIAS |
| Stormwater Pollution Mitigatn | Cleared | 5/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/14/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Stewart,, Carl William; Lic. No.: C86681 | 8811 GENTLE WIND DR CORONA, CA 92883 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 9/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 9/3/2021 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 9/16/2021 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/16/2021 | Partial Approval | SABAS ALONSO |
| Deputy Drilled-In Anchors | 11/24/2021 | Conditional Approval | SABAS ALONSO |
| Green Building Rough | 12/2/2021 | Not Ready for Inspection | SABAS ALONSO |
| Pre-Inspection | 12/2/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 1/4/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Underground Mechanical | 1/4/2022 | Partial Approval | ADAM ESCOTO |
| PLUMBING-Rough | 1/6/2022 | Not Ready for Inspection | HORACE FULTZ |
| Sewer | 1/11/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Sewer | 1/13/2022 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/18/2022 | Approved | HORACE FULTZ |
| Sewer | 1/18/2022 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 1/21/2022 | Approved | SABAS ALONSO |
| Sewer | 1/21/2022 | Approved | SABAS ALONSO |
| Insulation | 2/9/2022 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 2/9/2022 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Corrections Issued | SABAS ALONSO |
| Deputy Wood Construction | 3/1/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Corrections Issued | HORACE FULTZ |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 3/29/2022 | Approved | SABAS ALONSO |
| Insulation | 3/29/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 3/29/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/21/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/21/2022 | Partial Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 4/29/2022 | Approved | SABAS ALONSO |
| Shower Pan | 5/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/6/2022 | Corrections Issued | HORACE FULTZ |
| Shower Pan | 6/6/2022 | Approved | HORACE FULTZ |
| HVAC-Rough | 7/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 8/5/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Final | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Final | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV No Gas | ANDREW BEELI |
| Service/Power Release | 9/2/2022 | Corrections Issued | ANDREW BEELI |
| Smoke Detectors | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | SABAS ALONSO |
| Final | 9/21/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/21/2022 | Approved | SABAS ALONSO |
| Service/Power Release | 9/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 9/21/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 10/19/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 3/21/2023 | Corrections Issued | STUART CHAPMAN |
| Service/Power Release | 3/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 5/9/2023 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 5/9/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/15/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 5/15/2023 | Not Required | SABAS ALONSO |
| Final | 5/23/2023 | Corrections Issued | SABAS ALONSO |
| Final | 8/8/2023 | OK to Issue CofO | SABAS ALONSO |