12324 W 25TH HELENA DR 90049
Certificate Information: 12324 W 25TH HELENA DR 90049
- Application / Permit
- 19047-30000-02174
- Plan Check / Job No.
- B19WL07264
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool
- Permit Issued
- Issued on 2/4/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | MANUEL GARCIA |
| Corrections Issued | 2/28/2020 | MANUEL GARCIA |
| Quality Review Completed | 3/6/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/3/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 10/14/2020 | MANUEL GARCIA |
| Green Plans Picked Up | 11/9/2020 | APPLICANT |
| Applicant returned to address corrections | 11/24/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/15/2020 | MANUEL GARCIA |
| Plan Check Approved | 1/12/2021 | MANUEL GARCIA |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Issued | 2/4/2021 | APPLICANT |
| CofO in Progress | 4/23/2024 | ARAM AVEDISIAN |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
| CofO Issued | 5/4/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 11/13/2020 | RICHARD REASER |
| Grading Pre-Inspection | Cleared | 1/12/2021 | MANUEL GARCIA |
Contact Information
| Architect | Barber,, Charles Timothy; Lic. No.: C29232 | 829 N HARPER AVENUE LOS ANGELES, CA 90046 |
| Contractor | Premier General Contractors Inc; Lic. No.: 638046-B | 1131 N GRANADA AVE ALHAMBRA, CA 91801 |
| Engineer | Ruan,, Federico R; Lic. No.: S6689 | 553 S OAK KNOLL AVE PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/14/2021 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 1/19/2022 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 2/25/2022 | Approved | JUAN VALENZUELA |
| Rough-Plumbing | 2/25/2022 | Partial Approval | JUAN VALENZUELA |
| Rough-Electrical | 4/20/2022 | Partial Approval | JUAN VALENZUELA |
| Rough-Plumbing | 4/20/2022 | Partial Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 8/24/2022 | Approved | JUAN VALENZUELA |
| Pool Piping | 8/24/2022 | Approved | JUAN VALENZUELA |
| Rough-Electrical | 8/24/2022 | Partial Approval | JUAN VALENZUELA |
| Rough-Plumbing | 8/24/2022 | Approved | JUAN VALENZUELA |
| Grounding or Bonding | 12/30/2022 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 9/18/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Enclosure/Fence | 9/25/2023 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 9/27/2023 | Approved | ARAM AVEDISIAN |
| Final | 10/12/2023 | Corrections Issued | ARAM AVEDISIAN |
| Pool/Spa Cover | 10/12/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| Final | 2/29/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 4/23/2024 | OK to Issue CofO | ARAM AVEDISIAN |