2500 N MANDEVILLE CANYON ROAD 90049

Certificate Information: 2500 N MANDEVILLE CANYON ROAD 90049

Application / Permit
19047-30000-02031
Plan Check / Job No.
B19WL06689
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool and spa
Permit Issued
Issued on 6/20/2020
Issuing Office
Current Status
CofO Issued on 9/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 MARJAN SHENASI
Corrections Issued 12/26/2019 MARJAN SHENASI
Quality Review Completed 1/10/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/20/2020 MARJAN SHENASI
Applicant returned to address corrections 5/22/2020 MARJAN SHENASI
Plan Check Approved 6/11/2020 MARJAN SHENASI
Issued 6/20/2020 APPLICANT
Building Plans Picked Up 6/22/2020 APPLICANT
CofO in Progress 8/20/2021 JUAN VALENZUELA
Permit Finaled 9/1/2021 KENNETH NAGLE
CofO Issued 9/1/2021 KENNETH NAGLE
Permit Finaled 9/1/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/13/2020 ANTHONY MAINEZ
Miscellaneous Cleared 1/22/2020 MARC WOERSCHING
Private street Cleared 1/22/2020 MARC WOERSCHING
Watercourse Cleared 1/28/2020 MAHELET GEBEYHU

Contact Information

Architect Al-Sayed,, Marwan; Lic. No.: C33865 11526 VICTORIA AVENUE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer Mills,, Garrett Ward; Lic. No.: S5271 553 S OAK KNOLL AVE      PASADENA, CA 91101
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Gladson,, Richard; Lic. No.: EG1758 1545 VICTORY BL      GLENDALE, CA 91201

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/29/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 7/8/2020 Partial Approval TIM CHRISTENSEN
FLOOD-Elevation Certificate 7/8/2020 Not Ready for Inspection TIM CHRISTENSEN
FLOOD-Proofing Certificate 9/15/2020 Not Ready for Inspection TIM CHRISTENSEN
Pre-Gunite 9/15/2020 Not Ready for Inspection TIM CHRISTENSEN
Pre-Gunite 9/30/2020 Corrections Issued TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/14/2020 Approved TIM CHRISTENSEN
Grounding or Bonding 10/14/2020 Approved TIM CHRISTENSEN
Pre-Gunite 10/14/2020 Approved TIM CHRISTENSEN
Rough-Plumbing 10/14/2020 Approved TIM CHRISTENSEN
Deputy Shotcrete 10/27/2020 Conditional Approval TIM CHRISTENSEN
Deputy Shotcrete 10/28/2020 Conditional Approval TIM CHRISTENSEN
Grounding or Bonding 1/28/2021 Not Ready for Inspection JOHN KIDWELL
Pool Piping 1/28/2021 Not Ready for Inspection JOHN KIDWELL
Grounding or Bonding 2/3/2021 Partial Approval JUAN VALENZUELA
Gas Piping or Gas Test 4/5/2021 Approved JUAN VALENZUELA
Grounding or Bonding 4/5/2021 Approved JUAN VALENZUELA
Enclosure/Fence 4/16/2021 Corrections Issued JUAN VALENZUELA
Enclosure/Fence 4/21/2021 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/21/2021 SGSOV Not Ready JUAN VALENZUELA
Final 6/22/2021 Corrections Issued JUAN VALENZUELA
Pool Equipment Noise Test 6/24/2021 No Result Entered STEVEN BELTRAN
Final 8/6/2021 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/6/2021 SGSOV Approved JUAN VALENZUELA
Final 8/13/2021 Not Ready for Inspection JOHN KIDWELL
Final 8/18/2021 OK to Issue CofO JUAN VALENZUELA