2814 N ROSCOMARE ROAD 90077
Certificate Information: 2814 N ROSCOMARE ROAD 90077
- Application / Permit
- 19047-30000-01938
- Plan Check / Job No.
- B19WL06383
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (n) pool and spa.
- Permit Issued
- Issued on 5/22/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Application Withdrawn | 11/15/2019 | APPLICANT |
| Re-Activate Applicaton | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | TARIK SAOUD |
| Corrections Issued | 11/30/2019 | TARIK SAOUD |
| Quality Review Completed | 12/11/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 4/1/2020 | APPLICANT |
| Plan Check Approved | 4/27/2020 | TARIK SAOUD |
| Issued | 5/22/2020 | LADBS |
| Building Plans Picked Up | 5/22/2020 | APPLICANT |
| CofO in Progress | 11/3/2021 | CHRISTOPHER WILSON |
| Permit Finaled | 11/24/2021 | DANIEL ORRANTE |
| CofO Issued | 11/24/2021 | DANIEL ORRANTE |
| Permit Finaled | 11/24/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 3/18/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 3/18/2020 | SARAH GOLDMAN |
| Specific Plan | Cleared | 3/18/2020 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2020 | DINAH GARIN |
| Sewer availability | Cleared | 4/17/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 4/27/2020 | TARIK SAOUD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul Darian; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 1836 PARNELL AVE 202 LOS ANGELES, CA 90025 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 10/30/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Grading Pre-Inspection | 11/2/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Gunite | 12/16/2020 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Rough-Electrical | 12/16/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 12/16/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Shotcrete | 12/22/2020 | Partial Approval | MATT KELLERMAN |
| Deputy Shotcrete | 12/23/2020 | Partial Approval | MATT KELLERMAN |
| Grounding or Bonding | 6/29/2021 | Approved | CHRISTOPHER WILSON |
| Enclosure/Fence | 8/19/2021 | Approved | CHRISTOPHER WILSON |
| Pool Equipment Noise Test | 8/25/2021 | Approved | RYAN TAGUINES |
| Excavation/Setback/Form/Re-Bar | 10/12/2021 | Approved | CHRISTOPHER WILSON |
| Final | 10/12/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Gunite | 10/12/2021 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Final | 10/25/2021 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Final | 10/29/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/29/2021 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 11/2/2021 | OK to Issue CofO | CHRISTOPHER WILSON |