726 W HOWARD ST 90292
Certificate Information: 726 W HOWARD ST 90292
- Application / Permit
- 19047-30000-01930
- Plan Check / Job No.
- B19WL06345
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool and spa
- Permit Issued
- Issued on 1/14/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | REZA HAGHIGHAT |
| Corrections Issued | 12/2/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 12/13/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/3/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 3/10/2020 | REZA HAGHIGHAT |
| Issued | 1/14/2021 | APPLICANT |
| Building Plans Picked Up | 1/15/2021 | APPLICANT |
| CofO in Progress | 4/20/2026 | DAKOTA LOW |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
| CofO Issued | 4/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Coastal Zone | Cleared | 1/17/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 1/17/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 1/17/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 1/17/2020 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2020 | ANTHONY MAINEZ |
| Work Adjacent to Public Way | Cleared | 3/9/2020 | ANTHONY MAINEZ |
Contact Information
| Contractor | Acker Resources; Lic. No.: 807114-B | 6068 W 82ND STREET LOS ANGELES, CA 90045 |
| Engineer | Adams,, Mark S; Lic. No.: C34257 | 9570 REO COURT DURHAM, CA 95938 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/26/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Pre-Gunite | 2/26/2021 | Corrections Issued | ENRIQUE MIRELES |
| Rough-Electrical | 2/26/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Mechanical | 2/26/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Plumbing | 2/26/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/5/2021 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 3/5/2021 | Approved | JUAN VALENZUELA |
| Rough-Electrical | 3/5/2021 | Partial Approval | JUAN VALENZUELA |
| Rough-Plumbing | 3/5/2021 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 10/15/2025 | Corrections Issued | WILBER ROSALES |
| Enclosure/Fence | 10/24/2025 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 10/30/2025 | Approved | JESUS RODRIGUEZ |
| Final | 3/4/2026 | Corrections Issued | DAKOTA LOW |
| Equipment Noise Level | 3/24/2026 | No Access for Inspection | EUSEBIO GUZMAN |
| Grounding or Bonding | 3/24/2026 | Not Ready for Inspection | DAKOTA LOW |
| Pool Equipment Noise Test | 3/24/2026 | No Access for Inspection | EUSEBIO GUZMAN |
| Pool Equipment Noise Test | 4/1/2026 | Approved | EUSEBIO GUZMAN |
| Grounding or Bonding | 4/3/2026 | Approved | DAKOTA LOW |
| Final | 4/14/2026 | Corrections Issued | DAKOTA LOW |
| Final | 4/17/2026 | OK to Issue CofO | DAKOTA LOW |