397 N FORDYCE ROAD 90049
Certificate Information: 397 N FORDYCE ROAD 90049
- Application / Permit
- 19047-30000-01709
- Plan Check / Job No.
- B19WL05613
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool/spa
- Permit Issued
- Issued on 11/18/2020
- Issuing Office
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 10/22/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 11/5/2019 | FELIX FIGUEROA |
| Applicant returned to address corrections | 12/5/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/25/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 3/6/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/1/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 7/27/2020 | APPLICANT |
| Applicant returned to address corrections | 8/3/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/18/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/22/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 11/17/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 11/18/2020 | APPLICANT |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| CofO in Progress | 3/4/2025 | CARLOS MATAMOROS |
| No Progress | 5/3/2025 | MICHAEL PELHAM |
| CofO in Progress | 5/3/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/11/2025 | RICHARD STEINBACH |
| CofO Issued | 6/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Norris Construction Company; Lic. No.: 379328-B | P O BOX 55786 VALENCIA, CA 91355 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Mccullum,, Eric William; Lic. No.: C68850 | 727 2ND ST STE 104 HERMOSA BEACH, CA 90254 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Partial Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 12/4/2023 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 12/4/2023 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/6/2023 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 12/6/2023 | Approved | CARLOS MATAMOROS |
| Pool Piping | 12/6/2023 | Approved | CARLOS MATAMOROS |
| Gunite | 1/2/2024 | Approved | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 7/30/2024 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 7/30/2024 | Approved | CARLOS MATAMOROS |
| Final | 1/23/2025 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Gunite | 1/23/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/3/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 2/3/2025 | Approved | CARLOS MATAMOROS |
| Final | 3/3/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| Special/Order Compliance | 5/3/2025 | Corrections Issued | MICHAEL PELHAM |