6510 W 5TH ST 90048
Certificate Information: 6510 W 5TH ST 90048
- Application / Permit
- 19047-30000-01693
- Plan Check / Job No.
- B19WL05558
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- new swimming pool/spa per standard plan #270
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Issued on 1/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | KAVIAN REFAHI |
| Corrections Issued | 10/22/2019 | KAVIAN REFAHI |
| Green Plans Picked Up | 10/25/2019 | APPLICANT |
| Quality Review Completed | 10/31/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/4/2019 | APPLICANT |
| Applicant returned to address corrections | 12/2/2019 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/8/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/18/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/23/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 4/16/2020 | KAVIAN REFAHI |
| Plan Check Approved | 4/21/2020 | KAVIAN REFAHI |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 12/11/2023 | MEL KHACHATOURIAN |
| Permit Finaled | 1/18/2024 | DANIEL ORRANTE |
| CofO Issued | 1/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction within easement | Cleared | 11/12/2019 | RIDWAN HARDY |
| CPC | Cleared | 11/27/2019 | ANNA VAN |
Contact Information
| Contractor | Mega Builders Inc; Lic. No.: 898347-B | 18375 VENTURA BLVD SUITE 520 TARZANA, CA 91356 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Plumbing | 8/21/2020 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/30/2020 | Approved | EVAN COOPER |
| Pre-Gunite | 9/30/2020 | Approved | EVAN COOPER |
| Pool/Spa Cover | 10/28/2020 | Not Ready for Inspection | EVAN COOPER |
| Final | 6/16/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Not Ready | EVAN COOPER |
| Pool Equipment Noise Test | 6/23/2022 | Conditional Approval | JUSTIN CURTIS |
| Final | 6/29/2023 | Corrections Issued | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | JEREMY TODD |
| Final | 9/21/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 12/12/2023 | OK to Issue CofO | MEL KHACHATOURIAN |