3933 N HAYVENHURST AVE 91436

Certificate Information: 3933 N HAYVENHURST AVE 91436

Application / Permit
19047-30000-01523
Plan Check / Job No.
B19WL05093
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) SWIMMING POOL & SPA AT REAR OF THE LOT. PER ENGINEERED DESIGN.
Permit Issued
Issued on 1/9/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2019 APPLICANT
Assigned to Plan Check Engineer 9/18/2019 REZA HAGHIGHAT
Corrections Issued 9/23/2019 REZA HAGHIGHAT
Quality Review Completed 10/4/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 10/4/2019 APPLICANT
Plan Check Approved 1/8/2020 REZA HAGHIGHAT
Issued 1/9/2020 LADBS
CofO in Progress 9/12/2020 RONALD COWAN
Permit Finaled 2/19/2021 RONALD MYRICK
CofO Issued 2/19/2021 RONALD MYRICK
Permit Finaled 2/19/2021 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/6/2020 REZA HAGHIGHAT

Contact Information

Contractor Pacific Blue Pools & Spas; Lic. No.: 565996-C53 13638 DONNYBROOK LANE      MOORPARK, CA 93021
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356
Geologist , ; Lic. No.: GEO2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Geologist Haenschke,, Eirik Francis; Lic. No.: EG1597 9616 GIERSON AVE      CHATSWORTH, CA 91311

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 3/10/2020 Corrections Issued RONALD COWAN
Pre-Gunite 3/19/2020 Approved RONALD COWAN
Deputy Shotcrete 3/25/2020 Approved RONALD COWAN
Deck 4/16/2020 Approved RONALD COWAN
Rough-Mechanical 4/22/2020 Approved RONALD COWAN
Enclosure/Fence 6/5/2020 Approved RONALD COWAN
Pool Equipment Noise Test 6/26/2020 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 8/28/2020 Not Ready for Inspection DAVID SCANTLIN
Final 8/28/2020 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/28/2020 SGSOV Not Ready DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 9/11/2020 Approved RONALD COWAN
Final 9/11/2020 OK to Issue CofO RONALD COWAN
SGSOV-Seismic Gas S/O Valve 9/11/2020 SGSOV Approved RONALD COWAN