215 N SALTAIR AVE 90049
Certificate Information: 215 N SALTAIR AVE 90049
- Application / Permit
- 19047-30000-01406
- Plan Check / Job No.
- B19WL04696
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ADD NEW SPA (5'-6" x 11') TO EXISTING SWIMMING POOL PER LA CITY STANDARD PLAN 270.
- Permit Issued
- Issued on 8/21/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2019 | SERGIO SILVA |
| Corrections Issued | 8/20/2019 | SERGIO SILVA |
| Issued | 8/21/2019 | LADBS |
| CofO in Progress | 9/5/2020 | CARLOS MATAMOROS |
| CofO Issued | 9/11/2020 | VINCENT COTTON |
| Permit Finaled | 9/11/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/20/2019 | SERGIO SILVA |
| ZA Case | Cleared | 8/20/2019 | SARAH GOLDMAN |
Contact Information
| Contractor | Cm Construction Inc; Lic. No.: 1030804-B | 9512 HILLHAVEN AVE TUJUNGA, CA 91042 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 1/3/2020 | Partial Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 1/16/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 1/24/2020 | Partial Approval | CARLOS MATAMOROS |
| Pre-Gunite | 2/20/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Pre-Gunite | 2/25/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 3/2/2020 | Approved | CARLOS MATAMOROS |
| Pool Piping | 3/2/2020 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 3/2/2020 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 6/17/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Enclosure/Fence | 6/26/2020 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/29/2020 | Approved | CARLOS MATAMOROS |
| Final | 7/29/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 7/29/2020 | SGSOV Approved | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 8/4/2020 | Approved | STEVEN BELTRAN |
| Final | 8/7/2020 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/13/2020 | Approved | CARLOS MATAMOROS |
| Final | 8/13/2020 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/19/2020 | Approved | CARLOS MATAMOROS |
| Final | 8/19/2020 | Partial Inspection | CARLOS MATAMOROS |