911 N TIONE ROAD 90077

Certificate Information: 911 N TIONE ROAD 90077

Application / Permit
19047-30000-01220
Plan Check / Job No.
B19WL04108
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool and spa within existing shell. See comments.
Permit Issued
Issued on 10/9/2019
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 2/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 8/9/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/16/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 8/27/2019 APPLICANT
Plan Check Approved 10/9/2019 VLADIMIR ARUTYUNYAN
Issued 10/9/2019 LADBS
CofO in Progress 4/16/2021 CHRISTOPHER WILSON
CofO Issued-Status Void 5/3/2021 VINCENT COTTON
Permit Finaled-Status Void 5/3/2021 VINCENT COTTON
Re-Activate Permit 7/2/2021 VINCENT COTTON
CofO Corrected-Status Void 7/12/2021 VINCENT COTTON
Permit Finaled-Status Void 7/12/2021 VINCENT COTTON
Re-Activate Permit 12/13/2022 DANIEL ORRANTE
Permit Finaled 2/21/2023 DANIEL ORRANTE
CofO Corrected 2/21/2023 DANIEL ORRANTE
Permit Finaled 2/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Los Angeles Pool Builders Inc; Lic. No.: 857866-C53 9018 BALBOA BLVD SUITE 353      NORTHRIDGE, CA 91325
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 10/25/2019 Conditional Approval ROBERT SHELLY
Deputy Shotcrete 10/28/2019 Partial Approval MATT KELLERMAN
Deputy Shotcrete 10/29/2019 Partial Approval MATT KELLERMAN
Deputy Shotcrete 10/30/2019 Partial Approval MATT KELLERMAN
Deputy Shotcrete 10/31/2019 Partial Approval MATT KELLERMAN
Deputy Shotcrete 11/1/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 11/5/2019 Partial Approval MATT KELLERMAN
Enclosure/Fence 12/18/2020 Corrections Issued THOMAS FINNILA
Enclosure/Fence 1/19/2021 Approved CHRISTOPHER WILSON
Final 2/12/2021 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 2/12/2021 SGSOV Approved CHRISTOPHER WILSON
Pool Equipment Noise Test 4/9/2021 Approved ROBERT CHAVEZ
Final 4/13/2021 Conditional Approval CHRISTOPHER WILSON