1927 N WILTON PL 90068

Certificate Information: 1927 N WILTON PL 90068

Application / Permit
19047-20002-00967
Plan Check / Job No.
B21VN05014
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
SUPPLEMENTAL TO PERMIT# 19047-20000-00967 TO ENLARGE THE SPA FROM IRREGULAR SHAPED 4'-11" x 9'-0" TO IRREGULAR SHAPE 6'-0 "x 9'-0" PER LA CITY STANDARD DETAIL#268 AND SPA DETAIL # 640-C
Permit Issued
Issued on 5/6/2021
Issuing Office
Current Status
CofO Issued on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2021 APPLICANT
Assigned to Plan Check Engineer 4/27/2021 SARKIS HARABEDIAN
Plan Check Approved 5/5/2021 SARKIS HARABEDIAN
Issued 5/6/2021 APPLICANT
Building Plans Picked Up 5/17/2021 APPLICANT
CofO in Progress 9/14/2022 STUART CHAPMAN
Permit Finaled 9/30/2022 DEROLD HAUFF
CofO Issued 9/30/2022 DEROLD HAUFF
Permit Finaled 9/30/2022 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 5/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Pre-Gunite 5/18/2021 Corrections Issued BRIAN SULLIVAN
Pool Piping 5/24/2021 Not Ready for Inspection BRIAN SULLIVAN
Pre-Gunite 5/24/2021 Not Ready for Inspection BRIAN SULLIVAN
Pool Piping 6/2/2021 Approved BRIAN SULLIVAN
Pre-Gunite 6/2/2021 Approved BRIAN SULLIVAN
Rough-Electrical 6/2/2021 Approved BRIAN SULLIVAN
Rough-Plumbing 6/2/2021 Approved BRIAN SULLIVAN
Pre-Inspection 10/29/2021 Approved JOSEPH MCGARRY
Enclosure/Fence 11/16/2021 Not Ready for Inspection JOSEPH MCGARRY
Pool Piping 11/16/2021 Approved JOSEPH MCGARRY
Deck 11/19/2021 Corrections Issued BRIAN SULLIVAN
Enclosure/Fence 11/19/2021 Corrections Issued BRIAN SULLIVAN
Pool Piping 11/19/2021 Approved BRIAN SULLIVAN
Deck 11/29/2021 Approved JOSEPH MCGARRY
Enclosure/Fence 12/21/2021 Approved BRIAN SULLIVAN
Final 6/30/2022 Corrections Issued BRIAN SULLIVAN
Final 9/12/2022 OK to Issue CofO STUART CHAPMAN