9844 N JUTLAND AVE 91325
Certificate Information: 9844 N JUTLAND AVE 91325
- Application / Permit
- 19047-20000-02202
- Plan Check / Job No.
- B19VN22828
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20' X 31' IRREGULAR SHAPED SWIMMING POOL WITH 10' X 10' SPA ALL WORK PER ENGINEERING AND STANDARD PLAN #270
- Permit Issued
- Issued on 11/30/2020
- Issuing Office
- Current Status
- CofO Issued on 8/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/22/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 1/28/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 11/12/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 11/30/2020 | APPLICANT |
| CofO in Progress | 7/28/2021 | MARK JOHNSON |
| Permit Finaled | 8/21/2021 | MICHAEL SMITH |
| CofO Issued | 8/21/2021 | MICHAEL SMITH |
| Permit Finaled | 8/21/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2020 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 8/13/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/13/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 10/29/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 11/12/2020 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | California Pools; Lic. No.: 185102-C53 | 901 CALLE AMANECER #115 SAN CLEMENTE, CA 92673 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 1/27/2021 | Corrections Issued | MARK JOHNSON |
| Pre-Gunite | 2/8/2021 | Approved | MARK JOHNSON |
| Deputy Shotcrete | 2/11/2021 | No Access for Inspection | MARK JOHNSON |
| Deck | 4/20/2021 | Approved | MARK JOHNSON |
| Grounding or Bonding | 4/20/2021 | Approved | MARK JOHNSON |
| Enclosure/Fence | 5/13/2021 | Approved | MARK JOHNSON |
| Equipment Noise Level | 6/7/2021 | Approved | FELIPE PENICHE |
| Final | 6/14/2021 | Corrections Issued | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | MARK JOHNSON |
| Final | 7/7/2021 | Corrections Issued | MARK JOHNSON |
| Final | 7/27/2021 | OK to Issue CofO | MARK JOHNSON |