940 W VENEZIA AVE 90291
Certificate Information: 940 W VENEZIA AVE 90291
- Application / Permit
- 19047-20000-02119
- Plan Check / Job No.
- B19VN21645
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New irregular 12' x 23'4" pool with a 8' x 8' spa per engineering.
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2019 | LUIS RINCON |
| Corrections Issued | 12/13/2019 | LUIS RINCON |
| Plan Check Approved | 1/24/2020 | HAYATO TSUCHIYA |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 4/12/2025 | DAVID FEILER |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/13/2019 | DAISY BENICIA |
| Miscellaneous | Cleared | 12/13/2019 | DAISY BENICIA |
| Miscellaneous | Cleared | 12/13/2019 | DAISY BENICIA |
| ZA Case | Cleared | 12/13/2019 | DAISY BENICIA |
| Coastal Zone | Cleared | 1/24/2020 | HERMINIGILDO AGUSTIN |
Contact Information
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 3/2/2020 | Approved | DAVID HEINE |
| Pool Piping | 3/2/2020 | Approved | DAVID HEINE |
| Pre-Gunite | 3/2/2020 | Approved | DAVID HEINE |
| Rough-Electrical | 3/2/2020 | Approved | DAVID HEINE |
| Rough-Plumbing | 3/2/2020 | Approved | DAVID HEINE |
| Deputy Shotcrete | 3/5/2020 | Partial Approval | DAVID HEINE |
| Grounding or Bonding | 3/16/2020 | Approved | JOHNNY MIRANDA |
| Enclosure/Fence | 5/18/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 5/26/2020 | Approved | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 5/26/2020 | Approved | DAVID HEINE |
| Final | 5/26/2020 | Conditional Approval | DAVID HEINE |
| PLUMBING-Final | 5/26/2020 | Approved | DAVID HEINE |
| Pool/Spa Cover | 5/26/2020 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 5/26/2020 | SGSOV Approved | DAVID HEINE |
| Pool Equipment Noise Test | 5/27/2020 | Approved | STEVEN BELTRAN |
| Final | 4/12/2025 | OK to Issue CofO | DAVID FEILER |