6100 N MAURY AVE 91367
Certificate Information: 6100 N MAURY AVE 91367
- Application / Permit
- 19047-20000-02001
- Plan Check / Job No.
- B19VN20587
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 23'-6" x 42'-4" POOL AND 8' X 10'-8" SPA ON PILES PER ENGINEERING
- Permit Issued
- Issued on 2/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | SELLA BENYAMIN |
| Corrections Issued | 12/10/2019 | SELLA BENYAMIN |
| Quality Review Completed | 12/11/2019 | STEVEN KIM |
| Building Plans Picked Up | 12/13/2019 | APPLICANT |
| Applicant returned to address corrections | 2/6/2020 | SELLA BENYAMIN |
| Plan Check Approved | 2/11/2020 | SELLA BENYAMIN |
| Issued | 2/11/2020 | LADBS |
| CofO in Progress | 8/18/2020 | TROY SANDERS |
| Permit Finaled | 9/9/2020 | JOHN JANSON |
| CofO Issued | 9/9/2020 | JOHN JANSON |
| Permit Finaled | 9/9/2020 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/11/2020 | Corrections Issued | JOHN KIDWELL |
| Piling/Pier/Caisson | 5/13/2020 | Partial Approval | JOHN KIDWELL |
| Deputy Other (see comments) | 5/15/2020 | Partial Approval | JOHN KIDWELL |
| Deputy Other (see comments) | 5/20/2020 | Partial Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 5/21/2020 | Partial Approval | JOHN KIDWELL |
| Deputy Other (see comments) | 5/22/2020 | Partial Approval | JOHN KIDWELL |
| Pre-Gunite | 6/3/2020 | Approved | DONALD SUNSERI |
| Deputy Shotcrete | 6/5/2020 | Partial Approval | JOHN KIDWELL |
| Enclosure/Fence | 7/16/2020 | Not Ready for Inspection | TROY SANDERS |
| Gas Piping or Gas Test | 7/23/2020 | Approved | TROY SANDERS |
| Grounding or Bonding | 7/23/2020 | Approved | TROY SANDERS |
| Rough-Electrical | 7/23/2020 | Approved | TROY SANDERS |
| Rough-Plumbing | 7/23/2020 | Approved | TROY SANDERS |
| Enclosure/Fence | 7/31/2020 | Not Ready for Inspection | TROY SANDERS |
| Enclosure/Fence | 8/4/2020 | Approved | TROY SANDERS |
| Pool Equipment Noise Test | 8/12/2020 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 8/12/2020 | SGSOV Not Ready | TROY SANDERS |
| ELECTRICAL-Final | 8/18/2020 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 8/18/2020 | Approved | TROY SANDERS |
| Final | 8/18/2020 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/18/2020 | SGSOV Approved | TROY SANDERS |