6100 N MAURY AVE 91367

Certificate Information: 6100 N MAURY AVE 91367

Application / Permit
19047-20000-02001
Plan Check / Job No.
B19VN20587
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 23'-6" x 42'-4" POOL AND 8' X 10'-8" SPA ON PILES PER ENGINEERING
Permit Issued
Issued on 2/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 SELLA BENYAMIN
Corrections Issued 12/10/2019 SELLA BENYAMIN
Quality Review Completed 12/11/2019 STEVEN KIM
Building Plans Picked Up 12/13/2019 APPLICANT
Applicant returned to address corrections 2/6/2020 SELLA BENYAMIN
Plan Check Approved 2/11/2020 SELLA BENYAMIN
Issued 2/11/2020 LADBS
CofO in Progress 8/18/2020 TROY SANDERS
Permit Finaled 9/9/2020 JOHN JANSON
CofO Issued 9/9/2020 JOHN JANSON
Permit Finaled 9/9/2020 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/11/2020 Corrections Issued JOHN KIDWELL
Piling/Pier/Caisson 5/13/2020 Partial Approval JOHN KIDWELL
Deputy Other (see comments) 5/15/2020 Partial Approval JOHN KIDWELL
Deputy Other (see comments) 5/20/2020 Partial Approval JOHN KIDWELL
Piling/Pier/Caisson 5/21/2020 Partial Approval JOHN KIDWELL
Deputy Other (see comments) 5/22/2020 Partial Approval JOHN KIDWELL
Pre-Gunite 6/3/2020 Approved DONALD SUNSERI
Deputy Shotcrete 6/5/2020 Partial Approval JOHN KIDWELL
Enclosure/Fence 7/16/2020 Not Ready for Inspection TROY SANDERS
Gas Piping or Gas Test 7/23/2020 Approved TROY SANDERS
Grounding or Bonding 7/23/2020 Approved TROY SANDERS
Rough-Electrical 7/23/2020 Approved TROY SANDERS
Rough-Plumbing 7/23/2020 Approved TROY SANDERS
Enclosure/Fence 7/31/2020 Not Ready for Inspection TROY SANDERS
Enclosure/Fence 8/4/2020 Approved TROY SANDERS
Pool Equipment Noise Test 8/12/2020 Approved ALFREDO FLORES
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Not Ready TROY SANDERS
ELECTRICAL-Final 8/18/2020 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 8/18/2020 Approved TROY SANDERS
Final 8/18/2020 OK to Issue CofO TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/18/2020 SGSOV Approved TROY SANDERS