11721 W CHAPARAL ST 90049

Certificate Information: 11721 W CHAPARAL ST 90049

Application / Permit
19047-20000-01921
Plan Check / Job No.
B19VN19615
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 47' X 73'6" IRREGULAR SHAPED SWIMMING POOL WITH 16'2" X 10' ATTACHED SPA, ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/5/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 RARES BODEA
Corrections Issued 11/23/2019 RARES BODEA
Quality Review Completed 12/13/2019 GUANG MIN TUNG
Building Plans Picked Up 12/17/2019 APPLICANT
Applicant returned to address corrections 1/10/2020 RARES BODEA
Plan Check Approved 1/27/2020 RARES BODEA
Issued 2/5/2020 LADBS
CofO in Progress 8/7/2024 CARLOS MATAMOROS
CofO Issued 8/14/2024 RICHARD STEINBACH
Permit Finaled 8/14/2024 RICHARD STEINBACH

Permit Application Clearance Information

Certificate of Compliance Cleared 1/7/2020 SARAH GOLDMAN
Tract Map conditions Cleared 1/7/2020 SARAH GOLDMAN
Tract Map conditions Cleared 1/7/2020 SARAH GOLDMAN
ZA Case Cleared 1/7/2020 SARAH GOLDMAN
Grading Pre-Inspection Cleared 1/27/2020 RARES BODEA

Contact Information

Contractor Saad Maher; Lic. No.: 627177-B 7641 TEXHOMA AVENUE      NORTHRIDGE, CA 91325
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 7/8/2020 Corrections Issued CARLOS MATAMOROS
Pre-Gunite 7/10/2020 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 7/15/2020 Conditional Approval CARLOS MATAMOROS
Deputy Shotcrete 7/16/2020 Conditional Approval CARLOS MATAMOROS
Deputy Shotcrete 7/17/2020 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/17/2020 Approved CARLOS MATAMOROS
Pool Piping 9/28/2020 Approved CARLOS MATAMOROS
Pre-Gunite 9/28/2020 Approved CARLOS MATAMOROS
Gas Piping or Gas Test 2/5/2021 Approved CARLOS MATAMOROS
Pool Piping 12/10/2021 Approved CARLOS MATAMOROS
Deputy Other (see comments) 3/20/2023 Conditional Approval CHRISTOPHER WILSON
Enclosure/Fence 5/7/2024 Not Ready for Inspection CARLOS MATAMOROS
Enclosure/Fence 5/14/2024 Approved CARLOS MATAMOROS
Final 7/12/2024 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Approved CARLOS MATAMOROS
ELECTRICAL-Final 8/6/2024 Approved CARLOS MATAMOROS
Final 8/6/2024 OK to Issue CofO CARLOS MATAMOROS